Citation : 2024 Latest Caselaw 16622 P&H
Judgement Date : 10 September, 2024
Neutral Citation No:=2024:PHHC:118282
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
RSA-374-2015 (O&M)
Reserved on: 02.09-2024
Pronounced on: 10.09.2024
SMT. SUNITA AND OTHERS
. . . .APPELLANTS
Vs.
RAJENDER SINGH AND ANOTHER
. . . . RESPONDENTS
CORAM: HON'BLE MR. JUSTICE DEEPAK GUPTA
Present:- Mr. P.R. Yadav, Advocate, for the appellants.
Mr. Vishal Aggarwal, Advocate, for the respondents.
DEEPAK GUPTA, J.
Present Regular Second Appeal was earlier disposed of by a Coordinate Bench of this Court by way of order dated 16.01.2019. However, the said order was challenged by the respondent of the appeal before Hon'ble Supreme Court by filing Civil Appeal No.4222 of 2023 (arising out of SLP-C- 19102-2019) and by way of order dated 06.07.2023, Hon'ble Supreme Court has set aside the order dated 16.01.2019 of this Court and has remanded the matter with the direction to examine the appeal afresh on the question of entitlement of the plaintiff to enforce specific performance of the agreement or any other relief. That is how, the present appeal is again before this Court.
2.1 Perusal of the paper-book would reveal that vide an agreement dated 10.04.2006, Raj Singh, the predecessor-in-interest of the defendants (appellants & performa respondent herein) had agreed to sell the suit land to plaintiff-Rajender Singh (respondent No.1 herein) and an amount of ₹4 lakh was paid as earnest money. Initially, the target date for execution of the sale deed was fixed as 16.08.2006, but with mutual consent, it was extended firstly to 16.12.2006 and thereafter to 31.01.2007. Seeking the decree for specific performance, it was alleged by the plaintiff that Rajender Singh had
1 of 13
Neutral Citation No:=2024:PHHC:118282
RSA-374-2015 2024:PHHC: 118282
failed to procure no objection certificate and avoided the matter to perform his part of contract on one pretext or the other and that with dishonest intention to grab the earnest money, had even filed civil suit against the plaintiff, which was duly contested by him. Later on, as Raj Singh had expired, so specific performance was sought against his legal heirs - defendants, as they did not respond to the repeated legal notices sent to them.
2.2 Defendants in the written statement raised various preliminary objections. They challenged the readiness and willing on the part of plaintiff to perform his part of the contract and prayed for dismissal of the suit.
2.3 Following issues were framed by the trial Court: -
"1. Whether late Raj Singh executed agreement to sell regarding his land as mentioned in para No.1 of the plaint on dated 10.04.2006 in favour of plaintiff?
2. Whether a decree for possession by way of specific performance of agreement to sell is liable to be passed in favour of plaintiff against the defendants on the grounds mentioned in the plaint? OPP
3. Whether the plaintiff has no cause of action to file the present suit?
OPD
4. Whether the plaintiff has no cause of action to file the present suit?
OPD
5. Whether the plaintiff has no locus-standi to file the present suit? OPD
6. Whether the suit of the plaintiff is hopelessly time barred? OPD
7. Relief."
2.4 After taking evidence produced by the parties, the trial Court decided issue No.1 in favour of the plaintiff. Issue No.2 was partly decided in favour of the plaintiff, whereas the findings on issues No.3 to 6 went against the defendants. Consequent to these findings, trial Court decreed the suit on 10.9.2013 by directing the defendants to pay the earnest money of ₹4 lakh to
2 of 13
Neutral Citation No:=2024:PHHC:118282
RSA-374-2015 2024:PHHC: 118282
the plaintiff along with the simple interest @ 8% per annum from the date of filing of the suit till actual realization within the period of two months.
2.5 Unsatisfied with the judgment and decree of the trial court, plaintiff filed appeal. The First Appellate Court modified the judgment and decree of the trial Court and held vide judgment dated 11.09.2014 that plaintiff was entitled to possession of the suit property by way of specific performance of the agreement dated 10.04.2006. Accordingly, the plaintiff was directed to deposit balance consideration amount either with the respondents/defendants or in the trial Court within the period of one month from the date of judgment & decree of the appellate Court, observing that thereafter defendants would execute the sale deed and get it registered within three months, failing which plaintiff would be at liberty to get the sale deed executed through the trial Court.
3.1 Against the aforesaid judgment and decree, defendants approached this Court by filing the present Regular Second Appeal.
3.2 The Coordinate Bench of this Court by way of the order dated 16.01.2019 held that target date for execution of the sale deed was 31.01.2007, whereas the suit had been filed on 01.02.2010 and so, it was clearly barred by limitation and on this ground itself, the suit deserved to be dismissed. The issue of readiness and willingness on the part of the plaintiff in performing the contract was also considered by the Coordinate Bench of this Court and it was held that plaintiff had failed to prove his readiness and willingness to perform his part of contract and that in these circumstances, the judgment and decree passed by the Courts below could not be sustained.
3.3 Consequently, the appeal was allowed and the judgments of the Courts below were set aside, dismissing the suit of the plaintiff.
4. In the appeal filed by the plaintiff against aforesaid order, it has been held by Hon'ble Supreme Court that the day, which has been treated by the High Court as the date of expiry of limitation was actually a holiday and that the suit was instituted on the next working day and as such, the suit was
3 of 13
Neutral Citation No:=2024:PHHC:118282
RSA-374-2015 2024:PHHC: 118282
instituted within time. As such, the finding of this High Court to the effect that suit was barred by limitation, was set aside.
5. On the issue of readiness and willingness of the plaintiff, Hon'ble Supreme Court referred to the observations made by the trial Court, which read as under: -
"15. Furthermore, plaintiff - PW1 when stepped into the witness box has deposed that he was ready and willing to perform his part of the contract, whereas, Late Raj Singh did not come present for getting the sale deed executed and his testimony is substantiated by PW2 also. Both these witnesses were thoroughly cross-examined, but, credibility of these witnesses could not be impeached. Although, plaintiff has admitted in his cross-examination that notice sent to him was received after 31.1.2007, but as no objection certificate was not obtained, therefore sale deed could not be executed. He has also explained that though notice was not replied, but same was not replied as the matter was taken up in the village brotherhood. The plaintiff has placed on record affidavit Ex.P.8, whereby, he marked his presence in the office of Sub Registrar on 31.1.2007. On the other hand, though, defendants have examined as many as three witnesses and all the witnesses have supported the case of defendants in their affidavits, but, none of them has deposed that Late Raj Singh went to the office of Sub Registrar for getting the sale deed executed on 31.1.2007 or on 2.2.2007, whereas, DW1 and DW2 have admitted that due date for executing the sale deed was extended twice. Even otherwise also, all the witnesses examined by defendants are relatives of defendants, therefore, their testimony is not worthy of credence. Therefore, conjoint reading of the oral testimony and affidavit shows that plaintiff had been ready and willing to perform his part of the agreement, whereas, Late Raj Singh has defaulted in the same.
6. Hon'ble Supreme Court then referred to the observations made by this Court in its order dated 16.01.2019 and then held as under: -
" So far as the readiness and willingness of the plaintiff to undertake or discharge his obligation in terms of a contract is concerned, we have quoted from the judgment of the Trial Court. We do not find any basis for negating the first two Court's views in the second appeal. The findings of the first two Courts were based on evidence. The High Court, in second appeal has undertaken the
4 of 13
Neutral Citation No:=2024:PHHC:118282
RSA-374-2015 2024:PHHC: 118282
exercise of reappreciation of evidence. The second issue, as framed by the Trial Court appears to cover the question of readiness and willingness of the plaintiff to perform his part of obligation.
We accordingly set aside the judgment of the High Court but remand the matter to the High Court for examining the appeal afresh on the question of entitlement of the plaintiff to enforce specific performance of the agreement or any other relief. Since this proceeding originates from a suit instituted in the year 2010, we request the High Court to fix an early date for hearing for considering the appeal on the aforesaid point."
