Citation : 2021 Latest Caselaw 11716 Raj
Judgement Date : 28 July, 2021
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR S.B. Civil Misc. Appeal No. 581/2021
Azure Power Forty Three Private Limited, 5th Floor, Southern Park, D-Ii, Saket Palace, New Delhi-110017, Site Office Village Daudsar, Tehsil And District Bikaner
----Appellant Versus Javed Khan S/o Khaleel Ahmed, Ward No. 16, Jat Colony, Gharsana, Dis. Sriganganagar
----Respondent
For Appellant(s) : Mr. Narendra Thanvi.
Mr. Mahendra Thanvi.
For Respondent(s) : Mr. Muktesh Maheshwari.
Mr. Aidan Choudhary.
HON'BLE MR. JUSTICE ARUN BHANSALI
Judgment
28/07/2021
This appeal is directed against the order dated 29/5/2021
passed by Addl. District Judge No.4, Bikaner, whereby, the
application filed by the respondent-applicant-plaintiff under Order
XXXIX Rule 1 and 2 CPC has been allowed and temporary
injunction has been granted restraining the appellant-company
from executing any work in the land indicated in para 2 of the
application and to maintain status quo.
The suit was filed by the respondent-plaintiff under Section 6
of the Specific Relief Act, 1963 ('the Act, 1963') and for
permanent injunction inter alia with the submissions that plaintiff
has 1/6th share in the land ad measuring 18.94 hectares situated
in village Daudsar, Patwar Halka, Jamsar comprised in Khasra no.
(2 of 14) [CMA-581/2021]
215, 421, 458, 709/420, 710/417, 711/422 and 792/459. It was
claimed that on the said land, the plaintiff had his possession and
cultivation. It was alleged that defendant company is engaged in
developing solar project at village Daudsar and other places and
around the land of the plaintiff it is executing the work of solar
project, resulting in lands getting converted into non-agriculture
from agriculture.
It was alleged that the defendant on 18/3/2021 has taken
possession of the land; the plaintiff is deprived of cultivating the
land, putting it to use and developing the same. Indications were
made that in the land in question, Akram, Jalaludin, Noor Jahan,
Baby, Barkat Khan and Hazi Khan have share, which was joint and
undivided, however, the defendant company without partition
among the land holders by metes and bounds took possession
belonging to Akram, Jalaludin, Noor Jahan, Baby, Barkat Khan and
Hazi Khan and has started work of constructing solar plant. It was
also alleged that the defendant was working against the Rules and
Rajasthan Solar Energy Policy, 2020. The plaintiff was entitled to
return back of his land immediately. It was also indicated that
plaintiff is entitled to permanent injunction against the defendant
not to act against the parameters for protection of environment
and without taking other security measures. It was claimed that
issues of balance of convenience and irreparable injury are also in
his favour as he cannot be deprived of use of his land. It was
indicated that the suit has been filed within limitation as
possession was taken on 18/3/2021 and within six months the suit
has been filed.
(3 of 14) [CMA-581/2021]
Based on the above averments, it was prayed that
possession of the land be restored and permanent injunction be
granted.
Along with the suit, an application under Order XXXIX Rule 1
and 2 CPC was filed seeking temporary injunction during the
pendency of the suit. In the application after reiterating the
averments made in the plaint, it was prayed that till the decision
of the suit, without partition of the land by metes and bounds, the
respondent should not execute any work on the land.
The defendant-appellant filed an application under Order VII
Rule 11 CPC seeking rejection of the plaint. However, the said
application was rejected on 8/4/2021 against which a revision
petition is pending consideration before this Court.
A reply to the application under Order XXXIX Rule 1 and 2
CPC was filed denying the averments made in the application. It
was contended that the plaintiff-applicant never had possession of
the property and he has not been dispossessed at any point of
time, therefore, the suit and the application were liable to be
dismissed.
In additional pleas, it was claimed that the suit was barred
under Section 207 of the Rajasthan Tenancy Act, 1955 ('the Act,
1955') and Section 41 (h) of the Act, 1963 and on that count the
application was liable to be dismissed.
On facts, it was indicated that out of 18.94 Hectares of
agricultural land, Jalaludin, Hazi Khan, Barkat Khan, Noor Jahan,
Bhapia had 5/6th share and legal representatives of Chotu had
1/6th share. Bhapia gifted his 1/6th share to Barkat Khan and the
khatedars executed registered lease deeds executed between July,
(4 of 14) [CMA-581/2021]
2019 to February, 2020 for a period of 30 years in favour of
defendant company. It was claimed that possession of the entire
undivided 1/6th share of the land belonging to Barkat Khan was
handed over to the company on 15/8/2020 and for rest 1/6 th
share the lease deed was to be executed and since then the
defendant was in possession of the property. It was claimed that
the defendant has executed huge project for setting up solar
power plant including civil work etc. Along with reply large number
of documents emphasizing the fact that plaintiff was never in
possession of the suit property were filed and that the entire land
was/is in possession of the defendant and that in case any
injunction is granted, the defendant would suffer irreparable
injury, the plaintiff had no cause inasmuch as the suit itself was
not maintainable and balance of convenience was in its favour and
prayed that the application be dismissed.
The trial court after hearing the parties came to the
conclusion that the plaintiff claims 1/6 th share in the disputed
property and the company having registered lease deed qua 5/6 th
share claims possession of entire 18.94 hectares of land. The
plaintiff is khatedar of the land and from photographs and
documents it appears that on the disputed land including other
land, on which solar project of defendant company has been
established and working, wherein, the construction and boundary
wall work is over, and as such the company has claimed its work
etc. on entire suit land and other Khasras. Barkat Khan
transferred his 1/6th share to Amrit Pal Sandhu, who on 7/3/2021
transferred the same to the plaintiff and as to whether the
possession of the land was transferred on 15/8/2020 to the
(5 of 14) [CMA-581/2021]
company or the plaintiff was dispossessed on 18/3/2021 was a
matter of evidence and as the plaintiff was found owner of 1/6 th
share in the land and several issues raised in the suit requires
leading of evidence, no definite conclusion can be drawn at this
stage and as the plaintiff had share in the property, there was
prima facie case in his favour.
While considering the aspects of balance of convenience and
irreparable injury, the trial court came to the conclusion that the
balance of convenience was in restraining the company from
working and from maintaining status quo without there being any
partition by metes and bounds as in case there is any change in
the suit property, the purpose of filing the suit would come to and
end and the plaintiff would suffer more, which may not be
compensated in terms of money and consequently granted
temporary injunction, as noticed hereinbefore.
Feeling aggrieved, the present appeal has been filed.
Learned counsel for the appellant made vehement submissions
that from a bare reading of the plaint, it was apparent that the
plaintiff was never in possession of the suit property and the basic
requirement of Section 6 of the Act i.e. dispossession without
adopting due process of law has not even been alleged in the
plaint.
Submissions were made that despite specific case of the
appellant that the plaintiff was never in possession of the suit
property as claimed by him and sufficient material in this regard
was produced on record, the trial court failed to return any
finding, even prima facie that the plaintiff was in possession of the
suit property at any point of time.
(6 of 14) [CMA-581/2021]
Submissions were made that the lease deeds were executed
in favour of the appellant over a period of time and the appellant
has also executed huge work over the land in question when the
plaintiff purchased the land on 7/3/2021 and looking to the nature
of appellant's possession, the plaintiff could not have taken
possession of the property, the suit has been filed by claiming that
within 11 days i.e. on 18/3/2021 he has been dispossessed. The
possession on the face of it was only paper possession and for lack
of any proof with regard to taking possession/dispossession, and
trial court having failed to record any finding on this aspect, there
was apparently no prima facie case in favour of the plaintiff and,
therefore, no injunction could have been granted.
Submissions were made that order passed by the trial court
is absolutely vague inasmuch as the appellant has been restrained
from executing the work at the site, which has resulted in plaintiff
seeking to interfere in all kinds of activities being undertaken by
the company by making complaints with the police and revenue
authorities and the said authorities for no reason, based on the
vague order passed by the trial court, is interfering with the work
of the appellant company, resulting in huge day to day loss to the
company, which financial loss in a suit of present nature cannot be
compensated.
Submissions were made that the trial court did not deal with
the aspect of balance of convenience and irreparable injury and in
a cryptic manner has jumped to the conclusion on the said
aspects, which has resulted in grave injustice to the appellant, and
therefore also the order impugned deserves to be quashed and set
aside.
(7 of 14) [CMA-581/2021]
Submissions were made that the plaintiff has share of about
7.80 Acres of land and even presently more than that land at the
site is lying vacant, on which right of the plaintiff can be
protected. Submissions were also made that appellant is prepared
to keep the said portion vacant till the disposal of the suit.
During the course of submissions, based on the above
assertion regarding the availability of vacant land, on the direction
of the court, additional affidavit has been filed indicating that
about 7.80 Acres of unused land situated in various khasras is
available and that essentially the work pertaining to HT cabling,
which needs to cross through Khasra no. 421 & 711/422, its
testing and finishing work at PSS were left to be done. A map
indicating the available unused land has also been placed on
record.
It is also submitted that no proof whatsoever regarding
possession of the plaintiff was placed on record except for the
copy of Jamabandi and sale deed in favour of the plaintiff.
Learned counsel for the respondent vehemently contested
the submissions. It was submitted that the land in question i.e.
1/6th share was transferred by Barkat Khan to one Amrit Pal
Sandhu on 20/7/2020 and said Amrit Pal Sandhu transferred the
said 1/6th share to the plaintiff by registered sale deed dated
7/3/2021, the plaintiff came in possession of the land, however on
18/3/2021 he has been dispossessed from the land in question
and, therefore, the plaintiff was forced to file suit under Section 6
of the Act for restoration of his possession.
Submissions have been made that plea raised regarding the
suit being barred under Section 207 of the Rajasthan Tenancy Act
(8 of 14) [CMA-581/2021]
and the fact that plaintiff allegedly was not in possession over the
suit property were incorrect and the trial court has rejected the
application under Order VII Rule 11 CPC. Submissions have been
made that admittedly the appellant only has right in 5/6 th portion
of the land, which is of joint khatedari of several persons including
the plaintiff and qua 1/6 th share it has no right and as such the
appellant is not entitled to any relief from this Court.
Submissions have been made that as the respondent-plaintiff
has been dispossessed from the land in question and the
appellant-company is proceeding with changing the nature of the
entire land, the trial court was justified in granting injunction.
Submissions have also been made that once the issue of prima
facie case was decided in favour of the plaintiff, the finding on
issues pertaining to balance of convenience and irreparable injury
as recorded by the trial court, cannot be faulted inasmuch as once
the plaintiff has ownership over 1/6 th share in the property, he
cannot be dispossessed of the same without due process of law
and till such time the suit is decided, the suit property is required
to be protected.
Submissions were also made that at best the trial court may
be directed to expedite the decision on the suit and the order
passed by the trial court does not call for any interference and the
appeal deserves to be dismissed.
Under the directions of the court, the respondent-plaintiff
has also filed an additional affidavit and has claimed that he was
handed over possession of land in Khasra no. 421 only. A map
showing the portion claimed to be in possession of the plaintiff
before alleged dispossession has also been placed on record.
(9 of 14) [CMA-581/2021]
I have considered the submissions made by leaned counsel
for the parties and have perused the material available on record
along with the additional affidavits as filed under the directions of
the Court.
The fundamental aspect relevant at the stage of application
under Order XXXIX Rule 1 and 2 CPC is regarding the right of the
plaintiff in the suit property. It is an admitted case of the appellant
company also that they have lease deeds qua 5/6 th share in the
land ad measuring 18.94 hectares. The appellant company has
also not indicated as under what right, it could remain in
possession of the entire land including 1/6 th share belonging to the
plaintiff.
However, as the nature of the suit is such, wherein, the
plaintiff has alleged dispossession without due process of law from
a portion of the land, the above aspect, presently, in view of the
appellant's claim being in possession of the entire land irrespective
of having lease deed qua 5/6th share in the land, is not of much
relevance as it is well settled that in a suit under Section 6 of the
Act, the issue of title is irrelevant.
Large amount of pictures, which have been produced on
record, show permanent and temporary constructions at the site
and not only this, in fact the appellant company relying on a
'Mauka Fard' dated 29/5/2020, wherein, the Patwari Jamsar has
made identification/demarcation, claims to be in possession of in
all as much as 795 hectares of land including the suit land i.e.
18.94 hectares of land, as such the fact that on 7.3.2021 when
the plaintiff purchased the land, it prima facie cannot be believed
that he was unaware of the fact of appellant's huge presence at
(10 of 14) [CMA-581/2021]
the site and, therefore, the claim made by the plaintiff, though
missing in the pleadings before the trial court, but by way of
additional affidavit pursuant to the directions of the Court, that he
was handed over possession of land specifically in Khasra no. 421,
cannot be believed.
The submissions made that as there was no partition, the
plaintiff has right in the entire land ad measuring 18.94 hectares
cannot be countenanced beyond a point inasmuch as similarly, the
appellant company also would have bonafide claim in the entire
land having lease deeds in its favour qua 5/6 th portion of the land
ad measuring 18.94 hectares.
In the above circumstances, the fact regarding possession of
the plaintiff and his alleged dispossession, would require
adjudication by the court during trial, once the parties lead
evidence on the said aspect as the same is the core question to be
decided in the suit and presently based on the material available
on record, this Court would not hazard recording a finding on the
said aspect.
In these circumstances, the interest of the parties to the suit
have to be protected during the pendency of the suit and as such
the fact that the trial court found a prima facie case in favour of
the plaintiff, essentially on account of his title and claim of
possession, cannot be faulted, despite the fact that the suit is
under Section 6 of the Act.
