Wednesday, 17, Jun, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Barkha Ram vs State Of Haryana And Others
2022 Latest Caselaw 322 P&H

Citation : 2022 Latest Caselaw 322 P&H
Judgement Date : 1 February, 2022

Punjab-Haryana High Court
Barkha Ram vs State Of Haryana And Others on 1 February, 2022
                                                                             (1)
CWP No.30077 of 2017



       IN THE HIGH COURT OF PUNJAB AND HARYANA AT
                    CHANDIGARH


                                  Pronounced on : 01.02.2022

                                  CWP No.30077 of 2017

Barkha Ram
                                                            ...Petitioner
                                  Versus
State of Haryana & others
                                                            ...Respondents

(2)
                                  CWP No.30078 of 2017

Rajeev Kumar
                                                            ...Petitioner
                                  Versus
State of Haryana & others
                                                            ...Respondents
(3)
                                  CWP No.30079 of 2017

Jang Singh (Deceased) through his LR
                                                            ...Petitioners
                                  Versus
State of Haryana & others
                                                            ...Respondents


CORAM: HON'BLE MR. JUSTICE AUGUSTINE GEORGE MASIH
       HON'BLE MRS. JUSTICE MEENAKSHI I. MEHTA

Present:     Dr. Surya Parkash, Advocate,
             for the petitioners.

             Mr. Ankur Mittal, Addl. A.G., Haryana
             assisted by Ms. Kushaldeep Kaur, Advocate.

                          *****

AUGUSTINE GEORGE MASIH, J.

By this order, I propose to dispose of three writ petitions i.e.

CWP Nos.30077, 30078 and 30079 of 2017 as they relate to same

1 of 16

CWP No.30077 of 2017

acquisition proceedings and issues involved therein are the same. Counsel

for the parties have consented for disposal of these writ petitions by a

common judgment and have referred to the pleadings in CWP No.30077 of

2017, titled as 'Barkha Ram Vs. State of Haryana & others'.

2. Petitioner has approached this Court for quashing of

notification dated 11.03.1981 (Annexure P-1) issued under Section 4 of the

Land Acquisition Act, 1894 (hereinafter referred to as '1894 Act'),

notification dated 14.12.1983 (Annexure P-2) issued under Section 6 of the

1894 Act and award No.9, dated 12.09.1986 (Annexure P-3) and

supplementary award No.1, dated 27.05.1987 (Annexure P-3A) with a

prayer for release of their land as per Section 24 (2) of the Right to Fair

Compensation and Transparency in the Land Acquisition, Rehabilitation

and Resettlement Act, 2013 (hereinafter referred to as '2013 Act').

3. It has been pleaded in the writ petition that in the year 1962,

residential plots were allotted to the residents of the village within the Lal

Dora but due to shortage of land within Lal Dora, five residents including

the father of the petitioner, were allotted plots outside the Lal Dora. Father

of the petitioner was allotted khasra/Plot No.218, measuring 10 marla (½

share) situated in village Devi Daspura, Hadbast No.361, Tehsil Thanesar,

District Kurukshetra, outside the Lal Dora, which is the land in dispute.

Thereafter, the petitioner had raised construction and built double storey

house on the said plot and is residing therein with his family.

A notification dated 11.03.1981 (Annexure P-1) under Section

4 of 1894 Act was issued by the Government of Haryana for development

2 of 16

CWP No.30077 of 2017

and utilization of land as residential and commercial for Sectors 5 and 7

under Haryana Urban Development Authority Act, 1977. Thereafter,

notification dated 14.12.1983 (Annexure P-2) under Section 6 of 1894 Act

was issued to acquire the land for the above purpose including the land of

the petitioner. After about two and half year, notices under Section 9 was

issued to the land owners including the petitioner to appear on 04.08.1986

for stating the nature of their respective interests and amount and particulars

of their claims for compensation. Thereafter, award No.9 was announced

on 12.09.1986 (Annexure P-3). Before the announcement of the said award,

land owners of the five plots, had approached this Court by filing CWP

No.3943 of 1986 for quashing of notifications referred to above. During

the pendency of the said writ petition, a supplementary award No.1 was

issued on 27.05.1987 (Annexure P-3A). On 14.09.1993, the said writ

petition was dismissed by the learned Single Judge of this Court, which

judgment was challenged by filing LPA No.885 of 1993 and during the

pendency of the said LPA, 2013 Act came into force w.e.f. 01.01.2014. In

the light of the said 2013 Act having come into effect, petitioner along with

other land owners withdrew their LPA on 04.09.2015 with a liberty to file a

representation to the respondents under the 2013 Act.

On 04.09.2015, petitioner/land owners filed their

representation, which ultimately was decided by the respondents on

16.10.2017 (Annexure P-8) by passing a speaking order. Petitioner has

attached a copy of written statement filed by the respondents on 08.01.1987

(Annexure P-9) in the writ petition preferred by the petitioner i.e. CWP

3 of 16

CWP No.30077 of 2017

No.3943 of 1986 to substantiate the fact that the respondents have

themselves admitted that the land in question is a gair mumkin bara and four

sub-standard rooms in the shape of farm house were already built. It was

also mentioned in the said written statement that a supplementary award in

respect of the building structures and trees will be announced soon as the

assessment in respect of these aspects was not received by them from the

technical experts. Thereafter, in a Reference made under Section 18 of the

1894 Act for enhancement of compensation, respondents got inspected and

evaluated the houses and structures on the land in question through

Executive Engineer, Provisional Division No.1 on 10.09.1992, who

submitted its report dated 28.10.1992 (Annexure P-9A), according to which

a house on Khasra No.218 was constructed by the petitioner in the year

1978 with covered area of 625.02 square feet and boundary wall, however,

complete construction was not shown but the said report shows that the

house of the petitioner existed on the land in question since 1978 i.e. prior

to issuance of notification under Section 4 of 1894 Act. Reference has been

made of a letter dated 02.11.2011 (Annexure P-10) addressed by the Estate

Officer, HUDA, Kurukshetra to the Administrator, HUDA, Panchkula,

wherein it has been stated that out of 5 plots, 4 plots have been constructed,

whereas 1 bara is lying vacant and if the land in question is released,

services of the sector would not be affected in any manner. Copy of

election card, ration card and certain photographs have been attached with

the writ petition as Annexure P-11 (colly).

4. Learned counsel for the petitioner asserts that in the light of the

4 of 16

CWP No.30077 of 2017

provisions as contained in Section 24 (2) of 2013 Act, respondents having

neither taken physical possession of the land nor having the compensation

amount been disbursed, would render the land of the petitioner acquired

vide the impugned award liable to be released, especially when the

petitioner had constructed his house thereon and is residing thereon with his

family. It is asserted that the land acquisition proceedings under 1894 Act

would lapse. Counsel for the petitioner, on this basis, asserts that the

notifications dated 11.03.1981 (Annexure P-1) and 14.12.1983 (Annexure

P-2) and award No.9, dated 12.09.1986 (Annexure P-3) as also

supplementary award No.1, dated 27.05.1987 (Annexure P-3A) cannot

sustain and deserves to be set aside.

5. On the other hand, learned counsel for the respondents submits

that the objections were filed by one of the co-sharers of the land involved

in these writ petitions i.e. Rulda Ram with respect to only 2 baras out of 5

baras under Section 5-A on the ground that these baras were being used by

them for residential purpose. The said objections were heard and considered

by the then Land Acquisition Collector on 22.05.1981. As per report of the

Land Acquisition Collector, bara situated on Khasra No.218 was having

four sub-standard rooms along with verandah in the shape of farm house

and the same was used for animals and therefore, the said land was

recommended by the Land Acquisition Collector for acquisition.

6. Learned counsel for the respondents further submits that for

applicability of Section 24 (2) of 2013 Act, which would entitle the

petitioner the benefit of release of land on the lapsing of the acquisition

5 of 16

CWP No.30077 of 2017

proceedings initiated under the 1894 Act, there should neither be physical

possession taken nor compensation paid. If any of the two contingencies

has been complied with, then the land acquisition proceedings under 1894

Act would not lapse. In this regard, counsel for the respondents has placed

reliance upon the judgment of the Hon'ble Supreme Court in Indore

Development Authority Vs. Manoharlal and others 2020 (AIR) SC 1496.

To substantiate this contention, counsel for the respondents has

referred to the reply which has been filed by way of an affidavit of Land

Acquisition Collector, Urban Estate, Panchkula, dated 08.09.2021, wherein

it has been stated that the possession of the land was taken vide Rapat

No.24, dated 12.09.1986, immediate after the passing of the award. It has

further been asserted that out of the total amount of the award of

Rs.26,38,322/-, an amount of Rs.25,35,608/- has already been disbursed and

rest of the amount is available for disbursement. So far as the amount of

compensation due to the petitioner is concerned, i.e. Rs.347.50/-, the said

amount is lying deposited in the account of the Land Acquisition Collector,

and same is available for payment immediately on demand of land owners.

