Citation : 2025 Latest Caselaw 1035 P&H
Judgement Date : 17 January, 2025
Neutral Citation No:=2025:PHHC:006983
RSA-4949--2019 (O&M) -1-
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
109
1. RSA
RSA-4949-2019 (O&M)
Shivjot Developers and Builders Ltd. .... Appellant
Versus
Sarup Singh .... Respondent
2. RSA
RSA-3938-2019 (O&M)
Shivjot Developers and Builders Ltd. .... Appellant
Versus
Sarup Singh .... Respondent
Date of Decision: 17.01.2025
CORAM: HON'BLE MS. JUSTICE NIDHI GUPTA
Present: - Mr.. Munish Kumar Garg, Advocate for the appellant.
NIDHI GUPTA, J. (ORAL)
1. The plaintiff is in second appeal before this Court laying
challenge to the judgment and decree dated 17.8.2015 passed by the
learnedTrial dTrial Court whereby decree for specific performance was declined,
but refund of earnest ea money was ordered; and judgment and decree dated
5.3.2019 passed by the ld.
l 1st Appellate Court, whereby refund of earnest
money was set aside;
aside and thus praying for decretal of the suit in toto.
2. By way of this common judgment the 02 aforementioned
appeals are being disposed of, as both appeals have arisen out of common
impugned judgments of both the Courts below dated 17.08.2015 (trial
Court) and 05.03.2019 (1st Appellate Court) and similar facts are involved
therein. For brevity, the facts are being extracted from RSA RSA-4949-2019.
1 of 11
Neutral Citation No:=2025:PHHC:006983
RSA-4949--2019 (O&M) -2-
3. The parties shall hereinafter be referred to as per their status
before the learned trial Court i.e. the appellant is being referred to as the
plaintiff whereas the respondent as defendant.
4. Brief facts of the case are that the plaintiff had filed a suit for
joint possession as owner by way of specific performance of agreement to
sell dated 03.08.2005 and 19.09.2005 regarding the suit land measuring
16 kanals-4¾ 4¾ marlas as described in the head note of the plaint; And suit
for permanent injunction restraining the defendant, its agent servants and
representative from selling, mortgaging, transferring alienating in any
manner the land as described in the second head note of the plaint; And
directing ng the defendant to execute the sale deed in favour of the plaintiff
or his nominee for Rs.17,97,65,600/ Rs.17,97,65,600/- after the adjustment of
Rs.23,96,000/ given as earnest money to the defendant. The plaintiff had Rs.23,96,000/-
exhibited his readiness and willingness to perform hhis part of contract.
5. The facts as set out in the plaint are that the plaintiff and
defendant entered into agreement on 03.008.2005 05 for sale of joint land
measuring 16 kanals k nals 4¾ marlas as fully described in the head note of the
plaint situated in the revenue estate of village Aujla Hadhbast No 182,
Tehsil Kharar Distt. SAS Nagar. The rate as settled between plaintiff and
the defendant initially was ₹93,50,000 93,50,000 per acre. In total six sale deeds
were agreed to be executed executed with regard to this land. It was agreed between
the parties that plaintiff would obtain the requisite permission from
PUDA/Town Planner Department and for the purpose Defendant would
furnish a consent deed in favour of plaintiff, for enabling plaintiff to apply
to PUDA/Town Planner Department for obtaining requisite permission
2 of 11
Neutral Citation No:=2025:PHHC:006983
RSA-4949--2019 (O&M) -3-
with respect to this land for building an infrastructure with respect to
developing residential colony. A total amount of ₹ 23,96,000/- was paid
by plaintiff towards the earnest money.
mo The total land agreed to be sold
was equally divided into six parts in order to affect six sale deeds at an
interval of four months each. Subsequently a fresh agreement dated
19.9.2005 05 was executed between defendant and plaintiff through which,
the basic sic terms and conditions as incorporated in the earlier agreement to
sell dated 3.8.2005 3.8. 05 were retained. However, substitution in the agreement
dated 19.9.2005 19.9. 05 were made and the rate of land was mutually agreed at
₹88,50,000 88,50,000 per acre, as it came to notice tthat hat this land agreed to be sold
through earlier agreement to sell dated 3.8.
3.8.2005, 05, was not within the
Municipal Limit of Municipal Council, Kharar. The date for effecting the
first registered sale deed would be within a period of four months, from
the date the Govt. issues necessary notification for bringing the land
within the Municipal of Municipal Council, Kharar. The rest of the terms
and conditions of earlier agreement to sell dated 3.8.
3.8.2005 05 were kept
intact. The substituted/amended agreement to sell da dated 3.8.2005 05 bears the
signature of the defendant as well as the signature oon behalf of plaintiff
and other marginal witnesses. The notification was issued by the Govt. of
Punjab on 20.2.2006.
20.2. Plaintiff on the basis of 'consent deed' furnished by
the defendant applied to Chief Town Planner lanner Govt. of Punjab for
obtaining required technical clearance of the building plans. Along with
the said application, plaintiff also appended the letter of consent which
had been prepared as per Section ection (2) (a) of the Punjab Apartment and
Property Regulation Regulation Act 1995 for a total 58 kanals 7 marlas of land. But
3 of 11
Neutral Citation No:=2025:PHHC:006983
RSA-4949--2019 (O&M) -4-
in actual defendant had not handed over the physical possession of the suit
land. Baldev dev Singh who is also a co-share sharerr has already executed and
registered sale deed measuring 8 Kanal in favour of plaintiff on 25.5.
25.5.2006
vide vasika No 845 with respect to his exclusive holding, after receiving
the full sale consideration money. The actual physical possession has also
been handed over to plaintiff by Baldev Singh with respect to his land
holding on execution of the registered sale deed by said Baldev Singh in
favour of plaintiff. Earlier there were various correspondence between the
defendant and plaintiff. Keeping all these correspondences in abeyance
and in view of the fact that sufficient time has already lost after the
issuance of the notification by the Govt. of Punjab on 20.2.
20.2.2006 06 through
which the land agreed to be sold by the defendant, in favour of plaintiff
has come within the municipal limits of Municipal Council, Kharar, Distt.
Mohali. Plaintiff in order to assert its bonafide called upon the defendant
that he is ready to execute the sale deed in its favour regarding the
remaining land. Plaintiff further asserted tthat hat it is ready with the entire
sale consideration money and is willing to execute the registered sale deed
for the remaining land. Plaintiff has neither ever intended to prolong the
execution of the registered sale deed in its favour any further, nor it iiss
ever interested in any delay and time-consuming consuming litigations in court of
law, in the larger interest of itself, as well as the defendant. The plaintiff
intends to build up the requisite infrastructure on the land. Plaintiff has
already suffered enormous loss loss and damages for the undue delay in
execution of registered sale deed in its favour. The plaintiff has served a
legal notice dated 17.5.2007 17.5. 07 upon the defendant for the purpose of
4 of 11
Neutral Citation No:=2025:PHHC:006983
RSA-4949--2019 (O&M) -5-
execution the registered sale deed on 4.7.2007 in favour of plaintiff. The
plaintiff also remained present in the office of Sub Registrar Tehsil
Complex on 20.6.2007 20 and 20.2.2008.
2008. It is pleaded that the plaintiff has
been throughout ready and willing and even now ready and willing to
perform his part of contract, but the contract has failed only because of
fault on the part of the defendants.
defendants. With these pleadings, the suit was
filed.
6. Upon notice, defendant/respondent respondent herein had put in
appearance and resisted the suit of the plaintiff on various grounds.
7. The plaintiff iff had filed replication reiterating the assertions
made in the plaint.
8. On the basis of the pleadings of the parties, following issues
were framed by the learned trial Court: -
"1. Whether the plaintiff is entitled for permanent injunction as prayed for for? OPP
2. Whether her the plaintiff is entitled for joint possession as owner by way of specific performance of the agreement to sell dated 03.08.2005 and 19.09 19.09.2005 2005 in the suit land as prayed for OPP 2a. Whether plaintiff company has always remained ready and willing to perform their part of contract? OPP
3. Whether the suit is not maintainable in the present form? OPD
4. Whether the suit is bad for delay and laches as prayed for? OPD
5. Whether the plaintiff is estopped stopped by his act and conduct to file the present suit? OPD
3. Relief."
9. On the basis of oral and documentary evidence adduced by
the parties, the learned trial Court decided issue No Nos.1, 2 and 2A in
5 of 11
Neutral Citation No:=2025:PHHC:006983
RSA-4949--2019 (O&M) -6-
favour of the plaintiff and against the defendant; and issues No. 3 to 5
were not pressed during the course of arguments and as such those
issues were decided against the defendant and in favour of the plaintiff.
However,, the learned trial Court decreed th the suit of the plaintiff in
alternative for refund of earnest/advance money to the tune of
Rs.23,96,000/ with proportionate costs Rs.23,96,000/- costs, while relief of specific
performance and permanent injunction was denied. The learned trial
Court also granted the plaintiff pre-institution, institution, pendente lite and future
interest @ 6% on the said amount from the date of its advance till
realization.
10. The said judgment and decree dated 17.08.2015 of the
learned trial Court was challenged by both the parties i.e. plaintiff and
thee defendant by way of two separate appeals before the learned
Additional District Judge, SAS Nagar (Mohali) bearing Civil Appeal
No. RT-318/21.09.201 318/21.09.2015/18.08.2016 /18.08.2016 filed by the defendant defendant; and Civil
Appeal No. RT-271/24.09.2015/27.07.2016 RT 15/27.07.2016 filed by the appellant; and
vide common judgment and decree dated 05.03.2019, the appeal filed by
the defendant was allowed and the appeal filed by the plaintiff was
dismissed while setting aside the relief of recovery of earnest money to
the plaintiff. Hence, the present present second appeal appeals.
11. Learned counsel for the appellant appellant-plaintiff, inter alia,
submits that both the agreements dated 3.8.2005 and 19.9.2005 have
been duly proven on record. Even readiness and willingness on part of
the plaintiff to perform the contract was proven before the learned trial
court. Despite this the learned lower Appellate Court has erred in
6 of 11
Neutral Citation No:=2025:PHHC:006983
RSA-4949--2019 (O&M) -7-
drawing an adverse inference against the plaintiff as it is clear from the
record that the plaintiff had appeared to execute the sale deed and had
therefore, fore, exhibited his readiness and willingness to perform the
contract. Moreover, the plaintiff was happy with the refund of earnest
money as granted to it by the learned trial Court. However, the learned
lower Appellate Court has set aside the money decree in favour of the
plaintiff only on the ground that the plaintiff had failed to demonstrate
his readiness and willingness to perform his part of contract and the
same is contrary to the evidence on record. In holding as above, the
learned lower Appellate Court Court has failed to appreciate that the plaintiff
had also sent a notice to the defendant to come to the Tehsil Office and
it is the defendant who had failed to put in appearance. Accordingly, it is
it prayed that the judgment of the learned 1st Appellate Court be set
aside.
12. No other argument is raised on behalf of the appellant.
13. I have heard learned counsel for the appellant and perused
the case file in great detail.
14. The learned trial court vide judgment and decree dated
17.8.2015 had denied the relief of specific performance and permanent
injunction to the plaintiff. The reasoning in this regard is contained in
para 19 of the trial court judgment dated 17.8.2015 17.8.2015, to the effect that
DW2 Director of the plaintiff company had deposed that the plaintiff
company was running short of funds because of which sale deed could
not be executed. It was further found that the contract between the
parties could not be concluded because of default and breach committed
7 of 11
Neutral Citation No:=2025:PHHC:006983
RSA-4949--2019 (O&M) -8-
by plaintiff company. However,, as payment of earnest money was found
to have been made, the suit was decreed in the alternative for refund of
earnest/advance /advance money of ₹23,96,000/-- along with pre-institution,
pendente lite and future interest at the rate of 6% on the said amount.
15. In appeal, vide the impugned judgment and decree dated
05.03.2019 the learned lower Appellate Court has dismissed the
plaintiff's suit holding that the plaintiff was not entitled to recovery of
the earnest money as he had failed to prove his readiness and
willingness to perform his part of contract, despite the fact that
defendant had sent a notice to the plaintiff to come present in the Tehsil
Office on 24.07.2006.
24.0 It was found that on 24.7.2006, the plaintiff did
not turn up in the office of the Sub-Regis Sub egistrar, whereas the defendant
appeared in the Tehsil and got marked his presence through Affidavit
Ex. D-4;; and further held that from Ex. D1 to D3 it was clear that the
plaintiff was not ready and willing to perform his part of the contract.
Learned Appellate Court further returned the finding that there was no
evidence by plaintiff to show that he was having sufficient amount to get
the sale deed executed. Moreover, refund of earnest money was declined
on account of a definite recital in the agreement in question to the effect
that failure to execute the sale deed would automatically entail
cancellation and forfeiture of earnest money. The relevant findings of
the learned Ist Appellate Court are contained in para para-Nos. 17 and 18 of
the impugned impugned judgment and Decree dated 5.3.2019, and the same are
reproduced as under:-
under:
"17. Now the question is whether the respondent was ready and willing to perform its part of the contract or not.
8 of 11
Neutral Citation No:=2025:PHHC:006983
RSA-4949--2019 (O&M) -9-
It is settled principle of law that mere filing of suit does not prove the readiness of a party to perform his part of the contract but readiness and willingness is to be inferred by the Court through the act and conduct of a party as well as other surrounding circumstances. In order to prove his readiness and willingness, ss, the respondent has merely placed on record affidavits Ex.P11/1 and Ex.P12/1 sworn by the representatives of respondent before the Executive Magistrate on 20.06.2007 and 22.02.2008 respectively. In this regard, a perusal of record shows that the appellaappellant had issued a legal notice dated 22.06.2006 Ex.D1 calling upon the respondent to get the sale deed executed from him as per the terms and conditions of agreement dated 03.08.2005. In reply to above legal notice, the respondent sent a legal notice Ex.D2 whereinherein it was averred that in addition to agreement dated 03.08.2005, a new agreement dated 19.09.2005 was executed between the parties and as per above agreement, the appellant agreed to sell his land to respondent at the rate of ₹88,50,000/ ₹88,50,000/- per acre. In the above legal notice, it was also mentioned that the parties also agreed that the appellant will execute first sale deed in favour of the respondent after four months from the date of issuance of notification by the government regarding the addition of the land of appellant in the limits of municipal council, Kharar. In the above legal notice, it was also mentioned by the respondent that the government has already issued notice qua land in dispute on 20.02.2006 in respect of the land measuring 2 Kanal 14 marlas. The appellant sent a rejoinder dated 12.07.2006 Ex.D3 to the respondent wherein it was stated that he has received additional amount of ₹3,96,000/ ₹3,96,000/- which was to be adjusted in the first sale deed whereas the remaining earnest money of ₹20 lacs was to be adjusted in the last sale deed since there was no such condition in the agreement. The appellant also stated that the total price of land measuring 2 kanal - 14 marla comes out to be ₹30,05,285/- out of which ₹3,96,000/- have already been received by him as additional amount and he is ready to execute the sale deed after receiving 26,04,000/- from the respondent. He also stated that he is in dire need of money for getting the sale deed executed from the person persons with whom he has entered into an agreement to sell for purchasing land and under these circumstances, without admitting the execution of agreement dated 19.09.2005, he is ready to sell his land to
9 of 11
Neutral Citation No:=2025:PHHC:006983
RSA-4949--2019 (O&M) -10-
respondent at the rate of ₹88,50,000/ ₹88,50,000/- per acre. In the above bove notice, the appellant also requested the respondent to come present in the Tehsil Comlpex, Kharar on 24.07.2006 alongwith balance sale consideration for execution and registration of first sale deed and it was also mentioned in the above notice that iin case, the respondent failed to come present in the above office on 24.07.2006, agreement dated 03.08.2005 and 19.09.2005 shall stand cancelled and earnest money will be forfeited. Thereafter, on 24.7.2006, the respondent did not turn up in the office of the Sub Registrar, Kharar whereas the appellant appeared in the above office and got marked his presence through affidavit Ex.D4. From documents Ex.D1 to Ex.D3, it becomes clear that respondent was not ready and willing to perform his part of the contract. He has not produced any evidence on record to establish that he was having sufficient amount to get the sale deed executed from the appellant. On the other hand, the appellant has examined DW2 Jaiteg Singh, who was Director of respondent company in the year ar 2005 and through whom the suit was filed by the respondent in the year 2008. Above witness clearly stated that after the execution of agreement to sell in question, the sale deed could not be executed because there was slump in market and respondent com company had no money. The statement of above witness clearly shows that the respondent company was not having sufficient funds to get the sale deed executed.
18. The respondent got presence of its representative marked in the office of the Executive Magistra Magistrate through affidavit Ex.P11/1 on 20.06.2007 and on 20.02.2008 through affidavit Ex.P12/1. As respondent failed to get the sale deed executed on 24.07.2006 i.e. the date fixed in the reminder Ex.D3, the appellant was not required to appear in the office of the Sub Registrar either on 20.06.2007 or on 20.02.2008 and in view the express terms of agreement dated 03.08.2005 and 19.09.2005, above agreements got automatically cancelled and the earnest money got forfeited. On the one hand, the learned trial court hhas observed that the respondent was not ready and willing to perform its part of the contract, as such, the relief of specific performance was not granted to the respondent but on the other hand, the relief of recovery of earnest money has been granted to the respondent. As the respondent was not ready and willing to perform its part of the contract, in
10 of 11
Neutral Citation No:=2025:PHHC:006983
RSA-4949--2019 (O&M) -11-
view of the express provisions of agreement to sell dated 03.08.2005 and 19.09.2005, the earnest money was liable to be forfeited. Moreover, in the plaint, the respondent has not claimed the alternative relief, so the learned trial court was not competent to grant above relief to the respondent. Reliance in this regard placed on cases titled as Surmukh Singh Vs. Swaran Singh (supra) and Harish Kumar and otherss Vs. Mohinder Singh and others (supra) (supra)."
16. Learned counsel for the plaintiff has very candidly admitted
before this Court that there were specific terms and conditions in the
agreements in question as per which failure to execute the sale deed
would automatically entail cancellation and forfeiture of earnest
money.Learned arned counsel for the appellant appellant-plaintiff is also unable to
dispute or controvert the above said evidence/findings or give any
satisfactory tory explanation for the same.
17. In view of the above facts and irrefutable evidence on
record,, I find that there is no infirmity in the impugned judgment and
decree dated 5.3.2019 passed by the learned 1st Appellate Court.
18. As such, the present appealss are dismissed.
19. Pending application(s) if any also stand(s) disposed of.
20. A photocopy of this order be placed on the file of other
connected case.
17.01.2025 ( NIDHI GUPTA )
rishu JUDGE
Whether speaking/reasoned Yes/No
Whether Reportable Yes/No
11 of 11
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!