Finding a prima facie case in favour of the plaintiff is not the
end of the matter as the court is then required to record finding
on balance of convenience and irreparable injury. The trial court,
despite the fact that there was lot of material produced by the
(11 of 14) [CMA-581/2021]
appellant company indicating the status of the land in question
and the fact that it had raised huge construction and had invested
huge funds, did not advert to the said aspect, though had
specifically noticed the fact that the company had executed
construction work and constructed boundary wall. Non
consideration of the material available on the said aspect and
jumping to the conclusion regarding balance of convenience and
irreparable injury by the trial court cannot be approved. Not only
this, the trial court then went to pass the following order:
"&vkns'k& 20- vr% izkFkhZ dk mDr vLFkk;h fu'ks/kkKk dk izkFkZuk i= fo:) vizkFkhZ Lohdkj fd;k tkdj bl vk"k; dh vLFkk;h fu'ks/kkKk tkjh dh tkrh gS fd rk&QSlyk ewy okn vizkFkhZ dEiuh izkFkZuk i= dh pj.k la[;k nks esa of.kZr Hkwfe ftlesa izkFkhZ dk [email protected] fgLlk gS] esa dksbZ dk;Z u djs o ekeyk gktk esa ;Fkkor~ fLFkfr cuk;s j[ksaA"
(emphasis supplied)
By the said order, the court ordered that on the land
indicated in para 2 of the plaint i.e. entire 18.94 hectares of land
in which the plaintiff had 1/6th share, no work should be executed
and that status quo be maintained.
Passing of above order, when admittedly over the part of the
land ad measuring 18.94 hectares, the appellant company had
constructed its power plant and was in the process of completing
the same, ordering for stopping of entire work cannot in any
manner be justified or approved inasmuch as, as noticed
hereinbefore, 5/6th share in the said land is on lease with the
appellant company.
The events subsequent to passing of the order, which have
been placed on record by both the parties reflect the consequence
(12 of 14) [CMA-581/2021]
of the said order, wherein, entire work of the appellant has been
sought to be put on hold by the revenue authorities with the aid of
police authorities seeking to implement the order passed by the
trial court.
Besides the fact that interference by the police and revenue
authorities for purportedly implementing an injunction, in which
proceedings they are not parties, cannot be appreciated, passing
of a blanket order without considering its implications, cannot be
sustained.
As the appellant has undertaken huge construction work and
invested huge funds, in case it is not permitted to
continue/complete its work, the same necessarily would result in
irreparable injury to the appellant and in those circumstances, it
cannot be said that the balance of convenience lies in favour of
the plaintiff alone. However, it also cannot be said that the plaintiff
is not entitled to any protection.
From the additional affidavits, which have been produced on
record, while the plaintiff has claimed his entire so called
possession in Khasra no. 421, which aspect, looking to the
existing construction over the said Khasra, has already been found
doubtful hereinbefore, the appellant has indicated vacant land ad
measuring 7.80 Acre in the map (Annex.2) filed along with
additional affidavit, which is connected by road as well and have
undertaken not to use the aforesaid 7.8 hectares unused land and
to keep the same intact.
Though learned counsel for the respondent-plaintiff disputed
the fact that the appellant company requires or was in possession
of the portion of Khasra No. 421, as indicated in the map and
(13 of 14) [CMA-581/2021]
made submissions that there was lot of temporary construction by
placing removable iron shelters, the said aspect cannot be
determined at this stage.
In over all circumstances of the case, the interest of justice
would be served in case the appellant-company is directed to
maintain status quo pertaining to the land ad measuring 7.80 Acre
as indicated as 'unused' by them in map (Annex.2) filed with the
additional affidavit and to undertake that in case any finding is
returned by the trial court that the plaintiff was in possession/in
possession of any specific portion of land, and orders for delivery
of possession of the said portion, they would deliver vacant
possession of the said portion to the plaintiff.
Consequently, the appeal is partly allowed. The order passed
by the trial court dated 29/5/2021 is set aside to the extent the
appellant company has been prohibited from undertaking any
work on the land indicated in para 2 of the application for
temporary injunction. Instead, it is directed that the appellant-
company shall maintain status quo pertaining to the land ad
measuring 7.80 Acres indicated as 'unused' by it in the map
(Annex.2) filed with the additional affidavit and it would be
required of the appellant to file an undertaking before the trial
court within three days that in case any finding is returned by the
trial court in the suit that the plaintiff was in possession/in
possession of any specific portion of land and the court orders for
delivery of possession of the said portion, it would deliver vacant
possession of the said portion to the plaintiff. The order for
maintaining status quo passed by the trial court shall also be
understood in the above context only.
(14 of 14) [CMA-581/2021]
Looking to the nature of the dispute, it is expected of the
trial court to proceed with the matter with utmost expedition.
No order as to costs.
(ARUN BHANSALI),J
baweja/-
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!