Wednesday, 20, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The South Bihar Power Distribution ... vs The State Of Bihar Deptt. Of Energy And ...
2025 Latest Caselaw 2418 Patna

Citation : 2025 Latest Caselaw 2418 Patna
Judgement Date : 25 March, 2025

Patna High Court

The South Bihar Power Distribution ... vs The State Of Bihar Deptt. Of Energy And ... on 25 March, 2025

          IN THE HIGH COURT OF JUDICATURE AT PATNA
                    Civil Writ Jurisdiction Case No.15623 of 2014
     ======================================================
     The South Bihar Power Distribution Company Ltd., through its Law Officer,
     having its head office at Vidyut Bhawan, Bailey Road, Patna - 800001
                                                                ... ... Petitioner/s
                                         Versus
1.   The State Of Bihar Deptt. Of Energy through its Principal Secretary, New
     Secretariat, P.S. Sachivalaya, District / Town Patna
2.    M/s Dina Metals Ltd, a company incorporated under the provisions of the
      Companies Act, 1956, having its registered office at Abdul Rahmanpur
      Road, Didarganj, P.S. - Alamganj, District/Town - Patna through its Director,
      Anand Kumar Sinha, son of Late Sharda Nand Prasad, resident of NTPC
      Company East Ramkrishna Nagar, P.S. - Ramkrishna Nagar, Patna - 27.
                                                               ... ... Respondent/s
     ======================================================
     Appearance :
     For the Petitioner/s      :     M/s Anand Kumar Ojha, Sr. Advocate
                                     Prakash Kumar, Advocate

     For the State             :     Ms. Neelam Kumar, AC to SC 3

     Fro the Respondent No.2:        M/s Suraj Samdarshi,
                                     Vijay Shankar Tiwari
                                     Avinash Shekhar,
                                     Abhilasha Jha,
                                     Simran Kumari, Advocates

     CORAM: HONOURABLE JUSTICE SMT. G. ANUPAMA CHAKRAVARTHY
                                   ORAL JUDGMENT

                                   Date : 25-03-2025

                            1. The Writ petition has been filed for

      quashing the order dated 26.02.2014 passed by the

      Consumer               Grievance       Redressal          Forum,       Patna

      (hereinafter referred to as 'the 'Consumer Grievance

      Redressal Forum') in Registered Case No. 83 of 2013

      (M/s Dina Metal               Ltd. Vs. The South Bihar Power

      Distribution Co. Ltd. & Ors) and to grant any other
 Patna High Court CWJC No.15623 of 2014 dated 25-03-2025
                                          2/23




         relief / reliefs for which the petitioner is found

         entitled in law.

                          2. The brief facts extracted from the

         petition are that the petitioner is a Power Distribution

         Company engaged in selling electricity as a licensee.

         Respondent No. 2 is a consumer of the petitioner

         under the HTSS Category tariff for a steel ingot

         manufacturing unit that operates electric furnaces,

         located at Didarganj in the District of Patna.

                          3. It is contended by the petitioner that

         respondent No. 2 manufactures steel ingots using

         electric furnaces, which require a continuous power

         supply. The respondent No. 2 applied for supply

         power to its plant. Accordingly, the supply was

         commenced by the petitioner-licensee on 16.10.1990

         for a contract load of 1450 KVA. As the production

         and furnace capacity increased, the respondent No.

         2 enhanced its contract demand from time to time. It

         is further contended by the petitioner that the

         contract demand was enhanced on 16.02.1991 to

         3000 KVA from 1450 KVA for which respondent No. 2

         entered into an agreement. Similarly on 01.06.1994,
 Patna High Court CWJC No.15623 of 2014 dated 25-03-2025
                                          3/23




         the contract demand was further enhanced to 4500

         KVA, and on 07.08.1995 it was further enhanced to

         6000 KVA due to enhancement in the capacity of

         furnaces.

