Citation : 2023 Latest Caselaw 4239 P&H
Judgement Date : 17 April, 2023
2023:PHHC:052097
RSA-89-2018 (O&M) 1
242
IN THE HIGH COURT OF PUNJAB AND HARYANA AT
CHANDIGARH
RSA-89-2018 (O&M)
Reserved on : 12.04.2023
Date of decision : 17.04.2023
Satpal Banga ....Appellant
Versus
SDO, PSEB, Saila Khurd and Others ....Respondents
CORAM : HON'BLE MRS. JUSTICE ALKA SARIN
Present : Mr. Arunjeet Singh Kakkar, Advocate for the appellant.
ALKA SARIN, J.
CM-111-C-2018
This is an application for condonation of delay of 19 days in
refiling the appeal.
For the reasons stated in the application, delay of 19 days in
refiling the appeal is condoned. CM stands disposed off.
RSA-89-2018 (O&M)
1. The present appeal has been preferred by the plaintiff-appellant
who has been unsuccessful before both the Courts below.
2. The brief facts relevant to the present lis are that the plaintiff-
appellant filed a suit for perpetual mandatory injunction directing the
defendant-respondents to remove the electricity poles, transformer, YOGESH SHARMA 2023.04.17 11:09 I attest to the accuracy and integrity of this judgment/order.
Punjab and Haryana High Court, Chandigarh 2023:PHHC:052097
electricity wires and other accessories attached with the said transformer
from the site 'ABCD' as shown in the plan attached with the plaint. The case
set-up by the plaintiff-appellant was that he was owner in possession of a
residential house as fully described in the head-note of the plaint and that the
defendant-respondents had illegally, forcibly and at the back of the plaintiff-
appellant installed the transformer and electricity poles along with wires and
other accessories in the house of the plaintiff-appellant. It was further
averred that a civil suit titled as Sat Pal Versus Punjab State Electricity
Board was filed which was dismissed on technical ground. On notice, a
written statement was filed raising preliminary objection that the plaintiff-
appellant had not approached the Court with clean hands. On merits, the
ownership of the plaintiff-appellant over the house was admitted except the
portion where the electric poles of the defendant-respondents were existing.
It was further averred that the plaintiff-appellant had earlier filed a civil suit
which was dismissed. The plaintiff-appellant went in appeal against the said
judgment and decree wherein the Appellate Court held that the defendant-
respondents would remove at their own expenses the L.T. Pole from the
courtyard of the plaintiff-appellant and that the defendant-respondents had
the right to repair the damaged poles and to install new poles and
transformer on the existing place. Replication was filed controverting the
stand taken in the written statement and reiterating the stand taken in the
plaint. On the basis of the pleadings of the parties, the following issues were
framed by the Trial Court :
1. Whether the plaintiff is entitled to mandatory
injunction as prayed for ? OPP YOGESH SHARMA 2023.04.17 11:09 I attest to the accuracy and integrity of this judgment/order.
Punjab and Haryana High Court, Chandigarh 2023:PHHC:052097
2. Whether the plaintiff is entitled to permanent
injunction as prayed for ? OPP
3. Whether the site plan produced by the plaintiff is
not correct ? OPD
4. Whether the plaintiff is estopped from filing suit by
his act, conduct and admission ? OPD
5. Whether the suit is hit by the principle of res
judicata ? OPD
6. Relief.
3. The Trial Court vide judgment and decree dated 01.11.2006
held that the matter stood finally decided in the earlier litigation and the
plaintiff-appellant could not reagitate the matter in the present suit.
Aggrieved by the same, an appeal was preferred by the plaintiff-appellant
which appeal was also dismissed vide judgment and decree dated
24.02.2009. Hence, the present regular second appeal.
4. Learned counsel for the plaintiff-appellant would contend that
the poles installed by the defendant-respondents affect the utility and value
of the property and that the installing of the transformer, poles and electricity
wires would cause irreparable loss and damage to the plaintiff-appellant.
5. Heard.
6. It has concurrently been found by both the Courts below that in
the earlier round of litigation the Appellate Court had modified the judgment
and decree of the Trial Court with a direction to the defendant-respondents
to remove at their own expenses the L.T. pole installed in the courtyard of
the plaintiff-appellant within a month from the date of the order. However, YOGESH SHARMA 2023.04.17 11:09 I attest to the accuracy and integrity of this judgment/order.
Punjab and Haryana High Court, Chandigarh 2023:PHHC:052097
as per the undertaking, it was made clear that the plaintiff-appellant herein
would not be entitled to any compensation for the transformer and poles
erected in his property. By way of the present suit the plaintiff-appellant
wanted to reagitate the matter which is directly and substantially the same as
in the previous litigation. Learned counsel for the plaintiff-appellant has not
been able to convince this Court that the findings in the earlier round of
litigation would not operate as res judicata in the present case. Even
otherwise, there is extra-ordinary delay of 2936 days in filing the present
appeal for which no cogent reasons are forthcoming. Though it has been
stated in the application (CM-504-C-2018) for condonation of delay that the
wife of the plaintiff-appellant was unwell and eventually expired and hence
the plaintiff-appellant was unable to prefer the appeal, however, there is no
document on the record to substantiate the said stand. The present appeal has
been pending since 2017 and till date no document has been brought on the
record by the plaintiff-appellant to substantiate the stand taken by him in the
application.
7. In view of the above, the present appeal, which raises no
question of law much less any substantial question of law, is dismissed on
the ground of delay as well as on merits. Pending applications, if any, also
stand disposed off.
8. Dismissed.
( ALKA SARIN )
17.04.2023 JUDGE
Yogesh Sharma
NOTE : Whether speaking/non-speaking: Speaking Whether reportable: YES/NO YOGESH SHARMA 2023.04.17 11:09 I attest to the accuracy and integrity of this judgment/order.
Punjab and Haryana High Court, Chandigarh
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!