Citation : 2022 Latest Caselaw 16909 P&H
Judgement Date : 15 December, 2022
CR-80-2019(O&M) -1-
IN THE HIGH COURT OF PUNJAB AND HARYANA AT
CHANDIGARH
CR-80-2019(O&M)
Date of decision:-15.12.2022
Narender
...Petitioner
Versus
Sub-Divisional Officer and another
...Respondents
CORAM: HON'BLE MR.JUSTICE H.S.MADAAN
Present: Mr.R.S. Dhull, Advocate
for the petitioner.
Mr.Randeep Tanwar, Advocate for
Mr.P.K. Dwivedi, Advocate
for respondents No.1 and 2.
Mr.CP Tiwana, Advocate
for respondent No.3.
****
H.S. MADAAN, J.
1. In nutshell, facts of the case are that plaintiff Narender had
filed a suit for declaration and injunction against Sub-Divisional Officer,
Operation Sub Division UHBVN Pundri, District Kaithal and Uttar
Haryana Bijli Vitran Nigam Ltd. (hereinafter referred to as UHBVN Ltd.)
through Managing Director, Panchkula restraining the defendants from
disconnecting the electricity connection bearing No.AP-1019 installed in
land bearing Khewat No.1762-63, khatoni No.2191, rect.no.195, killa
Nos.18, 19, 20 comprised in two kittas as per jamabandi for the year
2013-14 within the revenue estate of village Pai, Tehsil Pundri, District
Kaithal.
2. As per the case of the plaintiff, initially the connection was
1 of 9
CR-80-2019(O&M) -2-
issued in the name of Ram Sarup son of Ranpat father of the plaintiff and
after his death the plaintiff along with his brother Gajender Singh moved
an application before the defendants to get the connection transferred in
their name; accordingly, the defendants changed the ownership with
regard to connection in the name of plaintiff; since then the plaintiff have
been regularly paying the electricity bills, however, the defendants issued
notice bearing No.MN-1671 dated 12.6.2017 calling upon the plaintiff to
submit original documents regarding change of name of said connection
as they were not satisfied with the report of Patwari; the plaintiff did
submit those documents but the defendants again issued a notice dated
14.9.2017 threatening to change/cancel the electricity connection from the
name of plaintiff; the plaintiff got the demarcation of the land conducted
and it transpired that a tubewell is installed in killa no.19, rect. No.195,
however due to mistake of revenue officials said tubewell connection was
shown in killa no.18 of rect. no.195 and for that reason, defendants
threatened to cancel the transfer of said connection in the name of plaintiff
and to disconnect the connection forcibly and illegally to which they have
no right. On refusal of defendants to concede his claim, the plaintiff had
filed the suit in question. Along with that suit, he moved an application for
grant of ad interim injunction.
3. On getting notice, the defendants put in appearance and filed
written statement and written reply contesting the suit as well as
application for grant of ad interim injunction. As per version of the
defendants, the plaintiff had applied for changing the name of the
electricity connection from the name of his father to his name as well as
2 of 9
CR-80-2019(O&M) -3-
that of his brother Gajender Singh in the month of February, 2016 along
with the documents, which included copy of jamabandi for the year 2013-
14 duly verified by the Halqa Patwari on 22.6.2015 pertaining to land
comprised in Khewat No.1762/1626, khatoni No.2191, rect. no.195, killa
no.18 and 19 within revenue estate of village Pai Tehsil Pundri, District
Kaithal and Aksh-sizra pertaining to killa no.18 of rect. no.195 verified by
the patwari on 2.7.2013; the jamabandi revealed that one tubewell
connection was installed in killa no.18 and the plaintiff along with his
brother Gajender Singh was owner of the land in question; the plaintiff
and his brother Gajender Singh had submitted their duly sworn affidavits ,
therefore, the electric connection was transferred in the name of plaintiff;
thereafter, one Raghvinder son of Ram Sarup moved an application in the
office of Executive Engineer Operation Division, UHBVN, Pundri
contending that connection in dispute is being run in his fields but had
been wrongly transferred in the name of plaintiff; he further requested to
get spot verification done by revenue patwari; the Executive Engineer
vide his letters bearing No.Ch.177/EB-20 dated 24.3.2017 and
Ch.179.EB-20 dated 7.4.2017 had directed SDO, Sub Division No.2,
UHBVN, Pundri to investigate the matter and submit his report; SDO
accordingly inquired into the matter and upon physical verification he
found that connection in dispute is being run in village Pai in the name of
Ram Sarup son of Ranpat, who died on 27.7.2008; Ram Sarup had four
sons namely Narender Kumar, plaintiff, Gajender, Raghuvinder and
Rajinder; during inquiry Raghuvinder produced the report by Halqa
Patwari from which it was found that a tubewell connection was being run
3 of 9
CR-80-2019(O&M) -4-
in killa no.13/8/1 of khasra no.195; Raghuvinder further produced another
report of Halqa Patwari wherein no tubewell connection was found in
killa No.18 of rect. no.195; defendant No.1 vide office memo no.1671
dated 12.6.2017 asked the plaintiff to explain the facts but the plaintiff did
not respond; a reminder was sent to him vide memo dated 14.9.2017; the
plaintiff submitted his reply but the same was not found to be satisfactory;
on 2.2.2018, defendant no.1 along with Ram Kumar and Vinod Jangra,
Junior Engineers and Dharambir, Lineman inspected the fields of the
plaintiff in his presence finding the plaintiff to be consuming direct supply
of the connection from LT Pole with the help of 4 Core PVC without any
connection; accordingly, LL-1 report was prepared, which plaintiff
refused to sign; the videography of the proceedings was got done and the
plaintiff was served with notice of assessment of penalty dated 5.2.2018
and Rs.30,000/- was imposed as penalty. It is contended that plaintiff had
intentionally not impleaded his brother Raghuvinder as a party in the suit,
therefore, the suit is bad for non-joinder of necessary parties. The
defendants prayed for dismissal of the suit and application.
4. After hearing arguments, the trial Court of Civil Judge
(Jr.Divn.), Kaithal vide order dated 8.2.2018 directed the parties to
maintain status quo qua the connection till the disposal of the suit.
5. Feeling aggrieved by that order, plaintiff Narender had
preferred an appeal before District Judge, Kaithal, which was assigned to
learned Additional District Judge, who vide judgment dated 28.9.2018
allowed the appeal partly and order dated 28.2.2018 was modified to the
extent that defendants are restrained from recovering whole of the penalty
4 of 9
CR-80-2019(O&M) -5-
amount till final disposal of the case.
6. However, the plaintiff Narender felt dissatisfied with the
order and has approached this Court by way of filing the present revision
petition, notice of which was issued to respondents, who put in
appearance.
7. I have heard learned counsel for the parties besides going
through the record.
8. Ad interim injunction dealt with by Order 39 Rules 1 & 2
CPC is a discretionary equitable relief, which is to be granted by the Court
keeping in view all the facts and circumstances including the conduct of
the parties, if the necessary ingredients for grant thereof are fulfilled, to
say the plaintiff having a good prima facie case, balance of convenience
being in favour of the plaintiff and plaintiff suffering irreparable loss and
injury in case of denial of ad interim injunction with all those ingredients
existing conjunctively. For laying basis for grant of permanent injunction,
a person approaching the Court must do so with clean hands disclosing all
the material facts and if he or she tries to conceal any material fact from
the Court, then such relief is not to be granted. Clause (i) of Section 41 of
the Specific Relief Act provides that an injunction cannot be granted when
the conduct of the plaintiff or his agents has been such as to disentitle him
to the assistance of the Court.
9. In light of such basic principles if the case of the plaintiff is
examined then it comes out that petitioner/plaintiff is certainly not entitled
to grant ad interim injunction. The trial Court without due application of
mind and keeping in view the relevant legal position disposed of the
5 of 9
CR-80-2019(O&M) -6-
application directing the parties to maintain status quo over the connection
till disposal of the suit. Such order goes to show that the trial Court lacked
clarity of vision in the matter and was unable to reach a clear conclusion
under the circumstances of the case. As it borne out from the record
plaintiff Narender had applied for changing the electricity connection
from the name of his father to his name as well as that of his brother
Gajender in the month of February, 2016 enclosing copy of jamabandi for
the year 2013-14 with such application. That jamabandi pertained to land
Khewat No.1762/1626, khatoni No.2191, rect. no.195, killa no.18 and 19
within revenue estate of village Pai Tehsil Pundri, District Kaithal.
Another document attached i.e. Aksh-sizra pertaining to killa no.18 of
rect. no.195 also verified by the patwari. The jamabandi reflected that the
tubewell connection was there in killa no.18, which was ownership of
plaintiff and his brother Gajender Singh. On that basis of affidavits
submitted by plaintiff and Gajender Singh, the tubewell connection was
transferred in the name of the plaintiff, however, Raghuvinder, a brother
of plaintiff had submitted an application in the office of Executive
Engineer Operational Division, UHBVNL, Pundri that connection to the
tubewell was there in his fields but was wrongly transferred in the name
of the plaintiff. He had requested for spot verification. The officers of
electricity department had inquired into the matter and it was found that
tubewell connection was being run in killa no.13/8/1 of khasra no.195
and as per report of Halqa Patwari no tubewell connection was there in
killa no.18 of rect. no.195. When the electricity department asked the
plaintiff to explain this fact, he opted to remain mum first, however later
6 of 9
CR-80-2019(O&M) -7-
on submitted written response, which was not found to be satisfactory.
Rather on spot inspection being carried out by officers of electricity
department in his presence, the plaintiff was found to be stealing
electricity by consuming a directing supply from LT pole with the help of
4 Core PVC without any connection. The proceedings there were got
videographed and plaintiff was served notice for recovery of penalty of
Rs.30,000/-. Furthermore, the plaintiff had not impleaded his brother
Raghuvinder, who was also an effected party in the matter. For all these
reasons, the plaintiff could not be said to have a good prima facie case or
balance of convenience being in his favour or he is suffering any
irreparable loss and injury in case of denial of ad interim injunction to
him. Rather he comes out to be a scheming type of person using unfair
means to get the tubewell connection transferred in his name not
hesitating to conceal material facts, rather trying to propagate falsehood to
achieve his aim. The trial Court in order has though noticed all these
things but has conveniently opted not to take those into consideration and
found a convenient way of directing the parties to maintain status quo
which is vague type of order having grave consequences, many a times
giving rise to quarrels and fights between the parties. The order passed by
learned Additional District Judge, Kaithal also comes out to be result of a
very casual approach without any attempt to consider the mater in a
proper perspective after trying to understand the factual and legal position
properly. Rather learned Additional District Judge, Kaithal deviated from
the main controversy and restrained the defendants from recovering the
penalty amount imposed upon the plaintiff till final disposal of the case, in
7 of 9
CR-80-2019(O&M) -8-
the process learned Additional District Judge, Kaithal perhaps forgot that
one of the basic ingredients for grant of ad interim injunction is suffering
of irreparable loss and whenever a loss can be calculated in terms of
money normally at ad interim injunction is not granted. Here with specific
allegations of theft of electricity being there against the plaintiff/appellant,
such type of relief should not have been granted by the learned Additional
District Judge to the plaintiff appellant.
10. It may be mentioned here that when the matter came up
before this Court, there also petitioner tried to play over smart as is
evident from the interim orders passed in the case, the petitioner was
successful in getting an order from the Court with regard to restoration of
the electricity connection. The order was passed in that regard on
28.5.2019, However, vide order dated 3.7.2019, the Court observed that
order dated 28.5.2019 appears to have been obtained by dubious means
since in any case the petitioner had failed to implead the applicant
Raghuvinder as one of the necessary parties in the revision petition, after
suppressing that his application for such impleadment had already been
allowed by the trial Court. For that reasons, direction contained in the
earlier order dated 28.5.2019 was recalled.
11. Such conduct of the petitioner/plaintiff is to be viewed with
all the seriousness and not lightly. Granting a discretionary equitable relief
to a litigant who indulges in unfair practise of concealing material facts
adopting dubious means and whose conduct is otherwise shoddy is most
uncalled for and that would rather result in failure of justice.
12. Here it may be mentioned that both the impugned orders are
8 of 9
CR-80-2019(O&M) -9-
arbitrary, perverse and passed ignoring the necessary ingredients provided
under Section 41 (i) of the Specific Relief Act, which provides that
injunction would be refused when conduct of plaintiff has been such as to
disentitle him to the assistance of the Court.
13. The revision petition is without merit and the same stands
dismissed. While exercising power under Section 227 of the Constitution
of India, the order passed by the trial Court as well as by learned
Additional District Judge, Kaithal are also set aside, resultantly,
application for ad interim injunction filed by the applicant/plaintiff is
dismissed.
Since the main revision petition has been dismissed, the
miscellaneous application(s), if any, stand disposed of accordingly.
15.12.2022 (H.S.MADAAN)
Brij JUDGE
Whether reasoned/speaking : Yes/No
Whether reportable : Yes/No
9 of 9
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!