                          4. It is further contended by the petitioner

         that in the year 1999, a new tariff schedule for

         induction furnace consumers was introduced under

         Section 49 of the Electricity (Supply) Act, 1948,

         effective from 01.09.1999. This re-categorized the

         consumers as High Tension Specified Service (HTSS)

         consumers. Clause 2 of the new tariff stipulated that

         the supply would only be provided if the sanctioned

         load was in accordance with the required tonnage of

         the furnace, with a minimum load of 600 KVA for

         every ton of furnace capacity. It was also made

         mandatory that no supply would be provided for

         loads below this norm.

                          5. It is further contended by the petitioner

         that the respondent No. 2 initially submitted an

         affidavit       dated       04.09.1999           stating   the   furnace

         capacity as 13 MT. However, it was later discovered

         that through the report from the manufacturer and
 Patna High Court CWJC No.15623 of 2014 dated 25-03-2025
                                            4/23




         the Excise Department, the furnace capacities were

         17.38 MT and 14.5 MT, respectively. Consequently,

         the petitioner issued a show cause notice to the

         respondent No. 2 regarding the furnace's capacity.

         The respondent No. 2 disputed the claim and

         requested a neutral body to verify the capacity.

         Meanwhile,           the      respondent         No.    2     agreed    to

         provisional billing at 14.5 MT until the verification

         was        completed.              The      measurement,               was

         subsequently carried out by I.I.T. Kanpur which

         calculated the capacity of the furnace to be 16.4 MT.

         Based       on this verified capacity,                  the petitioner

         requested the respondent No. 2 through a Letter

         dated 09.12.1999, to sign a new agreement by

         11.12.1999

, reflecting a contract demand of 9600

KVA, effective from 01.09.1999. The new agreement

was eventually signed on 15.02.2000.

6. It is further contended by the petitioner

that in partial modification of earlier notification

dated 15.03.2000 (Annexure-2), a revised tariff for

the consumers of under HTSS service was

introduced, effective from 1st April 2001 vide Tariff Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

Notification No. COM/TAR-1F- 903/2000/166/2000

dated 28.05.2001. The Clause 3 of the revised Tariff

Notification dated 28.05.2001 included a demand

charge of Rs 700 per KVA per month and an energy

charge of 120 paise per unit for HTSS consumers.

Clause 4 of the said tariff also prescribed a minimum

monthly charge of Rs 1012 per KVA of contract

demand, payable on a monthly basis, with a

guaranteed minimum supply of 630 hours per

month. If the actual supply hours were lower, the

monthly charges were adjusted, based on the actual

hours of consumption. As per clause 5 of the said

revised tariff, the demand charge as per clause-3

was to be levied on actual maximum demand

recorded in the meter during the month or 100% of

the contract demand whichever is higher. It is

contended by the petitioner that in the light of the

revised tariff, the petitioner along with all similarly

situated consumers including Respondent No. 2 are

bound to pay the energy bill as per the HTSS tariff

prepared in accordance with clauses 2, 3, 4 & 5 of

the HTSS tariff as revised effective from 01.04.2001. Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

7. It is further contended by the petitioner

that it is the case of the respondent-consumer that

although the contract demand was enhanced from

6000 KVA to 9600 KVA, still the actual maximum

demand of the respondent-consumer did not

undergo change in the past several years. However,

the petitioner-erstwhile-Board continued to bill on the

basis of minimum monthly charges instead of actual

meter readings taken every month by the Board

officers. As such in this way, the respondent was

forced to pay 30% more than its actual demand

charge every month. It is further the case of the

respondent consumer that during the months of April

and May 2002, the petitioner as per official

announcement imposed heavy load restriction on the

petitioner's factory continuously from 14.04.2002 to

23.05.2002, but the energy bills for the month of

April and May 2002 were served on the basis of

minimum monthly charge based on 9600 KVA.

8. It is submitted by the petitioner that

the respondent-consumer's claim was examined in

Letter No. 4633 dated 14.11.2002, issued by the GM- Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

cum-Chief Engineer, Patna Electric Supply

Undertaking. It was stated therein that regular

power supply was not possible due to the outage of a

100 MVA transformer at the Fatwa grid sub-station

from 22.04.2002 to 17.05.2002. As a result, the

power supply to the respondent was severely

restricted, with the available power dropping from

the required 20-25 MVA to only 11.5 to 13.5 MVA. M/s

Dina Metal Ltd.'s supply was limited to 1.5 to 3.5

MVA, against their contract demand of 9.6 MVA. The

Letter No. 4633 dated 14.11.2002 also referred

Clause 4 of the HTSS tariff, which stipulates that

minimum monthly charges are subject to minimum

assured hours of supply of 630 hours per month.

The Clause had the provision for allowing

proportionate relief to the consumers if power supply

is less than 630 hrs in a month. However, the total

hours of supply in the month of April and May 2002

were 691.5 and 681.5 hours, respectively, exceeding

the minimum stipulated hours. It is submitted that

this clause does not allow relief for restricted power

supply or to unmeet full load requirements. Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

Nevertheless, the GM-cum-Chief Engineer, Patna

Electric Supply Undertaking considered one part of

the tariff notification and suggested that the

respondent's claim for relief during this period might

be justified, without fully applying the tariff

provisions.

9. It is further submitted by the petitioner

that respondent No. 2 approached the Hon'ble Patna

High Court by filing CWJC No. 5783/2005 and claimed

that the aforesaid energy bill for the month of April

2002 and May 2002 were not justified in view of the

acceptance by the authority such as GM-cum-Chief

Engineer, Patna Electric Supply Undertaking that the

load was restricted and the petitioner was supplied

energy between 1.5 MVA to 3.5 MVA. The Writ

application dismissed vide order dated 27.06.2012

passed in CWJC No-5783/2005. The respondent No. 2

filed LPA No. 74/2013 against the order of the

Learned Single Judge. The appellate court after some

argument permitted the respondent No. 2 to

withdraw CWJC No. 5783/2005 with liberty to

approach the Consumer Grievance Redressal Forum , Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

under Section 42 (5) of the Electricity Act, 2003 who

was directed to decide the matter in accordance with

law, without being prejudiced or influenced by the

order dated 27.06.2012. Accordingly, the the

respondent No. 2 moved before the Consumer

Grievance Redressal Forum.

10. It is submitted by the petitioner that

the Consumer Grievance Redressal Forum vide order

dated 26.02.2014 usurped the provisions of tariff and

without appreciating the same in right perspective

held the respondent-consumer was entitled for relief

on the point of non supply of adequate power for the

months of April 2002 and May 2002. It is further

submitted that the Consumer Grievance Redressal

Forum without any provision to grant remission in

view of terms and condition of Clause Nos. 3, 4 & 5

of the Tariff Notification dated 28.05.2001 formulated

an independent formula, for the grant of remission

which is not sustainable either in the light of

provisions of tariff or the terms and condition of the

agreement executed between the parties.

11. The Learned Senior counsel Sri Anand Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

Kumar Ojha for the petitioner submitted that the

Consumer Grievance Redressal Forum has not

considered Clause-4 of the Tariff Notification dated

28.05.2001, which states that a minimum monthly

charge has to be levied in terms of the contract

demand as reflected in Clause-4 of the notification

and the Board is justified in raising demand at 9600

KVA from the respondent. It is further contended on

behalf of the petitioner that the respondent No. 2 has

also entered into an agreement making a

commitment to pay the minimum contracted

demand as well as monthly charges which is

provided for not only in the tariff notified, but also in

the obligation created under the agreement.

12. The Learned Senior counsel for the

petitioner submitted that the Consumer Grievance

Redressal Forum failed to appreciate in right

perspective that the petitioner has an obligation to

provide electricity for a minimum of 630 hours per

month which has been provided and that during this

period, the supply has been over and above 630

hours. Remissions are granted if the supplies fall Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

below the minimum supply hours agreed between

the parties, but since in the present case there is no

provisions of remission for supplies made above 630

minimum hours, there is no escape for the

respondent from paying the liability created in the

terms of the demand for the bills raised.

