Wednesday, 17, Jun, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ram Lal & Ors vs State Of Haryana & Ors
2022 Latest Caselaw 319 P&H

Citation : 2022 Latest Caselaw 319 P&H
Judgement Date : 1 February, 2022

Punjab-Haryana High Court
Ram Lal & Ors vs State Of Haryana & Ors on 1 February, 2022
                                                                                (1)
CWP No.5379 of 2016



        IN THE HIGH COURT OF PUNJAB AND HARYANA AT
                     CHANDIGARH

                                    CWP No.5379 of 2016
                                    Pronounced on: 01.02.2022

Ram Lal & others
                                                               ...Petitioners
                                    Versus

State of Haryana & others
                                                               ...Respondents

CORAM: HON'BLE MR. JUSTICE AUGUSTINE GEORGE MASIH
       HON'BLE MRS. JUSTICE MEENAKSHI I. MEHTA

Present:     Mr. Ajay Jain, Advocate,
             for the petitioners.

             Mr. Ankur Mittal, Addl. A.G., Haryana with
             Ms. Kushaldeep Kaur, Advocate, for the respondents.
                        *****

AUGUSTINE GEORGE MASIH, J.

By filing the present writ petition, petitioners have

challenged notification dated 26.09.2007 (Annexure P-1) issued under

Section 4 of the Land Acquisition Act, 1894 (hereinafter referred to as

'1894 Act'), notification dated 25.09.2008 (Annexure P-2) issued under

Section 6 of the 1894 Act and the award dated 24.09.2010 (Annexure

P-6).

2. Counsel for the petitioners asserts that the petitioners are

assailing the acquisition proceedings qua the land measuring 2 Bigha and

13 Biswa comprised in Khasra No.31/2 situated in village Bhagwanpur,

Tehsil Kalka, District Panchkula, as their land measuring 3 Bigha and 10

Biswa has already been left out from the acquisition after considering the

objections filed by them under Section 5-A of 1894 Act and in pursuance

1 of 9

CWP No.5379 of 2016

to the recommendations made by the State Joint Inspection Committee

(for short 'SJIC'). Counsel for the petitioners asserts that on the land in

question, houses of the petitioners are existing, which they had

constructed much prior to the acquisition proceedings and till date, they

are in physical possession of the same. Reliance has been placed upon

the policy of the Government of Haryana dated 26.10.2007 (Annexure P-

7) to substantiate that along with the constructed house, proportionate

vacant area is to be kept out of the acquisition proceedings. In support of

his contention, learned counsel for the petitioners has also placed reliance

upon the decision of this Court dated 28.04.2021 (Annexure P-8) given

in LPA No.68 of 2008, titled as 'State of Haryana Vs. Kamlesh Rani.

Counsel for the petitioners contends that some land of the petitioners has

already been kept out of the acquisition on the ground that construction in

the shape of residential houses existed thereon. He, therefore, submits

that the land of the petitioners measuring 2 Bigha and 13 Biswa

comprised in Khasra No.31/2 situated in village Bhagwanpur, Tehsil

Kalka, District Panchkula, be also released and acquisition proceedings

qua the said land be quashed.

3. On the other hand, learned counsel for the respondents

submits that the father of petitioner No.1 and father-in-law of petitioner

No.2, namely Dhanna Ram, had filed objections under Section 5-A of

1894 Act. Mother of petitioners No.3 to 5, namely Smt. Kesho, had also

filed objections. The said objections were duly heard from 27.05.2008 to

29.05.2008 at PWD Rest House, Kalka and considering the same, land

2 of 9

CWP No.5379 of 2016

measuring 3 Bigha and 10 Biswa was recommended for release as there

were residential houses constructed at the time of issuance of notification

under Section 4 of 1894 Act and remaining land, which was vacant at that

time, was recommended for acquisition.

4. Learned counsel for the respondents further submits that the

possession of the land in question was taken vide Rapat No.72, dated

24.09.2010. It has further been asserted that the total amount of the

award of Rs.2,59,77,50,090/- was tendered and out of the same, an

amount of Rs.1,69,27,40,159/- has already been disbursed. Rest of the

amount could not be disbursed as the concerned landowners are not

coming forward to receive the same and not tendering the documents

regarding ownership etc. Further, as per the award statement, total

amount of compensation of the petitioners is Rs.1,34,63,885/-, which is

still pending as the petitioners are not coming forward to receive the same

and not tendering the requisite documents. The said amount would be

disbursed to the petitiones immediate on their demand and submitting

their documents.

5. Reliance has been placed upon the judgment of the Hon'ble

Supreme Court in Aflatoon & others Vs. Lt. Governor of Delhi &

others 1975 (4) SCC 285 to contend that the petitioners cannot be

allowed to raise this plea when the notifications under Sections 4 and 6

have never been challenged nor has the validity of the award been

attacked. There being dilatory tactics on the part of the petitioners, the

writ petition is liable to be dismissed on the ground of delay and laches

3 of 9

CWP No.5379 of 2016

on the part of the petitioners. Similarly, reliance has been placed upon

another judgment of the Hon'ble Supreme Court in Northern Indian

Glass Industries Vs. Jaswant Singh & others 2003 (1) SCC 335, where

writ petition was filed after almost 17 years of finalization of the

acquisition proceedings when the said proceedings have not been

challenged earlier and it being the settled proposition of the law that after

the passing of the award and after taking possession of the land, the

acquired land vests with the Government free from all incumbrances.

Delay and laches is itself a ground for dismissing the writ petition. It has,

in any case, been pressed by the counsel that the land of the petitioners is

essential for green belt, which is the part of the planning of the road and

the same would be effected.

6. Learned counsel for the respondents has placed reliance upon

the latest judgment of the Hon'ble Supreme Court in Indore

Development Authority Vs. Manoharlal and others 2020 (AIR) SC

1496 to submit that the land cannot be released from acquisition if

possession of the acquired land, for which the award has been passed, has

been taken through Rapat Roznamacha or even the amount of

compensation tendered. In this case, possession of the land in question

was taken vide Rapat No.72, dated 24.09.2010 and even the

compensation amount stands deposited, which the petitioners have not

taken. He, therefore, submits that the land in question cannot be released.

7. His further submission is that since the land in question

affects the site of 12 meters wide service lane to the main road, the same

4 of 9

CWP No.5379 of 2016

cannot be released. Since the compensation amount has been duly

deposited with the Land Acquisition Collector and further, the possession

has been taken vide Rapat No.72, dated 24.09.2010, the writ petition

deserves to be dismissed.

8. We have considered the submissions made by the learned

counsel for the parties and with their assistance have gone through the

pleadings as well as the various judgments passed by the Hon'ble

Supreme Court.

9. The facts, as have been narrated above, have not been

disputed. Notifications under Sections 4 and 6 of the 1894 Act were

issued on 26.09.2007 (Annexure P-1) and 25.09.2008 (Annexure P-2)

respectively, leading to the passing of the award dated 24.09.2010

(Annexure P-6). Petitioners are asserting themselves to be the owners in

possession of the land measuring 2 Bigha and 13 Biswa comprised in

Khasra No.31/2 situated in village Bhagwanpur, Tehsil Kalka, District

Panchkula, and are seeking release of the same from acquisition.

10. The main argument of the learned counsel for the petitioners

that on the land in question, houses of the petitioners existed prior to the

issuance of notification under Section 4 of 1894 Act, cannot be accepted

in the light of the specific stand taken by the respondents in the reply that

after hearing and considering the objections filed by Dhanna Ram and

Smt.Kesho, predecessors of the petitioners, land measuring 3 Bigha and

10 Biswa was released on the same ground that houses existed thereon

prior to issuance of notification under Section 4 of the 194 Act and

5 of 9

CWP No.5379 of 2016

remaining land was recommended for acquisition as the same was lying

vacant. Learned counsel for the petitioners has failed to produce any

documentary evidence which would show that the houses of the

petitioners were in existence on the land in question prior to issuance of

notification under Section 4 of 1894 Act. Merely by placing on record

two photographs (Annexures P-9 and P-10) to prove that houses of the

petitioners were in existence on the land in question at the time of

acquisition cannot substantiate that the said houses were existed prior to

issuance of notification under Section 4 or even constructed on the land

in question or on some other land. Petitioners have not been able to place

on record any document in support of this argument and having failed to

do so, this contention of the learned counsel for the petitioners cannot be

accepted especially when their land measuring 3 Bigha and 10 Biswa has

been left out of acquisition on the same ground that certain houses were

in existence prior to issuance of notification under Section 4 of the 1894

Act. Learned counsel for the petitioners has also been unable to explain

as to how some land of the petitioners could be released on the ground

that there being houses existed prior to issuance of notification while

acquiring the adjacent land and not releasing it, had there been any

construction thereon. If the houses would have been constructed on the

land in question prior to the issuance of notification under Section 4, the

land in question would have also been released along with the land which

has been recommended for release i.e. 3 Bigha and 10 Biswa.

For the above mentioned facts and reasons, petitioners would

6 of 9

CWP No.5379 of 2016

not be entitled to any benefit of the policy of the Government of Haryana

dated 26.10.2007 (Annexure P-7) and the decision of this Court dated

28.04.2021 (Annexure P-8) given in LPA No.68 of 2008, titled as 'State

of Haryana Vs. Kamlesh Rani', on which reliance has been placed by

them.

11. Further, it has been specifically stated in the reply which has

been filed to this writ petition that the possession of the land in question

has already been taken vide Rapat No.72, dated 24.09.2010. It has also

been stated that the total amount of the award of Rs.2,59,77,50,090/- was

tendered and out of the same, an amount of Rs.1,69,27,40,159/- has

already been disbursed and rest of the amount could not be disbursed as

the concerned landowners are not coming forward to receive the same or

are not tendering the documents regarding ownership etc. As per the

award statement, total amount of compensation of the petitioners is

Rs.1,34,63,885/-, which stands deposited and is still pending as the

petitioners are not coming forward to receive the same and not tendering

the requisite documents. The said amount would be disbursed to the

petitioners immediately on their demand and submitting their documents.

12. Paras 244 and 245 of the judgment in Indore Development

Authority's case (supra) deal with the vesting of the land in the State on

taking of possession of the acquired land for which the award has been

passed free from encumbrances. The taking of possession through Rapat

Roznamacha entry has been held to be a valid mode of taking possession

of land. The person retaining possession thereafter is to be treated as a

7 of 9

CWP No.5379 of 2016

trespasser as he does not have any right to continue in possession of the

land, which has vested in the State. Possession of the land has been taken

vide Rapat Roznamacha No.72, dated 24.09.2010, thus, fulfilling one of

the conditions with regard to the possession having been taken over

especially in the light of the fact that the possession through rapat

roznamacha has been held to be valid mode of taking possession of the

land.

13. Para 203 of the judgment in Indore Development Authority's

case (supra) deals with the word 'paid' and it has been concluded in para

206 that when the amount has been tendered, the obligation has been

fulfilled by the Collector. In case a person does not collect the amount,

he cannot take the benefit of the same by asserting that the amount has

not been paid to him.

14. It may also be added here that the petitioners themselves have

admitted in para 5 of the writ petition that a Reference under Section 18

of 1894 Act has been filed by petitioners No.1 and 2 before the

Competent Court for enhancement of compensation amount, which

would not entitle them to release the land in question. The Hon'ble

Supreme Court, in para 363 (5) of the judgment in Indore Development

Authority's case (supra), has held that the landowners, who have filed a

reference for higher compensation, cannot claim release of their land and

therefore, the petitioners cannot be held eligible for claiming the said

benefit.

15. Further, in the light of the judgments of the Hon'ble Supreme

8 of 9

CWP No.5379 of 2016

Court in the cases of Aflatoon and Northern Indian Glass Industries

(supra), the present petition is not maintainable as the impugned

notifications under Sections 4 and 6 of the 1894 Act have never been

challenged by the petitioners and the present petition has been filed after

about 6 years of the finalization of the acquisition proceedings. The

petitioners should have approached this Court immediately after the

issuance of notification dated 25.09.2008 (Annexure P-2) under Section 6

when the land in question was recommended for acquisition. It appears

to be the delaying tactics on the part of the petitioners to continue in

illegal possession when the land stands vested in the Government free

from all incumbrances and therefore, the writ petition is liable to be

dismissed on the ground of delay and laches.

16. That apart, since the land in question affects the site of 12

meters wide service lane, which is essential for public purpose and thus,

the same cannot be released as it would directly affect the planning.

17. In view of the above, we do not find any merit in the present

writ petition and therefore, dismiss the same.



                                        (AUGUSTINE GEORGE MASIH)
                                                JUDGE



01.02.2022                                (MEENAKSHI I. MEHTA)
Harish
                                                 JUDGE

      Whether speaking/reasoned:                            Yes/No
         Whether Reportable:                                Yes/No



                                         9 of 9

 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter