Citation : 2023 Latest Caselaw 14296 P&H
Judgement Date : 28 August, 2023
311 2023:PHHC:112716
IN THE HIGH COURT OF PUNJAB AND HARYANA
AT CHANDIGARH
CR-718-2023
Date of Decision: August 28, 2023
RAJIV AND ORS ......Petitioners
Versus
STATE OF PUNJAB AND ORS ........ Respondents
CORAM: HON'BLE MR. JUSTICE HARKESH MANUJA
Present: Mr. Adarsh Jain, Advocate for the petitioners.
Mr. Navneet Singh, Sr. DAG, Punjab.
****
HARKESH MANUJA, J. (ORAL)
By way of present revision petition, challenge has been laid
to an order dated 31.03.2022 passed by Addl. District judge, Bathinda-
cum-Executing Court.
2. In the present case, land owned by petitioners was acquired
vide notifications dated 21.09.2000 and 14.09.2001 issued under
Sections 4 and 6 of the Land Acquisition Act, 1894 (hereinafter referred
to as 1894 Act) followed by an award dated 12.09.2003. Being
dissatisfied, the petitioners invoked reference under Section 18 of 1894
Act which came to be decided vide award dated 12.02.2003. Still
aggrieved, petitioners filed RFA which came to be decided on
01.04.2019. The operative part thereof is reproduced hereunder:-
"Resultantly, keeping in view the above judgments, this Court is of the opinion that the landowners will be entitled for the payment of interest @ 6% per annum from 15.03.1996 till the date of Section 4 notification, i.e., 21.09.2000, to offset the period of illegal possession by the State, as the said fact has not been denied by the respondents. Even it has come on record that foundation- stone was laid for the construction of the road, on account of which, possession had been taken."
TEJWINDER SINGH 2023.08.31 09:40 I attest to the accuracy and integrity of this document 2023:PHHC:112716
3. Based thereupon, the petitioners filed execution application
claiming additional compensation on the amount of interest awarded in
their favour with effect from 15.03.1996 to 21.09.2000. The petitioners
also submitted that once the amount of damages awarded @ 6% from
15.03.1996 to 21.09.2000 was payable in their favour on the date of
notification issued under Section 4 of the 1894 Act, they were entitled
for interest thereupon with effect from the date of notification issued
under Section 4 of 1894 Act till its disbursement. Instead of issuance of
directions in favour of the landowners, the Executing Court merely
awarded the damages. Being aggrieved thereof, the present revision
petition has been filed.
4. At the outset, learned counsel for petitioners very clearly
submits that petitioners shall not press for their claim of additional
amount of compensation on the damages awarded @6% from
15.03.1996 to 21.09.2000.
4. I have heard learned counsel for the parties and gone
through the paper-book.
5. As regards the claim of interest on the delayed payment of
damages which no doubt became payable on the date of notification
under Section 4 of 1894 Act that is on 21.09.2000, the petitioners have
substance in their submission.
6. Admittedly, the possession of land under acquisition was
taken away from the petitioners on 15.03.1996 and that is why they
were held entitled for payment of interest @6% from 15.03.1996 to
TEJWINDER SINGH 2023.08.31 09:40 I attest to the accuracy and integrity of this document 2023:PHHC:112716
21.09.2000 i.e. the date of notification under Section 4 of 1894 Act and
since the said amount of damages became payable in favour of
petitioners on 21.09.2000, though being released at a later point in time,
the petitioners are no doubt entitled for payment of interest thereupon in
terms of Section 34 of 1894 Act. Nonetheless, a perusal of Annexure P-
6 i.e. the calculation sheet submitted under the signatures of Executive
Engineer, Rural Works Division (B&R), Bathinda submitted in the
execution application at the instance of respondents also shows that
amount of interest prayed for by the petitioners have even been
calculated on the amount of damages.
7. In view of the discussions made hereinabove, the petitioners
shall be entitled for award of interest on the amount of damages
assessed by this Court vide judgment dated 01.04.2019 passed in
favour of the petitioners and the execution shall be carried out in the
aforesaid terms.
28.08.2023 ( HARKESH MANUJA )
tejwinder JUDGE
Whether speaking/reasoned Yes/No
Whether Reportable Yes/No
TEJWINDER SINGH
2023.08.31 09:40
I attest to the accuracy and
integrity of this document
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!