Citation : 2023 Latest Caselaw 877 P&H
Judgement Date : 17 January, 2023
RSA-79-2022 (O&M) -1-
IN THE HIGH COURT OF PUNJAB AND HARYANA AT
CHANDIGARH
RSA-79-2022 (O&M)
Date of decision: 17.01.2023
Municipal Corporation, Faridabad and others
...Appellants
Versus
M/s Thola Gamdu Coop. L & C Society Ltd.
...Respondent
CORAM: HON'BLE MR.JUSTICE H.S. MADAAN
Present: Mr. Udit Garg, Advocate for
Mr. Rajiv Verma, Advocate for the appellants.
*****
H.S. MADAAN, J. (Oral)
Briefly stated facts of the case are that plaintiff M/s Thola
Gamdu Coop. L & C Society Ltd. Matindu, Sonipat had brought a suit
against Municipal Corporation, Faridabad through its Commissioner
and Executive Engineer, Municipal Corporation, Faridabad seeking a
declaration that letter dated 22.04.2014 vide which a penalty of 10% of
allotted amount of work i.e. Rs.41,04,600/- under Clause-II and
decision of Corporation to forfeit the security amount are illegal,
arbitrary liable to be set aside, besides craving for grant of permanent
injunction restraining the defendants from recovering the said amount
from the plaintiff and from forfeiting the security amount deposited by
the plaintiff. As per version of the plaintiff, defendant No.1 had allotted
construction work of water drain from Bodh Vihar Chowk to Hitkari
1 of 6
RSA-79-2022 (O&M) -2-
Chowk, NIT Faridabad to plaintiff society after accepting its tender.
The work order had been issued by the defendants, vide letter dated
12.11.2010 and the entire cost of work was fixed as Rs.5,09,30,943/-
which was liable to be extended as per work done at site subject to
approval from the State Government. However, the attitude of
defendant Corporation and its employees was non-cooperative
inasmuch as the plaintiff was not given design of water drain till
03.11.2011 despite various requests, therefore, work could not start. It
took 3 ½ months for defendants to issue the design. The plaintiff had
taken up the matter with officials of defendants in that regard, vide
letter dated 08.03.2011, requesting for extension of time limit from
21.01.2011 to 31.03.2012.
According to the plaintiff, it could not complete the work
due to non finalization of layout of drainage for want of shifting of
transformer poles, water pipelines and delayed payment etc. The
plaintiff kept on making representations to officials of defendants but
no proper and appropriate response was given and delay in completion
of work was solely on account of the sluggish and slow response of
officials of defendants. No ground was there to impose any penalty
upon the plaintiff when defendants refused to withdraw the impugned
notice and threatened to forfeit security amount deposited by the
plaintiff with them. Feeling aggrieved, the plaintiff brought the suit in
question.
2 of 6
RSA-79-2022 (O&M) -3-
2. On notice, the defendants appeared and filed joint written
statement, contesting the suit, raising various preliminary objections,
contending that the plaintiff lacked locus standi to file the suit because
it had failed to execute the alleged work within the stipulated period,
therefore, the penalty was imposed upon it as per terms & conditions of
the contract. The plaintiff itself being a wrong doer is estopped from
filing the suit. According to the defendants, full cooperation was
extended to the plaintiff and designs were supplied within time. All the
hurdles pointed out by the plaintiff in the construction were got
removed. Even time for completion of contract was extended, however,
progress of the work was not upto the satisfaction despite various
letters having been written to the plaintiff. Only 20% of the work was
completed in one year, therefore, penalty was rightly imposed upon the
plaintiff as per rules adopting proper procedure. Refuting the remaining
assertions, the defendants prayed for dismissal of the suit.
3. From the pleadings of the parties, following issues were
framed:-
1. Whether the plaintiff is entitled to get a decree of declaration against the defendants as prayed for? OPP.
2. Whether the plaintiff is entitled to get decree of permanent injunction against the defendants as prayed for? OPP.
3. Whether the suit is not maintainable due to law of estoppal? OPD
4. Whether the plaintiff has violated the terms of agreement? OPD
5. Relief.
3 of 6
RSA-79-2022 (O&M) -4-
4. Parties were afforded adequate opportunities to lead
evidence in support of their respective claims. During the course of
evidence of plaintiff, Sh. Pradeep, its authorized representative
appeared as PW1 and submitted his affidavit Ex.PW1/A in which he
has made assertions in tune of the case of the plaintiff as given in the
plaint. The plaintiff relied upon various documents, whereas, during
the course of evidence of defendants, Sh. Sumer Singh, JE got his
statement recorded as DW1 and repeated on oath the version of
defendants as given in the written statement. The defendants also
proved in evidence several documents.
5. After hearing arguments, the trial Court of Civil Judge (Jr.
Divn.) Faridabad, vide judgment and decree dated 15.09.2018 decreed
the suit of the plaintiff with costs, declaring that the impugned letter
dated 22.04.2014 levying penalty of 10% of amount of contract i.e.
Rs.41,04,600/- under Clause II issued by the defendant Corporation is
null and void and is not binding upon the plaintiff, therefore, the
defendants were restrained from recovery the amount of penalty as
well as forfeiting the security amount in any manner.
6. Feeling aggrieved by the judgment and decree passed by
the trial Court, the defendants had preferred an appeal before District
Judge, Faridabad. The appeal was assigned to Addl. District Judge,
Faridabad, who vide judgment and decree dated 27.10.2021, dismissed
the same.
7. Still feeling aggrieved, the defendants have knocked at the
4 of 6
RSA-79-2022 (O&M) -5-
door of this Court by way of filing the present Regular Second Appeal.
8. I have heard learned counsel for the appellant/defendants
besides going through the record and I find that there is no merit in the
appeal. Here both the Courts below i.e. trial Court of Civil Judge (Jr.
Divn.) Faridabad and Ist Appellate Court of Addl. District Judge,
Faridabad have returned concurrent findings that the delay in execution
of the work by the plaintiff was not deliberate but on account of the act
and conduct of officials of defendants inasmuch as they had not
provided the requisite drawings to the plaintiff within time and had not
got the site cleared for smooth completion of project. The progress in
the drain work could not be done due to non finalization and non
removal of hurdles of crossing of water pipeline to alignment of drain,
electric poles and constructed house in alignment of drains. The
transformer and electric poles coming in between layout of drainage
were also got removed quite belatedly. In that way, the
problems/hurdles pointed out by the plaintiff in various letters written
to officials of defendants were not sorted out at the earliest. Therefore,
the burden for non completion of work in time could not be shifted
upon the plaintiff.
9. The Courts below have analyzed the evidence adduced by
the parties in a very minute and detailed manner, finding that there was
no justification for the defendant corporation to impose any penalty
upon the plaintiff or threatening to forfeit the security deposited by the
plaintiff with Municipal Corporation, Faridabad. Therefore, the relief
5 of 6
RSA-79-2022 (O&M) -6-
of declaration and permanent injunction as prayed for by the plaintiff
was granted to it.
I find that the judgments passed by the Courts below are
quite detailed, well reasoned, based upon proper appraisal of evidence
and correct interpretation of law. No illegality or infirmity therein is
found to be there. There is no ground to interfere with the impugned
judgments and decrees by exercising the power in Regular Second
Appeal. No substantial question of law arises in this appeal. The appeal
is found to be without merit and is dismissed accordingly.
17.01.2023 (H.S. MADAAN)
sumit.k JUDGE
Whether speaking/reasoned : Yes No
Whether Reportable : Yes No
6 of 6
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!