13. The Learned Senior counsel for the

petitioner submitted that in view of the matter, the

impugned order passed by the Consumer Grievance

Redressal Forum in bad in law, as well as on the facts

of this case, and it is in the interest of the justice that

this Court may be pleased to allow this application

and quash the impugned order dated 26.02.2014 as

wholly without jurisdiction.

14. A detailed counter affidavit was filed

by respondent No. 2. It is averred in counter affidavit

that the respondent's electric supply began on

16.10.1990 with a contract demand of 1450 KVA,

which was increased over time: to 3000 KVA on

16.2.1991, thereafter to 4500 KVA on 1.6.1994, and

to 6000 KVA on 7.8.1995. It is further averred that

during the disputed period, the contract demand was Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

9600 KVA, for which an agreement which was

executed on 15.2.2000 (Annexure-4). It is contended

on behalf of the respondent No. 2 that according to

Clause 1(a) of the agreement, the licensee -

petitioner was required to provide a constant supply

of electrical energy at the specified contract

demand. The applicable HTSS tariff mandates

charges for both energy consumption and demand,

based on the contract demand (Annexure-5).

15. The Learned counsel for the

respondent No. 2 submits that it is an admitted fact

that the Fatwa Grid Sub-station supplied limited

power due to the outage of a 100 MVA power

transformer. During the period from 22.4.2002 to

17.5.2002, when the transformer was out of service,

the supply to the respondent No. 2 was severely

restricted. The chart provided by the Electrical

Superintending Engineer, PESU, clearly illustrates the

date-wise availability of power in the 33 KVA Katra

feeder, which supplies power to the respondent.

While the Katra feeder required 20-25 MVA, only

11.5-13.5 MVA was available. Of this, the power Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

allocated to the respondent No. 2 was restricted from

1.5-3.5 MVA. It is contended that this fact is evident

from Annexure-5 to the Writ application, specifically

in the Letter dated 14.11.2002 issued by the General

Manager-cum-Chief Engineer to the Financial

Controller (Revenue), requesting for consideration of

the respondent's case for proportionate remission in

demand charges.

16. The the Learned counsel for

respondent No. 2 submitted that the respondent No.

2 filed C.W.J.C. No. 5783 of 2005, challenging the

energy bill for the month of April-May 2002 due to

the reduced supply. However, the Writ was

dismissed, as there was no provision for remission if

the supply is not as per the contract. Respondent No.

2 then filed L.P.A. No. 74 of 2013. The Hon'ble

Division Bench of this Court vide order dated

18.7.2013 (Annexure 8 to the Writ petition),

considering the submissions made by the parties and

the acceptance of the petitioner that it has no

objection, if the respondent No. 2 was relegated to

the alternative remedy of the Consumer Grievances Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

Redressal Forum, the Writ application was disposed

of with a clear observation that the Forum

constituted under Section 42(5) of the Electricity Act,

2003 will decide the matter in accordance with law

without being prejudiced or influenced by the

impugned judgment and order dated 27.6.2012. The

appeal was disposed of as withdrawn, with the

aforesaid liberty.

17. Further, respondent No. 2 submits

that in furtherance of this, the answering respondent

filed a case before the Consumer Grievances

Redressal Forum under Section 42(5) of the

Electricity Act, 2003, which was registered as Case

No. 83 of 2013. The Consumer Grievances Redressal

Forum, by order dated 26.2.2014, after considering

the facts of the case and the relevant decisions

rendered by this Hon'ble Court and the Hon'ble

Supreme Court, held that the respondent No. 2 was

entitled to remission due to the failure to supply

electrical energy at the contracted demand. This

conclusion was supported by the rulings in

Raymond Limited vs. Madhya Pradesh Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

Electricity Board (2001 (1) SCC 534, paragraph

21) and Tata Iron & Steel Company vs. Bihar

State Electricity Board (AIR 1989 Patna 119,

paragraph 12). The order passed by the Forum,

which is under challenge, is contained in Annexure-1

of the Writ application.

18. The the Learned counsel for the

respondent No. 2 submits that the petitioner's

argument that the consumer cannot claim further

remission once the supply is made for 630 hours ,

which is entirely misconceived, in view of the law

established by the Hon'ble Apex Court was well as

this Hon'ble Court as the two component are distinct

in nature. Supplying energy for 24 hours and

supplying energy as per the consumer's contract

demand both are distinct. For instance, if an

industrial consumer has executed an agreement for

100 KVA to operate its industry, and the licensee fails

to supply energy at the contract demand of 100 KVA

but supplies energy for 24 hours for 30 days, at 1

kilowatt which is sufficient for lighting fan and light,

such supply this cannot be considered a supply of Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

energy in accordance with the agreement. The very

purpose of the agreement, which was to run the

industry, would be defeated. Furthermore, the tariff

clearly states that demand charges are levied at Rs.

700 per KVA, in addition to the energy charge at the

prescribed rates. More importantly, Rs. 700 per KVA

is to be applied for the actual consumption of 100%

of the contracted demand, whichever is higher.

Therefore, the tariff assumes that energy will be

supplied to the extent of 100% and even if the

consumer fails to avail energy at the contracted load,

the charges would be levied for 100%.

19. The Learned counsel for the

respondent No. 2 submits that permitting the

licensee to charge 100% of the demand, despite the

acknowledgment that the licensee failed to supply

energy at the contracted load, would result in unjust

enrichment on the part of the licensee.

20. The Learned counsel for respondent

No. 2 submits that the Consumer Grievances

Redressal Forum's reliance on Clause 4 of the

agreement, which clearly specifies that the Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

consumer's liability to pay charges is subject to the

minimum contract demand applicable for each

category, thus, the charges payable under the

"demand charge" category are contingent upon the

licensee supplying the agreed contract demand.

Furthermore, the submission in paragraph 24 of the

Writ application, which claims there is no provision

for remission, is therefore misconceived. The Forum

has addressed this issue in detail, relying on the

decisions of both the Hon'ble Apex Court and this

Hon'ble Court. Hence, the Writ petition is liable to be

dismissed on this ground alone, affirming the order

of the Consumer Grievance Redressal Forum.

21. Heard Learned Senior counsel for the

petitioner as well as the respondents and perused

the record.

22. The main cause of the dispute

between the parties since April 2002 is the mode of

billing demand raised by the petitioner for the period

from 14.04.2002 to 23.05.2002, according to

respondent No. 2. However, according to the

petitioner, the period is from 22.04.2002 to Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

17.05.2002. During this intervening period, the

power supply to the petitioner was severely

restricted, ranging from 1.5 MVA to 3.5 MVA, against

the contracted demand of 9.6 MVA. This restriction

occurred due to the outage of the 100 MVA

transformer unit installed at the 220/132/33 KV

Fatuwaha Grid Power Substation, through which the

33 KV Katra Meena Bazar feeder, supplying power to

respondent No. 2, emanates. The respondent-

consumer's feeder depends on the said Fatuwaha

Grid Substation.

23. Upon perusal of the order of the

Consumer Grievances Redressal Forum, this Court

finds that the Forum has carefully addressed the

issue in question and passed a reasoned and well-

versed order, after considering all the pleas of the

parties. The Forum has also duly examined the

decisions rendered by this Hon'ble Court, as well as

by the Hon'ble Supreme Court of India. After careful

examination of the order, this Court is of the opinion

that the Forum rightly held that respondent No. 2 is

entitled to remission due to the non-supply of Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

electrical energy at the contracted demand.

24. The Hon'ble Apex Court in Raymond

Limited (supra) observed in paragraph 21 as

follows:

"21. So far as the cases under consideration and the liability of the consumers relating to minimum guarantee are concerned, the relevant clause relating to minimum guarantee charges as well as the tariff notification relied upon, would go to show that what was guaranteed was not the payment of a flat sum or amount of money to be calculated with reference to a particular number or percentage of units, dehors the quantum of electrical energy distributed and supplied by the Board. In other words, the guarantee was of "... such minimum consumption as when calculated at the tariff..." will yield a particular monthly/annual sum to the Board. Even going by the tariff notification which prescribes also a minimum entitling the Board to collect it [vide clause 21(b)] it merely casts liability on the consumer to "guarantee a minimum monthly consumption equivalent to 40% load factor of the contract demand". Consequently, for the consumer to honour his/its commitment so undertaken to give a minimum consumption there should essentially be corresponding Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

supply by the Board at least to that extent, without which the consumption of the agreed minimum is rendered impossible by the very lapse of the Board. The minimum guarantee, thus, appears to be not in terms of any fixed or stipulated amount but in terms of merely the energy to be consumed. The right, therefore, of the Board to demand the minimum guaranteed charges, by the very terms of the language in the contract as well as the one used in the tariff notification is made enforceable depending upon a corresponding duty, impliedly undertaken to supply electrical energy at least to that extent, and not otherwise. It is for this and only reason we find that the ultimate conclusion arrived at by the Full Bench of the High Court does not call for any interference in these appeals."

25. The Division Bench of this Court in

Tata Iron & Steel Company (supra) observed in

paragraph 12 as follows:

"12. The words 'constant supply of electrical energy' must mean that continuous supply of electrical energy. That to us appears to be the plain meaning of the words used. In the modern context where even our day to day life is so much dependent upon supply of Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

electricity, it is not too much to expect that the Board should supply electrical energy throughout the 24 hours. However, having regard to the fact that annual charges are payable by consumers who generally require electrical energy in larger quantities than any ordinary domestic consumer for carrying on his business or establishment, the annual charges payable by him have a direct relationship with the supply of electrical energy to him at a time when he can consume the supply. The minimum guaranteed consumption itself implies that the energy is supplied when it can be consumed. No doubt, even beyond his normal working hours, such a consumer requires electrical energy for other purposes, such as security lighting etc. However, the consumption for such purposes is so small as compared to the main purpose for which electrical energy is taken, that it may be ignored in the matter of determining the liability for annual charges. So viewed, 'constant supply' in the context of annual charges must mean continuous supply during the normal working hours of the consumer when the supply can be consumed. This to us appears to be a fair interpretation of the agreement having regard to its purpose, commercial nature and preacticability. We are of the view that when the Board wants a guarantee from the consumer about minimum Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

units it would consume, any prudent businessman would agree to pay that amount only if the Board fulfils its obligation. If in fact it is found that there had not been constant suppy of electricity at the contract demand during the period the factory of the petitioner was expected to work, the petitioner can certainly claim that it is entitled to a reduction in annual charges proportionate to the period for which there was no supply of electrical energy or supply as per the contract demand. The case of TISCO is that its units at Adityapur complex work 24 hours and electrical energy at the contract demand is required for all 24 hours. It was urged that in this case, constant supply must, therefore, mean constant supply for 24 hours. On behalf of the Board it was not stated that TISCO's units at Adityapur complex do not work for 24 hours."

26. This conclusion aligns with the

principles laid down by the Hon'ble Apex Court in

Raymond Limited (supra) and Tata Iron & Steel

Company (supra). Accordingly, this Court concurs

with the order passed by the Forum and finds no

lacuna in the same.

27. Based on the facts and circumstances Patna High Court CWJC No.15623 of 2014 dated 25-03-2025

stated above, this Court is of the considered view

that there is no merit in the case of the petitioner.

The Court does not find any error in the order dated

26.02.2014 (Annexure-1) passed by the Consumer

Grievance Redressal Forum. Therefore, the order of

the Consumer Grievance Redressal Forum, dated

26.02.2014, is hereby confirmed.

28. Accordingly, the Writ petition is

dismissed as devoid of merits.

29. Interlocutory Application(s), if any,

shall stand disposed of.

Spd/-                                    (G. Anupama Chakravarthy, J)
AFR/NAFR                NAFR
CAV DATE                NA
Uploading Date          16.04.2025
Transmission Date
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter