Thursday, 21, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Uttar Haryana Bijli Vitran Nigam Ltd. ... vs M/S Roop Kamal Stone Crusher And Anr
2024 Latest Caselaw 15966 P&H

Citation : 2024 Latest Caselaw 15966 P&H
Judgement Date : 2 September, 2024

Punjab-Haryana High Court

Uttar Haryana Bijli Vitran Nigam Ltd. ... vs M/S Roop Kamal Stone Crusher And Anr on 2 September, 2024

                                      Neutral Citation No:=2024:PHHC:114657




CWP-6284-2021                                                      -1-

         IN THE HIGH COURT OF PUNJAB AND HARYANA
                       AT CHANDIGARH

222                                           CWP-6284-2021
                                              Date of decision: 02.09.2024

Uttar Haryana Bijli Vitran Nigam Limited & ors.                 ...Petitioners

                                   Versus

M/s Roop Kamal Stone Crusher & another                     ...Respondents

CORAM: HON'BLE MR. JUSTICE VINOD S. BHARDWAJ

Present :   Mr. R.S. Longia, Advocate
            for the petitioners.

            Mr. Vinay Kumar Arya, Advocate for
            Mr. Anshul Mangla, Advocate,
            for respondent No.1.

VINOD S. BHARDWAJ, J. (Oral)

The present petition has been filed challenging the award dated

02.12.2020 passed by Permanent Lok Adalat (Public Utility Services),

Yamuna Nagar, whereby the application filed by respondent No.1-applicant

has been allowed and the demand raised by the petitioners has been set

aside.

Learned counsel appearing on behalf of the petitioners

contends that respondent No.1-applicant is a consumer of the petitioners

having a non-domestic electricity supply connection for running his Saw

Mill. The electricity connection account No.LS-26 of respondent No.1-

applicant was audited by the internal audit party and as per its Half Margin

Report No.8 dated 29.11.2019 for the period from April, 2017 to March,

2018, it was noticed that the energy meter was replaced vide MCO No.

48/01 dated 18.05.2017 on 19.06.2017 for providing CT/PT facility. In the

previous meter, the consumption was being computed by applying a

1 of 4

Neutral Citation No:=2024:PHHC:114657

multiplying factor of .15 to the recorded units, whereas in the new meter,

consumption was to be computed by applying Multiplying Factor of 3. The

billing was however inadvertently done by applying the old Multiplying

Factor of .15 thus resulting in less amount being charged by the distribution

licensee from the consumer. The account of respondent No.1-applicant was,

accordingly, over-hauled for the said period and the differential charge was

claimed from respondent No.1-applicant. The same was challenged by

respondent No.1-applicant before the Permanent Lok Adalat (Public Utility

Services), Yamuna Nagar, which allowed the application by relying on

Section 56(2) of the Electricity Act, 2003, to contend that a demand which

is raised after a period of more than 2 years, cannot be recovered by the

distribution licensee.

Learned counsel appearing on behalf of the petitioners

contends that the award of the Permanent Lok Adalat (Public Utility

Services), Yamuna Nagar, suffers from misappreciation of the statutory

provisions enshrined under Section 56(2) of the Electricity Act. He

contends that the amount becomes due and payable to the distribution

licensee after the mistake is detected and that the Hon'ble Supreme Court

has already held that the distribution licensee is entitled to claim such an

amount. It was held by the Hon'ble Supreme Court in the matter of M/s

Prem Cottex vs. Uttar Haryana Bijli Vitran Nigam Ltd. and others,

reported as 2021 (4) RCR (Civil) 422, that if the licencee has not raised any

bill, merely because there is no negligence on the part of the consumer to

pay bill, the period of limitation prescribed under Section 56 (2) of the

Electricity Act will not start running and has to be computed from the date

2 of 4

Neutral Citation No:=2024:PHHC:114657

when the error/mistake is detected.

Second argument raised is to the effect that the dispute was

principally in the nature of a billing dispute on account of revision of the

charges due to the bills having been wrongly demanded on account of a

wrong multiplication factor. The same was essentially a billing dispute and

not a supply dispute and thus the Permanent Lok Adalat had no jurisdiction

to entertain the application.

Learned counsel for respondent No.1 is not in a position to

dispute the applicability of the aforesaid judgment and fairly concedes that

the dispute was essentially not in the nature of supply dispute and was

principally a dispute pertaining to the demand of electricity consumption

charges.

I have heard learned counsel for the respective parties and have

gone through the documents appended along with the present petition.

As the counsel for the respondent-applicant concedes that the

dispute was not in the nature of supply dispute and is a billing dispute

which could not have been taken cognizance of by the Permanent Lok

Adalat, the other argument pertaining to Section 56(2) of the Electricity Act,

2003, need not be dealt with any further. The proceedings were thus not

maintainable before the Permanent Lok Adalat. This Court refrains from

proceeding any further in the matter on merits lest it may cause prejudice to

the inter se rights of the contesting parties.

The present writ petition is, accordingly, allowed and the award

dated 02.12.2020 passed by Permanent Lok Adalat (Public Utility Services),

Yamuna Nagar, in application No.20/YNR/2020 titled 'M/s Roop Kamal

3 of 4

Neutral Citation No:=2024:PHHC:114657

Stone Crusher Vs. S.D.O., Op, U.B.V.N.', is set aside. Respondent No.1-

applicant shall however be entitled to raise a challenge to the said demand

before the competent forum under Section 42(5) of the Electricity Act,

2003.

In the event of respondent No.1-applicant taking recourse to

such a proceeding, the period spent in pursuing the remedy with the Legal

Services Authority and before this Court shall be taken into consideration

for computing limitation. Needless to mention that an expeditious decision

shall be taken on the case, if so instituted.




02.09.2024                                      (VINOD S. BHARDWAJ)
monika                                                JUDGE
             Whether reasoned/speaking:         Yes/No
             Whether reportable:                Yes/No




                                       4 of 4

 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter