Citation : 2023 Latest Caselaw 16735 P&H
Judgement Date : 25 September, 2023
134 RA-RS-63-2023 IN RERA-APPL-83-2023 RA-RS-61-2023 IN
RERA-APPL-84-2023 RA-RS-62-2023 IN RERA-APPL-88-2023
M/S PIVOTAL INFRASTRUCTURE PVT LTD VS ASHWINI KUMAR
KHOSLA
Present: Mr. Karan Kaushal, Advocate for applicant-appellant.
*****
Prayers made in the applications are for recalling of order
dated 08.08.2023 seeking modification thereof.
A perusal of order dated 08.08.2023 shows that the appeals
were disposed of in terms of order dated 01.06.2023 passed by this
Court in RERA-APPL-65 to 67-2023 while granting the same relief to
the appellant.
I have heard learned counsel for the applicant-appellant and
gone through the contents of application. For the reasons mentioned in
the applications, the same are allowed.
Although, the present appeals were disposed of in terms of
judgment dated 01.06.2023 passed in RERA-APPL-65 to 67-2023,
however, no cost was imposed in the present appeals for the reason
that no recovery certificate and writ of demand by the Tehsildar was
ever issued against the present appellant.
In view thereof, the order dated 08.08.2023 is modified to
the extent that though, the appeal shall remain disposed of in terms of
decision dated 01.06.2023 passed in RERA-APPL-65 to 67-2023,
however, subject to no cost.
CMs stand disposed of.
A photocopy of this order be placed on connected case files.
25.09.2023 (HARKESH MANUJA)
tejwinder JUDGE
TEJWINDER SINGH
2023.09.26 15:38
I attest to the accuracy and
integrity of this document
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!