7. It is, thus, clear that Hon'ble Supreme Court held that findings of the two Courts below on the issue of readiness and willingness of the plaintiff to undertake or discharge his obligation to the contract was based upon evidence and that this Court had undertaken an exercise of re-appreciation of evidence and as such, the order of this Court was set aside.
8. In view of the aforesaid observation made by Hon'ble Supreme Court, the issue relating to readiness and willingness of the plaintiff to perform his part of contract cannot be re-agitated before this Court.
9. The only question to be considered by this Court is regarding the entitlement of the plaintiff to enforce specific performance of the agreement or any other relief. In other words, whether in the facts and circumstances of the present case, the discretionary relief of grant of specific performance of contract should be granted in favour of the plaintiff or not?
10.1 Learned counsel for the appellants-defendants has drawn attention of this court towards the fact that as per the own case of the plaintiff-respondent, the last date for execution of the sale deed after extension was 31.01.2007 and that suit has been filed for seeking specific performance on 01.02.2010. Though the suit has been held by Hon'ble Supreme Court to be within limitation, but still the suit is on the last date prior to expiry of the limitation. Attention is further drawn by ld. counsel towards the fact that property in dispute is situated in village Barhi, Tehsil Ganaur, District Sonepat, which is adjacent to the GT Road and there is a
5 of 13
Neutral Citation No:=2024:PHHC:118282
RSA-374-2015 2024:PHHC: 118282
phenomenal increase in the prices of the land. It is contended that the plea of 'time is not an essence of the contract', cannot be pleaded in these facts and circumstances. Attention is drawn further towards the fact that total value of the suit property as per the agreement works out to be `28,04,175/- and only an amount of `4 lakh was paid as earnest money. Even the amount of `5 lakh, which was agreed to be paid by the plaintiff while extending the time for execution of the sale deed on 16.08.2006 was never paid and that in these circumstances, plaintiff is not entitled for discretionary relief of specific performance.
10.2 Learned counsel refers to the following decisions: -
(i) Saradamani Kandappan Vs. S. Rajalakshmi and others, 2011 AIR
SC (Civil) 812
(ii) U.N. Krishnamurthy (since deceased) through LRs Vs. A.M. Krishnamurthy, 2022 AIR (Supreme Court) 3361
(iii) P. Daivasigamani Vs. S. Sambandan, 2022 AIR (Supreme Court)
(iv) Alagammal and others Vs. Ganesan and another, 2024(1) RCR (Civil) 502.
11.1 Refuting the aforesaid contentions, it is urged by learned counsel
for the respondent-plaintiff that it is Raj Singh, predecessor-in-interest of the
defendants-appellants, who was required to obtain no objection certificate
but he failed to do so. Repeated legal notices were sent to the legal heirs of
Raj Singh i.e. the defendants to come forward for execution of the sale deed,
but they failed to do so and once it has been found that suit is within
limitation, it is no longer in the discretion of the Court to refuse the specific
performance, as the question of readiness and willingness cannot be
re-agitated before this Court in view of the concurrent findings of the Courts
below, as per the observations made by Hon'ble Supreme Court. Ld. counsel
refers to a decision of Hon'ble Supreme Court rendered in Sughar Singh Vs.
Hari Singh (Dead) through LRs and others, 2021(4) RCR (Civil) 632.
6 of 13
Neutral Citation No:=2024:PHHC:118282
RSA-374-2015 2024:PHHC: 118282
11.2 It is further argued that hardship to the plaintiffs or the
phenomenal increase in prices cannot be the reason to decline the relief of specific performance. To support this contention, ld. counsel refers to decision of Hon'ble Supreme Court rendered in Prakash Chandra Vs. Narayan and a decision of this Court rendered in Manju Vs. Virender Singh, 2023(4) RCR (Civil) 167.
12. I have considered submission of both the sides and have appraised the record.
13. Factual position is not in dispute to the effect that target date for execution and registration of the sale deed, after agreed extensions, was 31.01.2007 and the suit has been filed on 01.02.2010 i.e. on the last date of the expiry of the limitation. It is also undisputed that only an earnest money of `4 lakh was paid at the time of execution of the agreement on 10.04.2006, out of total price of the suit land, which works out to be above `28 lakh. It is further undisputed that as per the endorsement dated 16.08.2006 for extension of target date, an amount of `5 lakh was to be paid up to 10.11.2006, but this additional amount of `5 lakh was never paid by the plaintiff-respondent.
14. Though, there is reference of obtaining no objection certificate in the subsequent endorsement for extension of time dated 16.12.2006, but there was no such stipulation in the agreement. Ld. counsel for the respondent has been unable to convince this Court as to what sort of no objection was to be obtained by Raj Singh and from which authority and as such, the plaintiff-respondent cannot be permitted to take shelter under the fact that Raj Singh failed to obtain any no objection certificate.
15. The question is that whether in the above said facts and circumstances, plaintiff deserves to be granted the relief of specific performance?
16. In the case of Saradamani Kandappan (Supra), Hon'ble Supreme Court has observed that the law that 'time was not essence of contract' was
7 of 13
Neutral Citation No:=2024:PHHC:118282
RSA-374-2015 2024:PHHC: 118282
evolved long years back, when prices were stable and inflation was unknown. However, these days there is galloping increase in prices of immovable properties. Market values of properties are no longer stable or steady and therefore, there is an urgent need to revisit the principle that time is not of the essence in contracts. It will be apt to reproduce the observations made by the Supreme Court in this regard after referring to a decision in K.S. Vidyanadam and others Vs. Vairavan, (1997) 3 SCC 1, which read as under: -
"27. A correct perspective relating to the question whether time is not of the essence of the contract in contracts relating to immovable property, is given by this court in K.S. Vidyanadam and Others vs. Vairavan - (1997) 3 SCC 1 (by Jeevan Reddy J. who incidentally was a member of the Constitution Bench in Chand Rani). This Court observed:
"It has been consistently held by the courts in India, following certain early English decisions, that in the case of agreement of sale relating to immovable property, time is not of the essence of the contract unless specifically provided to that effect.
In the case of urban properties in India, it is well-known that their prices have been going up sharply over the last few decades - particularly after 1973. .........We cannot be oblivious to the reality and the reality is constant and continuous rise in the values of urban properties - fuelled by large scale migration of people from rural areas to urban centres and by inflation.
Indeed, we are inclined to think that the rigor of the rule evolved by courts that time is not of the essence of the contract in the case of immovable properties - evolved in times when prices and values were stable and inflation was unknown - requires to be relaxed, if not modified, particularly in the case of urban immovable properties. It is high time, we do so." (emphasis supplied)
Therefore there is an urgent need to revisit the principle that time is not of the essence in contracts relating to immovable properties and also explain the current position of law with regard to contracts relating to immovable property made after 1975, in view of the changed circumstances arising from inflation and steep increase in prices. We do not propose to undertake that exercise in
8 of 13
Neutral Citation No:=2024:PHHC:118282
RSA-374-2015 2024:PHHC: 118282
this case, nor referring the matter to larger bench as we have held on facts in this case that time is the essence of the contract, even with reference to the principles in Chand Rani and other cases. Be that as it may.
28. Till the issue is considered in an appropriate case, we can only reiterate what has been suggested in K.S. Vidyanadam (supra) :
(i) Courts, while exercising discretion in suits for specific performance, should bear in mind that when the parties prescribe a time/period, for taking certain steps or for completion of the transaction, that must have some significance and therefore time/period prescribed cannot be ignored.
(ii) Courts will apply greater scrutiny and strictness when considering whether the purchaser was `ready and willing' to perform his part of the contract.
(iii) Every suit for specific performance need not be decreed merely because it is filed within the period of limitation by ignoring the time-
limits stipulated in the agreement. Courts will also `frown' upon suits which are not filed immediately after the breach/refusal. The fact that limitation is three years does not mean a purchaser can wait for 1 or 2 years to file a suit and obtain specific performance. The three year period is intended to assist purchasers in special cases, as for example, where the major part of the consideration has been paid to the vendor and possession has been delivered in part performance, where equity shifts in favour of the purchaser."
17. Taking similar view in the case of U.N. Krishnamurthy (since deceased) through LRs (Supra), Hon'ble Supreme Court held that the fact that limitation is three years does not mean that purchaser can wait for one or two years to file the suit and obtain specific performance. Hon'ble Supreme Court observed as under: -
"38. In this case, we cannot overlook the fact that the suit property is located in the industrial town of Hosur located about 30/40 kms. from Bengaluru. The Court is obliged to take judicial notice of the phenomenal rise in the price of real estate in Hosur. The proposition finds support from case reported in K.S.
9 of 13
Neutral Citation No:=2024:PHHC:118282
RSA-374-2015 2024:PHHC: 118282
Vidyanadam v. Vairavan (supra). To quote this Court "we cannot be oblivious to reality - and the reality is constant and continuous rise in the values of urban properties -fuelled by large scale migration of people from rural areas to urban centres and by inflation."
39. Mr. Venugopal argued that the Plaintiff had only paid an insignificant amount of Rs.10,001/- as advance when the consideration was Rs.15,10,000/-. Having paid an insignificant amount the Plaintiff was not entitled to discretionary equitable relief of Specific Performance, as observed by this Court in Saradamani Kandappan v. S. Rajalakshmi (2011) 12 SCC 18. The relevant paragraph of the judgment of this Court is set out hereinbelow:-
"37. The reality arising from this economic change cannot continue to be ignored in deciding cases relating to specific performance. The steep increase in prices is a circumstance which makes it inequitable to grant the relief of specific performance where the purchaser does not take steps to complete the sale within the agreed period, and the vendor has not been responsible for any delay or non-performance. A purchaser can no longer take shelter under the principle that time is not of essence in performance of contracts relating to immovable property, to cover his delays, laches, breaches and 14 (2011) 12 SCC 18 "non-readiness". The precedents from an era, when high inflation was unknown, holding that time is not of the essence of the contract in regard to immovable properties, may no longer apply, not because the principle laid down therein is unsound or erroneous, but the circumstances that existed when the said principle was evolved, no longer exist. In these days of galloping increases in prices of immovable properties, to hold that a vendor who took an earnest money of say about 10% of the sale price and agreed for three months or four months as the period for performance, did not intend that time should be the essence, will be a cruel joke on him, and will result in injustice. Adding to the misery is the delay in disposal of cases relating to specific performance, as suits and appeals therefrom routinely take two to three decades to attain finality. As a result, an owner agreeing to sell a property for rupees one lakh and receiving rupees ten thousand as advance may be required to execute a sale deed a quarter century later by receiving the remaining rupees
10 of 13
Neutral Citation No:=2024:PHHC:118282
RSA-374-2015 2024:PHHC: 118282
ninety thousand, when the property value has risen to a crore of rupees."
40. As argued by Mr. Venugopal, the fact that the suit had been filed after three years, just before expiry of the period of limitation, was also a ground to decline the Respondent Plaintiff the equitable relief of Specific Performance for purchase of immovable property. Mr. Venugopal's argument finds support from the judgments of this Court in P.R. Deb and Associates v. Sunanda Roy (1996) 4 SCC 423; K.S. Vidyanadam v. Vairavan (1997) 3 SCC 1; Manjunath Anandappa v. Tammanasa (2003) 10 SCC 390, Azhar Sultana v. B. Rajamani (2009) 17 SCC 27; Saradamani Kandappan v. S. Rajalakshmi (2011) 12 SCC 18.
41 & 42 Xxxxxxxx.......
43. In Saradamani Kandappan (supra) this Court reiterated that (i) while exercising discretion in suits for Specific Performance, the Courts should bear in mind that when the parties prescribed a time for taking certain steps or for completion of the transaction, that must have some significance and therefore time/period prescribed cannot be ignored; (ii) the Courts will apply greater scrutiny and strictness when considering whether purchaser was ready and willing to perform his part of the contract and (iii) every suit for Specific Performance need not be decreed merely because it is filed within the period of limitation, by ignoring time limits stipulated in the agreement. The courts will also frown upon suits which are not filed immediately after the breach/refusal. The fact that limitation is three years does not mean that a purchaser can wait for one or two years to file a suit and obtain Specific Performance. The three year period is intended to assist the purchaser in special cases, as for example where the major part of the consideration has been paid to the vendor and possession has been delivered in part performance, where equity shifts in favour of the purchaser."
18. In the case of P. Daivasigamani (Supra), after referring to decisions in the case of K.S. Vidyanadam and others (Supra) and Saradamani Kandappan (Supra), it has been held by Hon'ble Supreme Court that there is distinction between limitation and delay and laches. Limitation is a ground for dismissing a suit, even if the plaintiff is otherwise entitled to specific performance, while delay operates to determine the discretion and exercise
11 of 13
Neutral Citation No:=2024:PHHC:118282
RSA-374-2015 2024:PHHC: 118282
under Section 20 of the Specific Relief Act, even if the suit is not dismissed on account of limitation. It was held further that not one but several aspects have to be considered when the court, in terms of Section 20 of the Specific Relief Act exercises discretion, guided by judicial principles, sound and reasonable.
19. In the case of Alagammal and others (Supra), suit for specific performance was filed 2½ years after the target date fixed in the agreement. It was observed by Hon'ble Supreme Court as under: -
"In the case before us, it is not mere delay. It is a case of total inaction on the part of the plaintiff for 2 1/2 years in clear violation of the terms of agreement which required him to pay the balance, purchase the stamp papers and then ask for execution of sale deed within six months. Further, the delay is coupled with substantial rise in prices -- according to the defendants, three times -- between the date of agreement and the date of suit notice. The delay has brought about a situation where it would be inequitable to give the relief of specific performance to the plaintiff." (Emphasis supplied)
20. In view of the legal position discussed as above and applying the
same to the facts of the present case, this Court is of the view that plaintiff-
respondent is not entitled to the relief of specific performance, having regard
to his conduct, who filed the suit three years after the target date fixed for
execution of the sale deed i.e. on the last date of limitation. The Court also
notices that petty amount of approximately 14% of the total sale
consideration was paid. Even additional amount of `5 lakh agreed to be paid
by the plaintiff while extending the time for execution, was not paid. Prices of
the suit property in the last approximately 20 years have increased
phenomenally and in these circumstances, it will not be a sound exercise of
discretion so as to grant the relief of specific performance in favour of the
respondent-plaintiff. Even in the case of Sughar Singh (Supra), referred by ld.
counsel for the respondent, it has been held by Hon'ble Supreme Court that
the discretion under Section 20 of the Specific Relief Act is required to be
exercised judiciously, soundly and reasonably.
12 of 13
Neutral Citation No:=2024:PHHC:118282
RSA-374-2015 2024:PHHC: 118282
21. Consequent to the aforesaid discussion, the present appeal is hereby accepted. The judgment and decree dated 11.09.2014 passed by the First Appellate Court of ld. Additional District Judge is hereby set aside. The judgment and decree of the trial Court dated 10.09.2023 of ld. Additional Civil Judge (Jr. Division), Ganaur is hereby upheld, whereby the defendants- appellants were directed to return the amount of `4 lakh towards earnest money to the plaintiff-respondent along with simple interest @ 8% per annum from the date of filing of the suit till actual realization. The appeal is accepted accordingly. Parties are left to bear their own costs.
10.09.2024 (DEEPAK GUPTA)
Vivek JUDGE
Whether speaking/reasoned? Yes
Whether reportable? Yes
13 of 13
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!