7. Counsel for the respondents further submits that award No.1

was announced on 27.05.1987 after the assessment report dated 16.09.1986

having been received from the Executive Engineer, HUDA, Divn. Karnal,

with regard to building structures/tubewell etc. and the assessment report

dated 11.09.1986 of the Sub-Divisional Engineer, Horticulture, with regard

to fruit/no-fruit trees. The assessment of Rs.25,400/- was made for the

construction on Khasra No.218 and Rs.334/- for trees on Khasra No.219.

6 of 16

CWP No.30077 of 2017

The said amount is lying deposited in the account of LAC and the same is

not received by the petitioner, however, the same is available for payment

immediately on demand of land owners. Therefore, it cannot be said that

because there is structures on the land in question, possession thereof has

not been taken by the respondents as the compensation amount was assessed

after the passing of the award and the same was available for disbursement

but the petitioner himself has not received it.

8. His further contention is that the land of the petitioners affects

the site of three plots of 4 marla and 9 meter wide road, and therefore, the

land of the petitioner cannot be released. Since the compensation amount

has been duly deposited with the Land Acquisition Collector and further,

the possession has been taken vide Rapat No.24, dated 12.09.1986, the

deemed lapsing of acquisition under Section 24 (2) of 2013 Act would not

apply. The writ petition, therefore, deserves to be dismissed.

9. An additional plea, which has been taken while challenging the

award which has been passed, is that an incomplete award has been

announced by the Land Acquisition Collector and since the award qua

superstructure has been announced with the lapse of 2 years after the

passing of the award under Section 11 of 1894 Act, the land acquisition

proceedings would lapse. Learned counsel for the respondents has refuted

this contention of the learned counsel for the petitioner by placing reliance

upon the judgment of Hon'ble Supreme Court in Mohanji and another Vs.

State of U.P. and others 1996 (27) ALR 76 and State of Punjab and

others Vs. Sharan Pal Singh and others 1996 (11) SCC 683, where this

7 of 16

CWP No.30077 of 2017

very plea has been considered and rejected. In any case, it has been asserted

that the award in this case has been announced on 12.09.1986 and the

amendment in 1894 Act came into force w.e.f. 24.09.1984 and therefore,

this contention of the learned counsel for the petitioner cannot be accepted.

10. We have considered the submissions made by the learned

counsel for the parties and with their assistance have gone through the

pleadings as well as the judgment passed by the Hon'ble Supreme Court in

Indore Development Authority's case (supra).

11. The facts, as have been narrated above, have not been disputed.

Notifications under Sections 4 and 6 of the 1894 Act were issued on

11.03.1981 and 14.12.1983 respectively, leading to the passing of the award

dated 12.09.1986. Petitioner is claiming himself to be the owner in

possession of khasra/Plot No.218, measuring 10 marla (½ share) village

Devi Daspura, Hadbast No.361, Tehsil Thanesar, District Kurukshetra and

is seeking lapsing of acquisition with the aid of Section 24 (2) of 2013 Act.

Paras 244 and 245 of the judgment in Indore Development

Authority's case (supra) deal with the vesting of the land in the State on

taking of possession of the acquired land, for which the award has been

passed free from encumbrances. The taking of possession through Rapat

Roznamacha entry has been held to be a valid mode of taking possession of

land. The person retaining possession thereafter is to be treated as a

trespasser as he does not have any right to continue in possession of the

land, which has vested in the State. Possession of the land has been taken

vide Rapat Roznamacha No.24, dated 12.09.1986, thus, fulfilling one of the

8 of 16

CWP No.30077 of 2017

conditions with regard to the possession having been taken over especially

in the light of the fact that the possession through rapat roznamacha has

been held to be valid mode of taking possession of the land.

12. As regards the compensation amount is concerned, it has been

specifically averred in the reply that out of the total amount of the award of

Rs.26,38,322/-, an amount of Rs.25,35,608/- has already been disbursed and

rest of the amount is available for disbursement. So far as the amount of

compensation due to the petitioner is concerned, i.e. Rs.347.50/-, the said

amount is lying deposited in the account of the Land Acquisition Collector,

and same is available for payment immediately on demand of land owners.

Further, award No.1 was announced on 27.05.1987 after the assessment

report dated 16.09.1986 having been received from the Executive Engineer,

HUDA, Divn. Karnal, with regard to building structures/tubewell etc. and

assessment report dated 11.09.1986 of the Sub-Divisional Engineer,

Horticulture, with regard to fruit/no-fruit trees. The assessment of

Rs.25,400/- was made for the construction on Khasra No.218 and Rs.334/-

for trees on Khasra No.219. The said amount is also lying deposited in the

account of LAC and the same is not received by the petitioner, however, the

same is available for payment immediately on demand of land owners.

Merely because the petitioner has not collected the amount of

compensation, it would not entitle him to assert that the compensation has

not been disbursed.

13. Para 203 of the judgment in Indore Development Authority's

case (supra) deals with the word 'paid' and it has been concluded in para 206

9 of 16

CWP No.30077 of 2017

that when the amount has been tendered, the obligation has been fulfilled by

the Collector. In case a person does not collect the amount, he cannot take

the benefit of the same by asserting that the amount has not been paid to

him and as such, there is a lapse of proceedings. Apart from that, it has

been held in para 224 of the said judgment that word 'paid' used in Section

24 (2) of 2013 Act does not include within meaning the word 'deposited',

which has been used for proviso to Section 24 (2). It has, therefore, been

concluded that the acquisition would not lapse, if the compensation amount

is deposited with the Land Acquisition Collector, which is available for

disbursement to the land owner(s).

14. The plea of the learned counsel for the petitioner with regard to

the award qua superstructure etc. having been announced by the Land

Acquisition Collector after a lapse of two years of passing of the award

under Section 11 of the 1894 Act and therefore, land acquisition

proceedings would lapse, cannot be sustained in the light of the judgment

passed by the Hon'ble Supreme Court in Mohanji's case (supra), on which

reliance has been placed by the learned counsel for the respondents,

wherein, on a similar plea, as has been taken by the petitioner herein, a

question was formulated, which reads as follows:-

"4. xxxx xxxxx. The question is whether in these

circumstances, it can be said that no award had been

made under Section 11 of the Act in the proceeding to

result in lapse of the entire proceeding for the acquisition

of the land?"

10 of 16

CWP No.30077 of 2017

While dealing with this question in para 5, it has been held as

follows:-

"5. It is no doubt true that the entire award which is

contemplated under Section 11 of the Act by virtue of

the prescription in Section 11A has to be made within the

period of two years failing which the entire proceeding

shall lapse. The question is whether it can be said in the

present case that no award has been made under Section

11 of the Act in this proceeding? In our view it cannot be

said that no award under Section 11 has been made for

the land acquired. Admittedly, compensation has been

determined in the award so made for ht entire area of

0.99 acres. In view of the fact that no piecemeal award by

making a subsequent award after the expiry of the period

of two years is contemplated in law, the award dated

23.9.1986 must be construed as the whole award made

under Section 11 awarding compensation for the entire

area of 0.99 acres with no compensation awarded for the

building. The Appellants, therefore, had the right to

claim compensation for the building by seeking a

reference under Section 18 of the Act treating the award

as one in which compensation had been determined and

awarded only for the entire land measuring 0.99 acres but

no compensation was awarded for the building therein.

11 of 16

CWP No.30077 of 2017

The Appellants had the remedy to claim compensation

for the building in accordance with law treating the

award made as not awarding any compensation for the

building. That is, however, a different matter and it does

not require any further consideration in this context. It is

sufficient to say that the award dated 23.9.1986 made

within the period specified in Section 11A of the Act

must be construed as an award under Section 11 in the

proceedings for acquisition of the Appellants' land

bearing plot No.1311 having a total area of 0.99 acres.

The contention that the entire proceeding for acquisition

of the land has lapsed by virtue of Section 11A cannot,

therefore, be accepted"

Similar view has been reiterated by the Hon'ble Supreme Court

in Sharan Pal Singh's case (supra). Therefore, plea of the learned counsel

for the petitioner with regard to award qua superstructure etc. having been

announced by the Land Acquisition Collector after a lapse of two years of

passing of the award under Section 11 of the 1894 Act, cannot be accepted

and thus, the same is hereby rejected.

15. Further, the objections filed by one of the co-sharers of the land

in question were heard and considered by the then Land Acquisition

Collector on 22.05.1981, who submitted its report that a bara is situated on

Khasra No.218 having four sub-standard rooms along with verandah in the

shape of farm house and the same was being used for animals. During the

12 of 16

CWP No.30077 of 2017

proceedings of Reference under Section 18 of the 1894 Act for

enhancement of compensation, respondents had got inspected and evaluated

the structures on the land in question through Executive Engineer,

Provisional Division No.1 on 10.09.1992, who submitted its report dated

28.10.1992 (Annexure P-9/A) and assessed the amount of compensation,

which was deposited in the account of Land Acquisition Collector but the

petitioner has not received the same. Thus, it cannot be said that the

compensation has not been awarded for the constructed portion on the land

in question.

16. The petitioner has failed to produce any documentary evidence

which would substantiate that he was residing in the house which was

constructed on the land in question prior to issuance of notification under

Section 4 of 1894 Act. According to the report of Land Acquisition

Collector, there were only four sub-standard rooms along with verandah in

the shape of farm house, which were being used for animals. The

documents placed on record by the petitioner i.e. ration card and Aadhar

Card etc. (Annexure P-11 colly), are of the year 2017 i.e. almost 35 years

after the issuance of notification under Section 4 of 1894 Act. No other

document has been placed on record which would substantiate that there

was a house on the land in question where the petitioner was residing with

his family prior to issuance of notification under Section 4 of 1894 Act. As

per the record available on file, there was only a structure constructed on the

land in question which was used for animals, compensation of which

structure has been assessed and evaluated by the respondents and award in

13 of 16

CWP No.30077 of 2017

that regard has been passed separately after having received the report from

the concerned authorities and compensation amount also stands deposited

in the account of Land Acquisition Collector.

17. It may also be added here that the petitioner himself has

pleaded in para 11 of the writ petition that a Reference before the

Competent Court for enhancement of compensation amount has been

filed, where the structure constructed on the land in question was

inspected and evaluated. The Hon'ble Supreme Court, in para 363 (5) of

the judgment in Indore Development Authority's case (supra), has held

that the landowners, who have filed a reference for higher compensation,

cannot claim lapsing of acquisition proceedings under Section 24 (2) of

the 2013 Act and therefore, the petitioner cannot be held eligible for

claiming the acquisition proceedings to be lapsed under Section 24 (2) of

the 2013 Act and thus, the petitioner cannot take the benefit by asserting

that there is a lapse of proceedings.

18. It is pertinent to mention here that since the earlier writ petition

i.e. CWP No.3943 of 1986, challenging the same very notifications stands

dismissed by this Court vide order dated 14.09.1993 and LPA preferred

against the said order stands withdrawn by the petitioner on 04.09.2015, the

prayer made by the petitioner in the present writ petition cannot be accepted

in the light of the observations of the Hon'ble Supreme Court in Indore

Development Authority's case (supra), where, in paras 359 and 363 (9), it

has been held that if the acquisition of land had earlier been challenged and

the same has been upheld, the proceedings having been concluded, the

14 of 16

CWP No.30077 of 2017

umbrella of protection provided under Section 24(2) of the 2013 Act, cannot

be invoked and it does not revive stale and time barred claims especially

when it has been held in the earlier part of the judgment that after passing of

the award, the amount of compensation has already been deposited with the

Land Acquisition Collector, leading to the land having been vested in the

State in accordance with law.

19. It may not be out of way to mention here that the speaking

order 16.10.2017 (Annexure P-8) which has been passed by the respondents

on the representation submitted by the petitioner in pursuance to the order

dated 04.09.2015 passed by this Court in LPA No.885 of 1993, has not been

challenged in the present writ petition and therefore, the same has attained

finality. Thus, the prayer as made by the petitioner in this writ petition for

quashing the acquisition proceedings cannot be accepted in the light of non-

challenging the speaking order 16.10.2017 (Annexure P-8).

20. Learned counsel for the petitioner has referred to a letter dated

02.11.2015 (Annexure P-10) addressed by the Estate Officer, HUDA,

Kurukshetra to the Administrator, HUDA, Panchkula, wherein it has been

stated that out of 5 plots, 4 plots have been constructed, whereas one bara is

lying vacant and if the land in question is released, services of the sector

would not be affected in any manner. This contention of the learned

counsel for the petitioner cannot be accepted in the light of para 4 of the

said letter where it has clearly been stated that release of these baras would

affect the site of plots of 4 marla. Since the land in question affects the

sites of three plots of 4 marla and 9 meter wide road, his land, in any case,

15 of 16

CWP No.30077 of 2017

cannot be released as it would directly affect the planning.

21. In view of the above, we do not find any merit in these writ

petitions and therefore, dismiss the same.




                                     (AUGUSTINE GEORGE MASIH)
                                             JUDGE


01.02.2022                              (MEENAKSHI I. MEHTA)
Harish                                         JUDGE


      Whether speaking/reasoned:                         Yes/No
         Whether Reportable:                             Yes/No




                                     16 of 16

 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter