Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Ramay Enterprise vs The Union Of India And Ors
2025 Latest Caselaw 4132 Patna

Citation : 2025 Latest Caselaw 4132 Patna
Judgement Date : 14 October, 2025

Patna High Court

M/S Ramay Enterprise vs The Union Of India And Ors on 14 October, 2025

         IN THE HIGH COURT OF JUDICATURE AT PATNA
                    Civil Writ Jurisdiction Case No.13010 of 2016
     ======================================================
     M/s Ramay Enterprise, through it's Managing Partner Birendra Singh, Son of
     Late Mohan Singh Resident of Khiriawan Bhawan Piparpati New Area, Gaya,
     P.S. - Kotwali, District - Gaya.

                                                       ... ... Petitioner/s
                                  Versus
1.   The Union Of India through the Divisional Railway Manager Eastern
     Central Railway Danapur.
2.   The Divisional Railway Manager Eastern Central Railway Danapur.
3.   The Divisional Engineer Eastern Central Railway, Danapur.
4.   The Divisional Finance Manager/Senior Accounts Officer Eastern Central
     Railway Danapur.
5.   The Sectional Engineer (Rail Path) Eastern Central Railway Jehanabad.

                                               ... ... Respondent/s
     ======================================================
     Appearance :
     For the Petitioner/s   :     Mr. Shivendra Prasad, Advocate
     For the Respondent/s   :     M/s Dr. Priya Gupta, CGC
     ======================================================
        CORAM: HONOURABLE JUSTICE SMT. G. ANUPAMA CHAKRAVARTHY
                                ORAL JUDGMENT
                                Date : 14-10-2025

                  1 The petitioner has filed the instant

      application for the following reliefs:

                                     "for        issuance           of       an
                      appropriate         writ/writs,        order/orders
                      direction/ directions to the respondent
                      authorities       to     make         payment          of
                      outstanding dues bill amount relating to
                      the contract work namely
                                     "The       through            turn   out
                      renewal of existing point and crossing
                      with 52 kg fan shaped curve switches
                      and renewal of derailing switches with
 Patna High Court CWJC No.13010 of 2016 dt.14-10-2025
                                           2/6




                          52 kg new one in P.G. sector of Danapur
                          Railway Division"
                                            With interest as the work
                          aforesaid contract of which was given to
                          the      petitioner          has    already      been
                          completed and though the final bill of
                          the work has already been prepared
                          and submitted but only part of the total
                          bill amount has been paid to the
                          petitioner and remaining bill amount
                          has still not been paid to the petitioner.
                          The petitioner further prays for any
                          other relief(s) for which the petitioner
                          may be found entitled in the facts and
                          circumstances of the present case."


                           2.    The brief facts as culled out from

         the petition are that the petitioner, a registered

         contractor, participated in Tender Notice No. W-

         7/Tender/02/Open/DNR/07-08                     dated    06.06.2007,

         floated by the Railways for the aforementioned

         contract        work.       Upon        successful     bidding,    the

         contract was duly awarded to the petitioner. It is

         submitted that the petitioner was directed by the

         Divisional Engineer, to deposit the performance

         guarantee and commence the work, which he did
 Patna High Court CWJC No.13010 of 2016 dt.14-10-2025
                                           3/6




         accordingly.

                           3. It is          submitted by the Learned

         counsel for the petitioner that                       due to non-

         availability of essential railway materials and

         simultaneous extension of time in the project area,

         the execution of the contract work was delayed.

         Multiple extensions for the date of completion were

         sought and it was subsequently, granted by the

         respondent authorities.

                           4. It is further submitted that                 after

         completion of the work, the final bill was duly

         prepared and submitted. However, the outstanding

         dues       amounting           to       Rs.4,63,520.72     was     not

         released           despite          repeated        requests       and

         representations             made        by    the   petitioner.    The

         petitioner claims that                   withholding of dues is

         arbitrary and in violation of his constitutional

         rights.

                           5. A counter affidavit was filed by the

         respondent Nos. 2 to 6.

                           6. It is submitted by the Learned

         counsel for the respondents that the petitioner
 Patna High Court CWJC No.13010 of 2016 dt.14-10-2025
                                           4/6




         failed to         attend on the date of the final joint

         measurement. The last date of completion                           was

         31.10.2010

, and it is stated that the petitioner only

appeared for final measurement in July 2011, after

a lapse of nearly nine months. By that time, was

the said work was deleted from the sanctioned

works list (commonly referred to as the Railway

"Pink Book") i.e. end of financial year. It is

contended the delay in completion that was

attributable solely to the petitioner, due to his

casual approach and failure to deploy adequate

manpower and equipment. The date of completion

was extended five times, on request of petitioner.

7. It is further submitted that all other

dues, including the performance guarantee and

security deposit, have been paid to the petitioner

and the respondents are in the process of re-

appropriating the required funds to facilitate

payment of the final bill and have assured that the

amount will be disbursed once such re-

appropriation is complete.

8. Heard the Learned counsel for the Patna High Court CWJC No.13010 of 2016 dt.14-10-2025

petitioner as well as the Learned counsel

appearing for the respondents and perused the

materials available on record.

9. It is not in dispute that the work in

question has been completed and that the final bill

for Rs.4,63,520.72 has been prepared and

submitted. The only ground taken by the

respondents for non-payment of the said amount is

the delay on the part of the petitioner in witnessing

the final measurement, which allegedly resulted in

deletion of the work from the sanctioned list and

thereby deletion of funds allocated for the said

project. While there may have been lapses on the

part of the petitioner in timely execution and

witnessing of final measurements, the fact remains

that the work in question has been completed to

the satisfaction of the Railways and a final bill has

been drawn. The petitioner cannot be made to

suffer indefinitely due to procedural lapses and

inter-departmental fund management issues of the

respondent authorities.

10. Admittedly, the work was Patna High Court CWJC No.13010 of 2016 dt.14-10-2025

completed by 31.10.2010. The petitioner waited

for 6 long years to his payment and was continued

to file the present Writ petition. This Court is of the

considered view that the respondents are under a

legal obligation to ensure payment of the said

contractual dues, after necessary re-appropriation

of funds.

11. In view of the foregoing discussion,

the writ petition is allowed. The respondents are

directed to release the outstanding amount of

Rs.4,63,520.72 to the petitioner within a period of

two months from the date of receipt / production of

a copy of this order.

12. With the above observations and

directions, the writ petition is allowed.

13. Interlocutory Application, if any,

shall stands disposed of.

(G. Anupama Chakravarthy, J) Spd/-

AFR/NAFR                NAFR
CAV DATE                NA
Uploading Date          15.10.2025
Transmission Date
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter