Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sify Digital Services Limited vs The State Of Bihar Through Additional ...
2025 Latest Caselaw 4128 Patna

Citation : 2025 Latest Caselaw 4128 Patna
Judgement Date : 14 October, 2025

Patna High Court

Sify Digital Services Limited vs The State Of Bihar Through Additional ... on 14 October, 2025

Author: P. B. Bajanthri
Bench: Alok Kumar Sinha, P. B. Bajanthri
          IN THE HIGH COURT OF JUDICATURE AT PATNA
                   Civil Writ Jurisdiction Case No.13538 of 2025
     ======================================================
     SIFY Digital Services Limited having its Registered Office at 2nd floor
     TIDEL PARK No.4, Canal Bank Road Taramani, Chennai-600113, E-mail-
     [email protected] through its Authorised Officer Sanjeev Kumar
     Agrawal, aged about 50 years, s/o Late Shri P.N. Agrawal, r/o G-3, Plot
     No.296, Sector-4, Vaishali, Ghaziabad, Uttar Pradesh-201010,

                                                             ... ... Petitioner/s
                                        Versus
1.   The State of Bihar through Additional Chief Secretary, Education
     Department, Patna, Government of Bihar Vikash Bhawan, New Secretariat,
     Patna-800015, Bihar, E-mail- [email protected]
2.   The Chairman, Bihar School Examination Board (BSEB), Sinha Library
     Road,    (Near  Sinha   Library),  Patna-800017,  Bihar,   E-mail-
     [email protected]
3.   The Director, State Council of Education Research and Training (SCERT)
     Mahendru,       Patna    (Bihar),    Pin    No.     800006,      E-mail-
     [email protected]

                                               ... ... Respondent/s
     ======================================================
     Appearance :
     For the Petitioner/s:            Mr. Chitranjan Sinha, Sr. Advocate
                         :            Mr. P.N. Shahi, Sr. Advocate
                         :            Mr. Sriram Krishna, Advocate
     For the State       :            Mr. P.K. Shahi, Advocate General
                         :            Mr. P.K. Verma, Sr. Advocate, AAG-3
                         :            Mr. Sanjay Kumar Ghosarvasy, AC to AAG-3
     For Respondent-BSEB :            Mr. Satyabir Bharti, Sr. Advocate
     ======================================================
     CORAM: HONOURABLE THE CHIEF JUSTICE
             and
             HONOURABLE MR. JUSTICE ALOK KUMAR SINHA
     CAV JUDGMENT
     (Per: HONOURABLE MR. JUSTICE ALOK KUMAR SINHA)

      Date : 14-10-2025

                            Heard the parties.

                       2. The petitioner in the writ application has prayed

      for following relief(s):

                                      "(i) To issue an appropriate writ, order,
                                      or direction, preferably in the nature of
 Patna High Court CWJC No.13538 of 2025 dt.14-10-2025
                                           2/34




                                         certiorari, for quashing and setting
                                         aside      the    impugned     order   dated
                                         22.07.2025

(Annexure-P/24), whereby the Petitioner has been blacklisted till 31.03.2026 and the contract has been terminated.

(ii) To issue a writ, order, or direction in the nature of mandamus, commanding the Respondents to recall and withdraw the impugned order, and to restore the Petitioner's eligibility to participate in future tenders issued by the Respondent Department."

3. Learned Senior Counsel for the petitioner

submits that the present writ petition has been filed challenging

the order dated 22.07.2025 (Annexure-P/1), passed by

Respondent No.1, whereby the petitioner has been debarred

from participating in any future tenders issued by the Education

Department, Government of Bihar, up to 31.03.2026. The said

order, it is contended, is wholly arbitrary, non-speaking, and in

violation of the directions passed by this Hon'ble Court in

CWJC No.1292 of 2025, decided on 16.04.2025, wherein the

earlier order of blacklisting dated 31.12.2024 was set aside and

the matter was remanded to the authorities to reconsider the

petitioner's defence in accordance with law.

4. It is submitted that the petitioner is a Public Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

Limited Company duly incorporated under the provisions of the

Companies Act, 2013. The present petition has been instituted

through Shri Sanjeev Kumar Agrawal, AGM (Operations), who

is an Indian citizen duly authorized by virtue of Board

Resolutions dated 20.10.2023, 07.08.2025 and Authority Letter

dated 10.01.2025, copies whereof are annexed as Annexure-P/2

to P/4 to this writ petition.

5. It is submitted that on 22.09.2023, Respondent

No.1 floated a Request for Proposal (RFP) bearing NIT No.

Online Examination/Educational/2023/01 for "Selection of

Agency to Setup Online Examination System and Conduct

Online Examinations (Computer Based Test)". The scope of

work included end-to-end provisioning of facilities for

conducting Computer Based Tests (CBT), including necessary

hardware, manpower, and technical requirements (Annexure-

P/5). Pursuant to the pre-bid clarifications issued on 09.10.2023

(Annexure-P/6), it was categorically stated by the respondents

that the question papers would be provided by BSEB/SCERT,

and the bidder was only to provide a Question Paper Authoring

Tool (QP Authoring Tool).

6. Upon evaluation of bids, the petitioner was

declared L1, and a Letter of Intent dated 20.12.2023 (Annexure- Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

P/7) was issued in its favour. The contract was formally

executed on 13.03.2024 (Annexure-P/8), for a period of five

years, extendable by two years, at the rate of ₹170 per candidate

(excluding GST). The petitioner duly furnished the Performance

Bank Guarantee of ₹10 lakhs in compliance with the contractual

terms. Clause 12 of the Contract empowered the Respondent to

terminate and blacklist the vendor only upon the occurrence of

specified events and after issuance of a 30-day written notice,

followed by a further 15 days' notice before blacklisting, as

detailed in the Note appended to Clause 12.1.

7. It is submitted that, after the award of contract,

the petitioner successfully conducted several large-scale

examinations for the Department, including BSSTET 2023,

CTT-1 2024, D.El.Ed 2024, Simultala Residential School

Pravesh Pariksha 2024, and STET 2024, wherein over

15,25,450 candidates appeared without any complaint of

irregularity. However, during the Competency Test for Local

Body Teacher-II (CTT-2) Examination 2024, conducted from

23.08.2024 to 26.08.2024, a limited issue arose on the final day

of the examination i.e. 26.08.2024, where certain repetition of

questions occurred in six subjects. The error affected only 749

candidates out of 85,252, i.e., less than 1% of total examinees. Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

8. Learned Senior Counsel submits that the root

cause of the said repetition was the inordinate delay on the part

of SCERT in providing the question paper content. The content

for the first batch of 26.08.2024 was received late in the night of

25.08.2024, and for the second batch, the content was furnished

on the same day of the examination, with the last lot of

questions received as late as 12:30 PM for an exam scheduled at

3:00 PM. Due to such delay, and the necessity of curating

questions through the QP Authoring Tool--a time-intensive

process--the petitioner was left with inadequate time for review,

which inadvertently led to the said repetitions.

Subsequently, Respondent No.2, BSEB, constituted a six-

member committee to examine the incident. The petitioner duly

appeared before the said committee on 20.09.2024 and

submitted a written analysis (Annexure-P/9).

The Committee's Report dated 08.10.2024 (Annexure-P/10)

clearly held that SCERT was equally responsible for the errors,

observing that the furnishing of incomplete and delayed content

was the primary cause. The Committee recommended:

(a) Re-examination in seven subjects at the

petitioner's cost,

(b) Deduction of 25% penalty from the relevant Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

invoice, and

(c) Warning to the petitioner that any future lapse

may attract blacklisting.

9. In compliance with the said recommendations,

BSEB directed the petitioner vide letter dated 22.10.2024

(Annexure-P/11) to conduct a re-examination in seven subjects

for 823 candidates, which was successfully conducted on

13.11.2024, without any cost implication to the respondents.

Despite this, Respondent No.1 issued a show cause notice dated

01.11.2024 (Annexure-P/12) proposing blacklisting of the

petitioner. The petitioner was given less than 24 hours to

respond. The petitioner promptly submitted a detailed reply on

02.11.2024 (Annexure-P/14), explaining the factual

background, highlighting the delays by SCERT, and

demonstrating the petitioner's bona fides by having already

conducted the re-examination successfully.

However, the respondents, ignoring the reply, wrongly alleged

non-submission of the same and issued another communication

dated 11.11.2024 extending 15 days' time for response. It is

contended that this was a mere afterthought to cure the

procedural defect of having granted only 24 hours earlier. Even

then, the mandatory 30 days' termination notice, followed by 15 Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

days' blacklisting notice, as required under Clause 12, was never

issued.

10. Learned Senior Counsel for the petitioner

further submits that without granting any further opportunity of

hearing, Respondent No.1 passed an order dated 31.12.2024

(Annexure-P/17), terminating the contract and blacklisting the

petitioner indefinitely. The said order was passed without

considering the Committee's findings or the petitioner's defence

and was therefore perverse, disproportionate, and violative of

due process. Aggrieved thereby, the petitioner approached this

Hon'ble Court in CWJC No.1292 of 2025. This Hon'ble Court,

vide judgment dated 16.04.2025, set aside the blacklisting order

and remanded the matter for fresh consideration, observing that

the incident occurred primarily due to delay by SCERT, that the

petitioner had already rectified the lapse without demanding

additional cost, and that the impugned blacklisting was wholly

disproportionate. (Annexure-P/21)

11. Pursuant to the directions of this Hon'ble Court,

the Education Department issued a letter dated 30.06.2025

(Annexure-P/22) scheduling a hearing on 08.07.2025. The

petitioner, in compliance, submitted a comprehensive

representation dated 02.07.2025 (Annexure-P/23), reiterating Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

that the repetition of questions occurred due to circumstances

beyond its control and emphasizing that the re-examination had

already been successfully conducted. On 08.07.2025, the

hearing was held before the Secretary, Education Department,

through video conferencing, as he was not physically present in

his office (Annexure-P/24). During the said hearing, the

petitioner once again urged the authorities to consider the

findings of the six-member committee, the successful re-

examination, and the absence of any mala fide intention or

financial loss to the Department.

However, to the utter shock of the petitioner, Respondent No.1

passed the impugned order dated 22.07.2025 (Annexure-P/1),

de-barring the petitioner up to 31.03.2026. The said order not

only ignored the observations of this Hon'ble Court in CWJC

No.1292 of 2025 but also relied upon new and extraneous

grounds that were never part of the original show cause notice.

12. The learned Senior Counsel for the petitioner

most respectfully submits that the impugned order dated

22.07.2025 (Annexure-P/24) issued by the Respondent No.1,

whereby the Petitioner has been blacklisted till 31.03.2026 and

the termination of the contract has been reaffirmed, is wholly

arbitrary, illegal, and unsustainable in the eyes of law. The said Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

order is vitiated for non-application of mind, reliance on

extraneous considerations, and gross violation of the principles

of natural justice.

13. It is submitted that despite this Hon'ble Court

having been pleased to pass a specific and reasoned order dated

16.04.2025 in CWJC No. 1292 of 2025 (Annexure-P/22),

directing the Respondents to re-consider the issue afresh in light

of the Petitioner's explanation and the admitted delay on part of

the SCERT, the Respondents have acted in complete disregard

of the said directions and have mechanically re-issued an order

of debarment, thereby rendering the entire decision-making

process illegal and void-ab-initio.

The learned counsel for the Petitioner further submits that the

show cause notices dated 01.11.2024 and 11.11.2024

(Annexures-P/12 and P/13) merely referred to two specific

deficiencies, viz.,

(i) repetition of questions in six subjects of the

CTT-2 examination held on 26.08.2024, and

(ii) appearance of answer keys in 50 questions of

the subject "Home Science" (Class XI-XII).

However, in the impugned order, entirely new and unconnected

allegations were introduced concerning the BSTET Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

Examination, delay in publishing results, and minor

typographical issues in the question papers--none of which

were ever mentioned in the show cause notice or put to the

Petitioner for rebuttal.

14. It is respectfully submitted that the law is well

settled that a person cannot be penalized on grounds not

mentioned in the show cause notice, as held by the Hon'ble

Supreme Court in Gorkha Security Services v. Govt. (NCT of

Delhi), (2014) 9 SCC 105, wherein it was categorically laid

down that a show cause notice must specifically mention both

the allegations and the proposed action to be taken, failing

which the entire proceedings stand vitiated for violation of

natural justice.

The learned counsel for the Petitioner submits that even after

remand by this Hon'ble Court, the Respondent authorities have

failed to appreciate that the repetition of questions had occurred

solely due to the inordinate delay and deficiencies on part of

SCERT, which furnished the question banks at the eleventh

hour, leaving no reasonable time for the Petitioner to curate or

verify the papers before uploading.

15. It is further submitted that the petitioner, in

compliance with the directions of the Respondents and the Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

recommendations of the six-member committee, had voluntarily

conducted a re-examination on 13.11.2024, covering 823

candidates (including 749 affected candidates), without

demanding any additional cost from the Respondents. The said

re-examination was successfully concluded and the results were

duly published, thereby curing any alleged breach. A true copy

of the communication evidencing re-examination and

compliance is annexed hereto and marked as Annexure-P/18.

The learned counsel submits that Clause 12.1 of the governing

agreement (Annexure-P/8) clearly stipulates that termination

and blacklisting can be effected only after giving 30 days' prior

written notice to the vendor to remedy the alleged breach. In the

instant case, no such notice was ever issued. The impugned

order thus suffers from jurisdictional error, being passed in utter

violation of contractual provisions and statutory fairness.

It is also submitted that even under the note appended to Clause

12.1, blacklisting is to be a "natural consequence" of

termination, which presupposes that the termination itself is

validly effected after due notice. Since in the present case the

termination itself is bad in law, the consequential blacklisting

order automatically falls.

16. The learned Senior Counsel for the petitioner Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

further submits that the six-member committee constituted by

the Respondent No.2 (BSEB) had categorically concluded that

the SCERT was equally responsible for the deficiencies noticed

during the CTT-2 examination, and had therefore recommended

only the issuance of a warning, along with the imposition of a

limited penalty to the extent of 25% of the invoice value.

Despite this clear finding, the Respondents have chosen to

ignore the committee's recommendation and have proceeded to

impose a far more severe punishment, amounting to gross

disproportion. A copy of the six-member committee report is

annexed and marked as Annexure-P/19.

It is further contended that the impugned order also misreads the

Petitioner's letter dated 08.07.2025 (Annexure-P/23) as an

admission of fault, whereas the said letter was only an appeal

for reconsideration based on the understanding that the

Respondents would withdraw the blacklisting if the Petitioner

assured non-repetition in future. This benign communication has

been deliberately misconstrued to sustain the order of

debarment.

17. Per Contra, learned counsel for the

Respondents submits that the impugned order dated 22.07.2025

(Annexure-P/1) has been passed strictly in compliance with the Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

order dated 16.04.2025 of this Hon'ble Court rendered in

C.W.J.C. No. 1292 of 2025, wherein the matter was remitted for

reconsideration by the competent authority after affording due

opportunity to the Petitioner. It is, therefore, contended that the

impugned order is neither arbitrary nor passed in violation of

natural justice, but is based on proper fact finding and material

evidence on record.

18. The learned counsel for the Respondents further

submits that the tender in question, Tender No. Online

Examination / Education / 2023 / 01 dated 22.09.2023, was

floated by the Education Department, Government of Bihar for

the selection of an agency to establish a system and conduct

Computer-Based Tests (CBT) for various examinations. The

Petitioner's bid was accepted and a Letter of Intent bearing Ref.

No. 4/V1.16-87/2023-2322 dated 20.12.2023 (Annexure-P/7)

was issued, followed by a formal agreement executed on

13.03.2024 determining the terms and conditions of work. The

said agreement clearly stipulated under Clause 12 the provisions

for Termination and Blacklisting, which authorize the

Department to terminate the contract and blacklist the vendor

upon occurrence of enumerated events such as serious

discrepancies, failure to provide quality services, clumsy Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

execution of work, or non-compliance with lawful directions,

subject to issuance of a written notice of 30 days. It is also

specified that blacklisting/debarment shall be a natural

consequence of termination.

19. Learned counsel for the Respondents submits

that during the conduct of the Competency Test-2 (CTT-2) for

local body teachers scheduled between 23.08.2024 and

26.08.2024, several serious discrepancies were reported by the

Director, State Council of Educational Research and Training

(SCERT) through Letter No. 4095 dated 12.09.2024 (Annexure-

A to the personal affidavit). The said communication pointed out

repetition of questions in as many as seven subjects -- Hindi,

Music, Dance, Home Science, Persian (Classes IX-X), and

Home Science and History (Classes XI-XII) -- where multiple

questions were repeated across sets, thereby compromising the

sanctity of the examination.

Apart from repetition, other grave errors were detected, such as

--

(a) absence of images in questions where they were

essential, rendering them meaningless;

(b) misprinting of percentage signs and ratio

symbols as random characters;

Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

(c) incorrect alignment of bilingual questions

leading to confusion; and

(d) typographical disarray where English answer

options (A, B, C, D) were merged within Hindi text.

These errors, taken collectively, were indicative of gross

negligence and lack of quality control on part of the Petitioner

company.

In view of these lapses, the Respondents constituted a six-

member committee vide Memo No. K.V.644/2024 dated

17.09.2024 to inquire into the discrepancies. The committee,

after detailed scrutiny, submitted its report on 08.10.2024,

concluding that the Petitioner company was prima facie

responsible for the errors and had itself admitted fault through

its email dated 21.09.2024 (01:39 PM), wherein it accepted that

repetition of questions had occurred due to oversight during data

processing. Copies of the report and the said email were

annexed as Annexures-B and C to the personal affidavit of the

Secretary, Education Department.

20. Learned counsel for the Respondents points out

that the committee's findings were not based merely on

conjecture but on specific data samples and technical validation,

which revealed multiple instances of identical question IDs Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

recurring in different sets prepared by the Petitioner. The

committee, therefore, recorded a clear finding of "serious

discrepancies attributable to vendor's lapse." It is further

submitted that in consequence of the committee's report, show

cause notices were duly issued to the Petitioner vide Letter No.

2355 dated 01.11.2024 and Letter No. 714 dated 26.10.2024,

seeking specific explanations regarding the deficiencies noticed.

The Petitioner submitted its reply, which was duly considered

along with the opinions obtained from SCERT and Bihar School

Examination Board (BSEB).

Both SCERT and BSEB, after examining the Petitioner's

response, opined unequivocally -- through Letter No. 5843

dated 03.12.2024 and Letter No. K.V.784/2024 dated

16.12.2024 (Annexure-D series) -- that the Petitioner was

indeed at fault and primarily responsible for the flawed conduct

of the examination. These communications formed the

substantive basis for the Department's subsequent decision-

making process.

21. Consequently, the earlier order bearing Memo

No. 2723 dated 31.12.2024 was passed, which, however, came

to be set aside by this Hon'ble Court in C.W.J.C. No. 1292 of

2025, directing the Respondents to reconsider the issue afresh Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

after giving the Petitioner an opportunity of hearing. Pursuant to

this direction, a fresh show cause notice dated 30.06.2025 was

issued to the Petitioner (Annexure-P/22), and the Petitioner

again submitted its written explanation dated 02.07.2025

(Annexure-P/23) as well as a representation dated 08.07.2025,

both of which were duly examined.

22. The learned counsel for the Respondents

emphasizes that even in the representation dated 08.07.2025, the

Petitioner categorically admitted its lapse, stating inter alia that

"It was only in the last exam (CTT-2) where an issue of question

repetition occurred due to lack of time and unintentional

manual error..." and further undertook "to ensure that such

mistakes are never repeated." This admission clearly

demonstrates that the Petitioner's fault was neither disputed nor

denied, and hence, the Respondents acted within their

contractual and administrative competence.

It is further submitted that the impugned order dated 22.07.2025

(Memo No. 391) was thus passed after full compliance with the

directions of this Hon'ble Court, after due notice, opportunity of

hearing, and consideration of all relevant records and

representations. The impugned order is a reasoned and speaking

order, detailing the sequence of events, the nature of Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

deficiencies, and the basis for the decision to blacklist the

Petitioner till 31.03.2026.

23. Learned counsel for the Respondents contends

that the mistakes committed by the Petitioner were not minor or

technical in nature but grave operational failures that directly

affected the integrity of a large-scale State-level examination,

causing cancellation and re-conduct of seven subject papers,

leading to administrative delay and financial loss. Therefore,

invocation of Clause 12 of the Agreement and the consequential

blacklisting were lawful, justified, and proportionate to the

nature of default.

It is further contended that the principle of proportionality has

been duly observed, inasmuch as the Petitioner has been

blacklisted only till 31.03.2026, i.e., for a limited period, and

not permanently. The Department consciously refrained from

imposing any monetary penalty in addition to the blacklisting,

thereby exercising measured discretion in conformity with law.

24. The learned counsel for the Respondents finally

submits that the Petitioner cannot seek relief in equity when it

has admitted fault on multiple occasions and when its lapses

have been established by independent bodies like SCERT,

BSEB, and a duly constituted committee. The impugned order Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

thus does not suffer from any legal infirmity, arbitrariness, or

procedural violation, and the writ petition, being devoid of

merit, deserves to be dismissed in limine.

ISSUES IN QUESTION:

1. Whether the impugned order dated 22.07.2025

blacklisting the petitioner till 31.03.2026 was passed in violation

of the principles of natural justice or without affording due

opportunity of hearing and does it suffers from arbitrariness,

mala fides, or absence of material evidence justifying the action

of blacklisting?

2. Whether the lapses committed by the petitioner

in the conduct of the Competency Test-2 examination were

minor and technical in nature or amounted to serious operational

failures adversely affecting the examination process?

3. Whether the petitioner's express admission of

mistake in its email dated 21.09.2024 and letter dated

08.07.2025 establishes acknowledgment of fault, thereby

justifying the respondent's decision to take disciplinary action?

4. Whether the action of blacklisting the petitioner

till 31.03.2026 is disproportionate to the nature and gravity of

the default, and whether it violates the doctrine of

proportionality?

Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

5. Whether the impugned order was passed in

accordance with Clause 12 of the Agreement dated 13.03.2024

and in compliance with the directions issued by this Hon'ble

Court in C.W.J.C. No. 1292 of 2025?

FINDINGS:

Issue 1: Whether the impugned order dated 22.07.2025

blacklisting the petitioner till 31.03.2026 was passed in

violation of the principles of natural justice or without

affording due opportunity of hearing and does it suffers

from arbitrariness, mala fides, or absence of material

evidence justifying the action of blacklisting?

The contention of the petitioner that the impugned order has

been passed in violation of the principles of natural justice or

without affording a reasonable opportunity of hearing is wholly

unfounded. The records of the case reveal that a show cause

notice dated 30.06.2025 was duly issued to the petitioner prior

to the passing of the impugned order, calling upon it to furnish

its explanation regarding the discrepancies noticed in the

conduct of the Competency Test-2 examination. The petitioner

duly submitted its written reply dated 02.07.2025 and

subsequently made a representation dated 08.07.2025, both of

which were duly considered by the competent authority before Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

arriving at the final decision.

It is further evident from the materials placed on record that the

petitioner had also, in its email communication dated

21.09.2024, categorically admitted its fault with respect to the

repetition of questions in multiple subjects during the said

examination. The admission of such lapse was reiterated in its

representation dated 08.07.2025, wherein the petitioner accepted

that the error had occurred "due to lack of time and

unintentional manual error" and assured that necessary

corrective measures would be taken in future. Such

unambiguous admission of fault clearly negates any suggestion

of arbitrariness or absence of material evidence.

Moreover, the decision to blacklist the petitioner was not taken

in isolation but was preceded by a detailed fact-finding process.

A six-member committee, constituted vide memo no.

K.V.644/2024 dated 17.09.2024, conducted an inquiry,

examined the report submitted by the petitioner, and held the

agency responsible for grievous discrepancies which resulted in

cancellation and re-conduct of examinations in seven subjects.

The opinions furnished by the SCERT vide letter no. 5843 dated

03.12.2024 and by the BSEB vide letter no. K.V.784-2024 dated

16.12.2024 also concluded that the petitioner was at fault. Thus, Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

the impugned order was passed only after comprehensive

consideration of the inquiry report, the petitioner's replies, and

expert opinions from the statutory bodies.

In view of these facts, it is clear that the principles of natural

justice were duly complied with and the petitioner was afforded

adequate opportunity to present its case. There is no material on

record to substantiate any allegation of mala fides or

arbitrariness. The impugned order is a reasoned administrative

decision, based on documentary evidence, factual findings, and

admitted lapses on the part of the petitioner.

Accordingly, this Court finds that the impugned order dated

22.07.2025 does not suffer from violation of natural justice,

arbitrariness, or lack of material evidence, and has been passed

in due compliance with law and after observance of fair

procedure.

Issue 2: Whether the lapses committed by the petitioner in

the conduct of the Competency Test-2 examination were

minor and technical in nature or amounted to serious

operational failures adversely affecting the examination

process?

Upon careful examination of the records and materials placed

before this Hon'ble Court, it is evident that the lapses Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

committed by the petitioner in the conduct of the Competency

Test-2 (CTT-2) examination cannot, by any stretch of reasoning,

be termed as minor, technical, or inadvertent. On the contrary,

the evidence demonstrates that the irregularities were serious

operational failures that struck at the very foundation of the

examination system, thereby undermining its fairness,

reliability, and integrity.

The letter no. 4095 dated 12.09.2024 issued by the Director,

State Council of Education Research and Training (SCERT)

brought to the notice of the Bihar School Examination Board

(BSEB) multiple grave discrepancies in the examination

conducted by the petitioner. It was found that questions were

repeated in several subjects -- including Hindi, Persian, Music,

Dance, Home Science, and History -- at both Class 9-10 and

Class 11-12 levels. In addition to the repetition of questions,

there were missing images, incorrect symbols in mathematical

content, erroneous use of characters in place of ratios and

percentages, and improper alignment of bilingual question

papers.

These defects were not confined to isolated instances but were

systemic and widespread across multiple subjects. As a result,

the examination of seven subjects had to be cancelled and fresh Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

examinations were ordered, causing substantial administrative

inconvenience, financial burden, and delay in the overall

assessment process. Such large-scale disruption cannot be

characterized as a mere technical defect or clerical oversight.

The matter was thoroughly examined by a six-member inquiry

committee constituted under memo no. K.V.644/2024 dated

17.09.2024, which held its meeting on 04.10.2024 and

submitted its report on 08.10.2024. The committee, after

analyzing the materials and the petitioner's own report, recorded

categorical findings that the petitioner had failed to ensure

quality control and adequate scrutiny of the question bank and

the computer-based test system. The committee further noted

that the petitioner, through its email dated 21.09.2024, admitted

its fault in respect of question repetition and other discrepancies.

The subsequent opinions of both SCERT (letter no. 5843 dated

03.12.2024) and BSEB (letter no. K.V.784-2024 dated

16.12.2024) confirmed the committee's conclusion that the

lapses were serious and attributable solely to the petitioner's

negligence and inadequate supervision.

Given these findings, the lapses committed by the petitioner

were not minor deviations but amounted to serious operational

failures, leading to cancellation and rescheduling of Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

examinations -- an eventuality that gravely affected thousands

of candidates and tarnished the credibility of the examination

process. The magnitude of the default clearly justified

disciplinary action by the respondent authority in exercise of its

contractual and administrative powers.

Accordingly, this Court finds that the failures of the petitioner

were grave, systemic, and detrimental to the sanctity of the

examination process, and therefore cannot be categorized as

minor or technical lapses. The respondent's action in treating

these lapses as serious operational failures stands fully justified.

Issue 3. Whether the petitioner's express admission of

mistake in its email dated 21.09.2024 and letter dated

08.07.2025 establishes acknowledgment of fault, thereby

justifying the respondent's decision to take disciplinary

action?

Upon consideration of the materials available on record, this

Hon'ble Court finds that the petitioner's categorical admission

of error in its own communications -- namely, the email dated

21.09.2024 and the letter dated 08.07.2025 -- constitutes an

unequivocal acknowledgment of fault, which fully justifies the

respondent's decision to initiate and conclude disciplinary

proceedings culminating in the order of blacklisting. Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

The record reveals that after the conduct of the Competency

Test-2 (CTT-2) examination, serious discrepancies were

reported, leading to the constitution of a six-member inquiry

committee vide memo no. K.V.644/2024 dated 17.09.2024. In

the course of this inquiry, the petitioner, through its email

communication dated 21.09.2024 (01:39 PM), admitted to the

occurrence of repeated questions across several subjects,

attributing it to "unintentional manual error" and lack of

adequate time. The said email was placed before the committee,

which took specific note of this admission while recording its

findings.

The petitioner, in its subsequent representation dated

08.07.2025, reiterated this admission in clear terms,

acknowledging that "it was only in the last exam (CTT-2)

where an issue of question repetition occurred due to lack of

time and some unintentional manual error" and further

assuring that "We'd take all the necessary steps to ensure such

mistakes are never repeated." These statements, emanating

directly from the petitioner, leave no room for ambiguity or

denial of responsibility.

Such voluntary and repeated acknowledgment of fault, made

both contemporaneously during inquiry proceedings and later in Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

response to the show cause notice, demonstrates the petitioner's

acceptance of the lapses and their causal connection to the

irregularities in the examination process. In law, an admission

made by a party, especially when made voluntarily and without

coercion, constitutes the best form of evidence against the

maker thereof and requires no further corroboration unless

successfully retracted with plausible justification, which is

conspicuously absent in the present case.

The respondent authority, while exercising its contractual and

administrative powers under Clause 12 of the Agreement dated

13.03.2024, was therefore fully justified in treating the

petitioner's admission as conclusive proof of operational failure

and in taking consequential disciplinary action. The impugned

order of blacklisting was passed not on conjecture or suspicion,

but on self-admitted lapses duly supported by documentary

evidence, inquiry reports, and expert opinions from both SCERT

and BSEB.

In view of the foregoing, this Court holds that the petitioner's

express admission of mistake in its email dated 21.09.2024 and

letter dated 08.07.2025 amounts to acknowledgment of fault in

unequivocal terms, and such acknowledgment serves as a valid

and sufficient basis for the respondent to impose disciplinary Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

action. The respondent's decision, therefore, stands on firm legal

and factual foundation and cannot be said to be arbitrary or

unjustified in any manner.

Issue 4: Whether the action of blacklisting the petitioner till

31.03.2026 is disproportionate to the nature and gravity of

the default, and whether it violates the doctrine of

proportionality?

Having examined the facts, records, and sequence of events

leading to the issuance of the impugned order dated 22.07.2025,

this Hon'ble Court finds no merit in the petitioner's contention

that the action of blacklisting till 31.03.2026 is disproportionate

or violative of the doctrine of proportionality. On the contrary,

the record reflects that the respondent authority has acted with

due care, reasonableness, and in strict conformity with both

contractual provisions and judicial directions.

At the outset, it is pertinent to note that the initial order of

blacklisting, passed vide memo no. 2723 dated 31.12.2024, had

imposed blacklisting of the petitioner for an indefinite period.

The said order was subsequently set aside by this Hon'ble Court

in C.W.J.C. No. 1292 of 2025, with a direction to the competent

authority to reconsider the matter after granting proper

opportunity of hearing and after assigning reasons supported by Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

relevant material. Pursuant thereto, the Education Department

reconsidered the entire matter, issued a fresh show cause notice

dated 30.06.2025, obtained the petitioner's reply dated

02.07.2025 and representation dated 08.07.2025, and thereafter

passed the impugned order on 22.07.2025, restricting the period

of blacklisting only till 31.03.2026.

This deliberate reduction of the blacklisting duration--from an

indefinite period to a time-bound measure--demonstrates that

the authority has exercised its discretion judiciously, keeping in

view the principle of proportionality. The penalty now imposed

is neither excessive nor arbitrary; rather, it is commensurate

with the gravity of the proven misconduct.

The admitted lapses on the part of the petitioner in the conduct

of Competency Test-2 (CTT-2) resulted in large-scale

discrepancies, cancellation of examinations in seven subjects,

and consequential re-examination, thereby affecting thousands

of candidates and causing administrative dislocation. Such

lapses go to the root of the examination process, striking

directly at its credibility and fairness. In this backdrop,

disciplinary action, including temporary blacklisting, is both

justified and necessary to uphold institutional integrity and

public interest.

Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

The doctrine of proportionality requires that the administrative

action must balance the gravity of the offence with the severity

of the penalty. Here, the respondent's decision satisfies that test

-- the duration of blacklisting is limited, reasonable, and

reviewable after a definite period. It serves as a deterrent against

negligence while affording the petitioner a fair opportunity to

rehabilitate and resume business after the prescribed term.

Further, the decision is not punitive in isolation but based on

self-admitted lapses, corroborated by inquiry findings, and

expert opinions of SCERT and BSEB holding the petitioner

responsible. Hence, the respondent's action is grounded in

evidence and cannot be termed arbitrary or disproportionate.

Accordingly, this Court holds that the blacklisting of the

petitioner till 31.03.2026 is a measured, proportionate, and

legally sustainable action, duly aligned with the doctrine of

proportionality. The respondent has exercised its authority in a

fair, reasonable, and balanced manner, and therefore, the

impugned order does not warrant any interference.

Issue 5: Whether the impugned order was passed in

accordance with Clause 12 of the Agreement dated

13.03.2024 and in compliance with the directions issued by

this Hon'ble Court in C.W.J.C. No. 1292 of 2025? Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

Upon a thorough examination of the contractual provisions, the

sequence of proceedings, and the materials placed on record,

this Hon'ble Court finds that the impugned order dated

22.07.2025 was passed strictly in conformity with Clause 12 of

the Agreement dated 13.03.2024 and in faithful compliance with

the directions issued by this Hon'ble Court in C.W.J.C. No.

1292 of 2025.

Clause 12 of the Agreement between the petitioner and the

Education Department specifically empowers the Department to

terminate the agreement and blacklist or debar the vendor in the

event of certain defaults, including (a) material breach of

contractual obligations, (e) failure to provide quality services,

(f) serious discrepancy or delay in performance impacting

departmental functioning, and (h) failure to abide by lawful

directions of the Department. The clause further mandates that,

before imposing blacklisting, the Department shall issue a

notice giving 15 days' time to the vendor to explain its position.

In the present case, the records demonstrate scrupulous

adherence to these requirements. A show cause notice dated

30.06.2025 was duly served upon the petitioner, providing

adequate opportunity to submit its explanation regarding the

grave lapses that occurred during the conduct of the Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

Competency Test-2. The petitioner availed such opportunity by

submitting a written reply dated 02.07.2025 and a representation

dated 08.07.2025, both of which were considered in detail by

the competent authority prior to the issuance of the impugned

order.

The impugned order itself expressly records that it has been

passed pursuant to and in continuation of the directions issued

by this Hon'ble Court in C.W.J.C. No. 1292 of 2025, wherein

the earlier order of blacklisting dated 31.12.2024 was set aside

with liberty to the authority to proceed afresh after due notice

and hearing. The subsequent proceedings undertaken by the

Department -- including issuance of a fresh show cause notice,

consideration of the petitioner's reply, and reduction of the

blacklisting period to 31.03.2026 -- clearly reflect compliance

with both the contractual safeguards and judicial directions.

Furthermore, the factual foundation for invoking Clause 12

stands well-established. The petitioner's admitted lapses in the

conduct of the CTT-2 examination, as acknowledged in its

email dated 21.09.2024 and letter dated 08.07.2025, coupled

with the findings of the six-member inquiry committee and

corroborative opinions from SCERT and BSEB, conclusively

establish breach of contractual obligations, poor quality of Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

service, and serious discrepancies affecting the Department's

functioning -- all of which squarely fall within the

contingencies contemplated under Clause 12.

Thus, both procedurally and substantively, the impugned order

conforms to the terms of the agreement and to the judicial

mandate previously issued. The action of the respondent cannot,

therefore, be said to be beyond the scope of its contractual

authority or in derogation of the directions of this Hon'ble

Court.

Accordingly, this Court holds that the impugned order dated

22.07.2025 has been validly passed under Clause 12 of the

Agreement dated 13.03.2024 and is in complete compliance

with the order and observations made in C.W.J.C. No. 1292 of

2025. The action is thus legally sound, procedurally fair, and

immune from challenge on the ground of non-compliance.

25. Upon a comprehensive appraisal of the

pleadings, records, and contractual framework, this Hon'ble

Court finds no illegality, procedural infirmity, or arbitrariness in

the impugned order dated 22.07.2025. The respondent

authorities acted strictly within the ambit of Clause 12 of the

Agreement dated 13.03.2024, and in faithful compliance with

the directions issued in C.W.J.C. No. 1292 of 2025, by affording Patna High Court CWJC No.13538 of 2025 dt.14-10-2025

due notice, opportunity of hearing, and passing a reasoned order

based on verified material and the petitioner's own admission of

fault. The blacklisting period, now rationalized till 31.03.2026,

cannot be termed disproportionate considering the gravity of the

lapses that jeopardized the integrity of the Competency Test-2

examination. Consequently, the action of the respondent is

found to be just, fair, and in accordance with law, warranting no

interference by this Hon'ble Court.

26. Accordingly, this Hon'ble Court is of the

considered opinion that the writ petition lacks merit and is

hereby dismissed. There shall be no order to costs.

(P. B. Bajanthri, CJ)

( Alok Kumar Sinha, J) Gaurav Sinha/-

AFR/NAFR                AFR
CAV DATE                08.10.2025
Uploading Date          14.10.2025
Transmission Date       NA
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter