Citation : 2022 Latest Caselaw 6507 P&H
Judgement Date : 11 July, 2022
CWP No.6060 of 2020 1
IN THE HIGH COURT OF PUNJAB AND HARYANA
AT CHANDIGARH.
104 CWP No.6060 of 2020(O&M)
Date of Decision: 11.07.2022
M/s Ferrous Infrastructure Pvt. Ltd. .....Petitioner.
Versus
State of Haryana and others ....Respondents.
***
CORAM: HON'BLE MR. JUSTICE AMOL RATTAN SINGH HON'BLE MR. JUSTICE LALIT BATRA
----
Present: Mr. Sourabh Goel, Advocate for the petitioner.
Mr. Ankur Mittal, Additional A.G. Haryana, for respondents No.1 and 2.
**** Amol Rattan Singh, J.(Oral)
By this petition, the petitioner challenges the order of the
learned Haryana Real Estate Regulatory Authority, Panchkula, by which
the complaint filed by respondents No.3 and 4 herein before that Authority
was allowed along with a large number of other such complaints pending
before that Authority; and the petitioner and other developers (as were
respondents in the other complaints) were directed to refund the amounts
paid by the complainants along with interest calculated in terms of Rule 15
of the Haryana Real Estate (Regulation and Development) Rules, 2017,
with such interest to be calculated from the date of payments made by the
complainants upto the date of uploading of the impugned order itself passed
1 of 7
by the Authority.
Upon Mr. Mittal, learned counsel for respondents No.1 and 2,
submitting that the matter is squarely covered by the judgment of the
Supreme Court in M/s Newtech Promoters and Developers Ltd. Vs. State
of U.P. and others [Civil Appeal Nos.6745-6749 of 2021 arising out of
SLP (Civil) Nos.3711-3715 of 2021], learned counsel for the petitioner
submits that though he cannot dispute that fact and that the ratio of the
judgment would cover the case of the petitioner (which he says very fairly
in our opinion), however, he submits that with the petitioner not having
been allowed to file even a reply before the Authority, the matter deserves
to be remanded to the Authority on that score alone, for hearing afresh.
Having considered that argument whereas otherwise learned
counsel for the petitioner may not have been incorrect in his submission,
however, firstly, the following part of the order of the Authority needs to be
referred to in the context of the reply not being filed but with the complaint
still decided nevertheless:-
"3. The Authority accordingly proceeded with disposal of the
two complaints No.826 of 2018 (M/S Ferrous Infrastructures
Pvt. Ltd.) and complaint No. 1402 of 2018 (Maximal
Infrastructure Pvt. Ltd.) versus M/s Ferrous Infrastructure Pvt.
Ltd. along with 2 other complaints, No.1343 of 2018 and
complaint No.1344 of 2018. The order of disposal of the 4
2 of 7
complaints dated 1.10.2019 was uploaded on the website of the
Authority on 15.10.2019.
4. Having disposed of the above said 4 complaints in
accordance with the orders of the Hon'ble High Court, the
Authority there-after took up the captioned 44 complaints for
adjudication.
5. All the complaints were accordingly listed for hearing on
15.10.2019. Since detailed facts about the project had been
captured in the orders dated 1.10.2019 in the 4 complaints with
lead complaint case No.826 of 2018, the Authority disclosed
its mind that individual complaints against the promoters
of the project will be disposed of in accordance with findings of
the Authority given in the order dated 1.10.2019.
6. When the matter was listed on 15.10.2019, Shri Saurabh
Goel and Reshab Bajaj learned counsels appeared for
respondent company (M/s Ferrous Infrastructure Pvt.Ltd.).
Both the counsels stated before the Authority that respondents
have not received copies of the complaints in any captioned
complaints except in complaint No.762 of 2018. Reply in the
said complaint No.762 had been filed by the respondents on
14.02.2019.
The Authority contradicted the stand of the learned
3 of 7
counsel for respondent that the respondents had not received
copies of the complaints Courier receipts vide which all the
complaints have been delivered at the addresses shown in Para
1 of this order were shown to them. Learned counsel
Shri Reshab Bajaj, however responded by saying that the
respondents had shifted from the given address, therefore, the
copies of complaints appear to
have been delivered to some unauthorised person. The
Authority verified the address of the respondent as was shown
in the agreement made with various
complainants. It observes that the address at which the notice
along with copies of complaint was delivered is the same as
has been shown in the
agreement. The respondents never intimated the changed
address to the complainants. For argument's sake even if it is
taken as correct that the respondents had shifted from the
earlier address. the Authority considers that it was their
responsibility to either informed the complainants of the
changed address or to make arrangements for receipt of the
mail at the earlier address.
xx xx xx
8. The Authority observes that the respondent M/s Ferrous
4 of 7
Infrastructure Pvt. Ltd. had duly received the notices in all the
captioned complaints. A benefit of doubt was given to them on
15.10.2019 and accordingly the learned counsels for the
respondent Shri Saurabh Goyal and Reshab Bajaj were asked
to obtain copies of the notice from the registry. Accordingly,
the respondents became fully aware of all the pending
complaints.
9. Today both the learned counsel Shri Saurabh Goyal as well
as Reshab Bajaj argued that they have not been in a position to
file reply because they had not received copies of the
complaints. In view of the foregoing discussion the Authority
decides to dismiss their arguments and further
decides to proceed with the matter for deciding it on merits.
This entire bunch of 44 complaints is being disposed of
together by this common order. Complaint No.762 of 2018
titled as Rakesh Kumar Versus M/s Ferrous
Infrastructure Pvt. Ltd. is taken as the lead case.
10. All the counsels for the complainants spoke in unison that
they had booked the apartments over 10 years ago and have
also made substantial payments to the respondents. The
respondents have not developed the project
or have seriously violated the building plans as have been
5 of 7
observed in detailed by this Authority while disposing of 4
cross complaints with lead complaint
No. 826 of 2018. They had sought the relief of possession of
their apartments in accordance with law and provisions of
agreement along with compensation for the delay caused by the
respondents, but now in view of the findings of the
Authority in lead complaint No.826 of 2018 the relief of
possession of the apartments appears extremely difficult.
Accordingly, the Authority may grant
them suitable alternate relief."
Learned counsel for the petitioner further points to Clause (vii)
of paragraph 2 of the writ petition itself wherein it is stated that although
the registered address of the petitioner was as had been mentioned in the
complaint before the Authority, however, notices were sent by the
Authority on other addresses, which fact would be clear from the notice
available on the website of the Authority, due to which the notice and the
copy of the complaint were not served upon the petitioner.
To repeat, whereas otherwise counsel for the petitioner would
have been correct in his contention to that effect, however, once it is not
denied that the matter is otherwise squarely covered by the judgment of the
Supreme Court in M/s Newtech Promoters and Developers Ltd.(supra)
and with learned counsel for respondents No.1 and 2 further submitting that
6 of 7
same view has been taken by this court even in CWP No.17657 of 2020
titled M/s Sana Realtors Pvt. Ltd. Vs. The Haryana Real Estate
Regulatory Authority and others (and other connected petitions), decided
on 25.05.2022, consequently, if the petitioner has any grievance at all qua
the impugned order, it is obviously always open to it to challenge the same
before the learned Haryana Real Estate Appellate Tribunal.
Consequently, finding no merit in the petition, it is dismissed.
(AMOL RATTAN SINGH) JUDGE
(LALIT BATRA) JUDGE 11.07.2022 D.Gulati Whether speaking/ reasoned : Yes/ No Whether Reportable : Yes/ No
7 of 7
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!