Citation : 2023 Latest Caselaw 1641 Raj
Judgement Date : 10 February, 2023
[2023/RJJD/004996]
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR S.B. Arbitration Application No. 21/2020
M/s Kamla Construction Company, Registered Partnership Firm 1-D-81, Jainarayan Vyas Colony, Tehsil And Dist. Bikaner.
----Petitioner Versus Rajasthan Rajya, District Collector, Bikaner.
----Respondent
For Petitioner(s) : Mr. Pradeep Choudhary. For Respondent(s) : Mr. Saransh Vij for Mr. Sudhir Tak, AAG.
HON'BLE MR. JUSTICE ARUN BHANSALI
Order
10/02/2023
This application under Section 10 and 11 of the Arbitration
and Conciliation Act, 1996 ('the Act') has been filed by the
applicant seeking reference of dispute between the parties to
Arbitrator.
It is inter alia indicated that the applicant was issued a work
order dated 1.1.1996 for manufacture and supply of 20 lakh first
class bricks and an agreement No.7/1995-1996 was executed in
this regard. As per the order and contract, the work was to
commence from 16.1.1996 and was to be concluded in 12 months
i.e. by 15.1.1997.
It is claimed that the applicant earnestly commenced
implementation of the work order and supplied 20 lakh bricks by
31.10.1996, however, another order dated 31.10.1996 was issued
to the applicant for supply of additional 20 lakh bricks and based
[2023/RJJD/004996] (2 of 6) [ARBAP-21/2020]
on the said quantity, it was expected that the contract would be
extended till 15.1.1998.
It is then indicated in the application that for various reasons
on account of rains etc. instead of 40 lakh bricks, the applicant
was required to manufacture 45.50 lakh bricks, however, the
applicant was not made full and final payment by the respondents
in terms of Clause-10(a) of the agreement. It is claimed that on
account of delayed payment, the applicant is entitled for interest
on the outstanding payment.
It is then indicated that in terms of Clause-19 of the
agreement, any question, difference or objection in connection
with the agreement was to be referred to a sole arbitrator to be
appointed as per the procedure prescribed, based on which, the
applicant issued a notice dated 5.3.2020, however, as the
respondents have not followed the procedure prescribed under
Clause-19, they have lost the right to appoint arbitrator and,
therefore, a sole arbitrator be appointed.
A reply to the application has been filed by the respondents
inter alia with the submissions that the petitioner did not complete
the work in the stipulated time period i.e. 31.3.1997 and there
was a delay of more than a year in execution of the work order
and, therefore, the petitioner is not entitled to any relief.
Further submissions have been made that the applicant was
lying in the state of slumber as the dispute pertains to the year
1998 and the present application has been filed in 2020 after
issuing notice. The claim made is ex-facie barred by limitation
even as per Article 137 of the Limitation Act, 1963 and, therefore,
the application deserves dismissal.
[2023/RJJD/004996] (3 of 6) [ARBAP-21/2020]
No rejoinder to the reply has been filed.
Learned counsel for the applicant made submissions that the
claim made by the applicant is genuine, wherein, the respondents
have not made payment of huge outstanding amount to the
applicant and not only this, even the final bill has not been
prepared and, therefore, the plea raised pertaining to the claim
being barred by limitation has no substance. It was emphasized
that as the final bill has not been prepared so far, it cannot be said
that the claim is barred by limitation so as to seek dismissal.
Further submissions have been made that it is well settled
that the issue pertaining to the limitation has to be considered by
the arbitrator and this Court while examining the matter under
Section 11 of the Act, cannot determine the aspect of limitation.
Reference in this regard has been made to judgments in
Duro Felguera. S.A. v. Gangavaram Port Limited: (2017) 9 SCC
729 and M/s. Jai Shiv Construction Company v. State of Rajasthan
& Ors.: S.B. Arbitration Application No.19/2019, decided on
21.7.2022.
Learned counsel for the respondent made submissions that
in case where the claim made is ex-facie time barred and it is
manifest that there is no subsisting dispute, the Court can refuse
to make the reference under Section 11 of the Act.
Reliance has been placed on judgment in Bharat Sanchar
Nigam Limited & Anr. v. Nortel Networks India Private Limited:
(2021) 5 SCC 738.
I have considered the submissions made by learned counsel
for the parties and have perused the material available on record.
[2023/RJJD/004996] (4 of 6) [ARBAP-21/2020]
From a bare perusal of the application it is apparent that the
applicant has himself claimed that the work pursuant to the work
order was completed by the applicant on 18.7.1998. For the
period subsequent to the year 1998, in para-5 of the application,
the applicant has made reference that grand-father and Uncle of
the applicant died in the year 2002 and 2010, respectively, the
office of the respondent being 400 kms off Bikaner, the applicant
could not contact the said office and under Clause-10(a) of the
agreement, it was the duty of the respondents to have make the
payment.
It was thereafter claimed that in the year 2015 applicant's
father / partner suffered paralysis, who was looking after the work
and on account of which, his memory became weak and he could
not indicate about the record of the klin and thereafter when
under Right to Information Act record was received in the year
2019, the applicant became aware of the outstanding from the
respondents and, therefore, the application was being made after
issuing of notice seeking appointment of arbitrator and failure of
the respondent to respond to the said notice.
From the above, it is ex-facie clear that between the year
1998 and 2020 i.e. the period when the work under the
agreement ended and the notice under Section 11 of the Act was
issued, there is no activity and/or attempt on part of the applicant
to seek payment of the alleged outstanding and whereafter for the
first time on issuing notice under Section 11 of the Act, besides
raising various claims, appointment of arbitrator has been sought.
The plea raised that as the final bill was not prepared by the
respondents, the cause of action did not arise cannot be
[2023/RJJD/004996] (5 of 6) [ARBAP-21/2020]
countenanced in the peculiar circumstances of the case, wherein,
for over 22 years, the applicant has chosen to remain silent
and/or did not seek enforcement of its alleged dues from the
respondent.
It is not in dispute that the limitation for the purpose of
money claim based on non-payment of amount under the
agreement is 3 years and in the present case, by no stretch of
imagination it can be said that the claim sought to be raised by
the applicant in the year 2020, is within limitation.
The very fact that the applicant in para-5 of the application
as well as in the notice, has made reference to certain deaths in
the family and the illness of the partner, necessarily leads to the
conclusion that the applicant himself being aware of the huge
delay somehow wants to explain the same, which aspect is of no
consequence insofar as the claim getting barred by limitation is
concerned.
It is true that Hon'ble Supreme Court in the case of Duro
Felguera. S.A. (supra) inter alia laid down that in an application
under Section 11 of the Act, the Court should only look into the
existence of the arbitration agreement before making the
reference, nothing more, nothing less. However, in the case of
Bharat Sanchar Nigam Ltd. (supra), Hon'ble Supreme Court after
inter alia referring to judgment in the case of Duro Felguera. S.A.
(supra), created a window inter alia holding that in rare and
exceptional cases where the claims are ex-facie time barred and it
is manifest that there is no subsisting dispute, the Court may
refuse to make the reference.
[2023/RJJD/004996] (6 of 6) [ARBAP-21/2020]
In view thereof, as the applicant has admittedly sought
reference of the dispute after 22 years, the claim is ex-facie
barred by limitation and there apparently was no subsisting
dispute between the parties.
So far as the judgment in the case of Jai Shiv Construction
Company (supra) is concerned, in the said case, the respondent
State wrote a letter to the applicant that for the balance payment,
the information was being sought from the earlier disputes and
that the pending bills would be cleared soon, based on which, the
Court came to the conclusion that the matter was pending
consideration at the hands of respondent and the dispute was not
resolved and, therefore, appointed the arbitrator.
Qua the said judgment, in SLP (Civil) Diary No.34268/2022,
Hon'ble Supreme Court on 14.12.2022, clarified that the question
of claim being barred by limitation can also effectively adjudicated
by the learned arbitrator.
No such letter and/or action on part of the respondent is
available in the present case so as to indicate that the dispute has
not been resolved/the same is subsisting, as such the said
judgment has no application to the facts of the present case.
In view of the above discussion, as the claims of the
applicant are ex-facie time barred and there is no subsisting
dispute, the application is liable to be dismissed and the same is,
therefore, dismissed.
(ARUN BHANSALI),J 7-Sumit/-
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!