The Union Of India Through Assistant ... vs Brajesh Kumar Sinha on 11 December, 2025

Author: Rajiv Roy
Bench: Rajiv Roy
         IN THE HIGH COURT OF JUDICATURE AT PATNA
                        Miscellaneous Appeal No.449 of 2025
     ======================================================
1.    The Union of India through Assistant General Manager Engineer (Civil)
      Airports Authority of India Gaya Airport, Gaya-923004 (Bihar).
2.   Airport Authority of India, A Statutory Corporation incorporated under the
     Airports Authority of India Act, 1995, having its Head Office at Rajiv
     Gandhi Bhawan, Safdarjung Airport, New Delhi-110003.
3.   The Chairman, Airports Authority of India Head Office at Rajiv Gandhi
     Bhawan, Safdarjung Airport, New Delhi-110003.
4.   Member (Planning) Head of the Department of Engineering, Airports
     Authority of India, Head Office at Rajiv Gandhi Bhawan, Safdarjung
     Airport, New Delhi-110003.
5.   Executive Director, Airports Authority of India, Head Office at Rajiv Gandhi
     Bhawan, Safdarjung Airport, New Delhi-110003.
6.   General Manager, Engg. (c) Airports Authority of India, NSCBI Airport,
     Kolkata-700002.
7.   Assistant General Manager, Engineer (civil) Airports Authority of India,
     Gaya Airport, Gaya-823004 (Bihar).

                                                                ... ... Appellant/s
                                      Versus
     Brajesh Kumar Sinha son of Sri Bharat Sinha, Resident of behind H/150, Veer
     Kunwar Singh Colony, Hinoo, Ranchi, P.O.-Hinoo, P.S.-Doranda, District-
     Ranchi-834002.

                                               ... ... Respondent/s
     ======================================================
     Appearance :
     For the Appellant/s    :      Mr. Dr. Pankaj, Advocate
     For the Respondent/s   :      Mr. Saurabh Bishwambhar, Advocate
     ======================================================
     CORAM: HONOURABLE MR. JUSTICE RAJIV ROY
     ORAL JUDGMENT
      Date : 11-12-2025

                  Heard the parties.

                  2. The present application has been preferred against

      the judgment dated 07/04/2025 passed by the learned

      Principal District and Sessions Judge, Patna in Arbitration

      Case No 18/2024. [The Union of India Through Assistant
 Patna High Court MA No.449 of 2025 dt.11-12-2025
                                           2/23




         General Manager, Engineer (Civil), Airports Authority of India,

         Gaya Airport, Gaya- 923004 Bihar vs. Brajesh Kumar Sinha]

         as also Award dated 31.05.2023 passed by the sole Arbitrator

         by which the case of the sole claimant-respondent was allowed

         and the appellants were directed to pay the Award amount

         within 90 days.

                      3.   The matrix of facts giving rise to the present

         appeal is/are as follows:

                      4. Tenders were invited through the e-tendering portal

         by the Assistant G.M. (E-C), AAI, Gaya Airport (Bid

         Manager) on behalf of Chairman, Airports Authority of

         India (henceforth for short 'the AAI'), on 07.11.2016 from the

         eligible contractors for the Construction of the Property

         Boundary Wall of 'the AAI' land situated at Gaya Airport, Gaya

         at an estimated cost of Rs.2,12,07,560.00 with the completion

         period of six months. The scope of work included RCC footing,

         RCC column, RCC Plinth beam, brick work etc. The last date

         and time of sale of tender document was 07.11.2016 while the

         last date for submission of e-bid was 17.12.2016.

                      5. The claimant-respondent thereafter submitted his

         application form along with other candidates within the

         stipulated period and time i.e. 02.12.2016 and after completion
 Patna High Court MA No.449 of 2025 dt.11-12-2025
                                           3/23




         of paraphernalia, the claimant respondent was selected for the

         above captioned work.

                      6. This followed the issuance of the Letter of

         Appointment on 04.01.2017 for the work mentioned above at

         the item rates quoted by him totaling to Rs.1,25,77,245/- (Rs.

         One Crore Twenty Five Lakhs Seventy Seven thousand Two

         hundred & Forty Five only) which was 40.69% below the

         estimated cost of tender of Rs. 2,12,07,560/- (Rupees Two

         Crores Twelve Lacs Seven Thousand Five Hundred & Sixty

         only). The claimant respondent was acknowledged about

         conversion of Earnest Money Amount of Rs. 4,24,152/- (Rupees

         Four Lakhs Twenty Four Thousand One Hundred Fifty Two

         only) into SECURITY DEPOSIT, as per condition number 15

         of the contract document.

                      7. The further direction to the claimant respondent

         was to deposit the remaining amount of Security Deposit i.e. Rs.

         8,33,573/- (Rupees Eight Lakhs Thirty Three Thousand Five

         Hundred & Seventy Three only) within ten days from the date

         of issue of the letter, failing which, the same will be deducted as

         per condition 13(iii) of the tender/contract document.

                      8. The claimant respondent was further asked to be

         present before the Assistant General Manager (E-C), of 'the
 Patna High Court MA No.449 of 2025 dt.11-12-2025
                                           4/23




         AAO' Gaya Airport, Gaya, the in-charge of the contract, to sign

         and complete the contract agreement on 15.01.2017.

                      9.    Thereafter,       the   Contract    Agreement    No-

         AAI/GAYA/AGM/Engg(c)                  03/2016-17      dated   19.01.2017

         signed and executed between 'the AAI' and Brajesh Kumar

         Sinha, the claimant-respondent.

                      10. The contention is that there was no dispute on the

         proposed property regarding title and possession of said

         property of the Gaya Airport and the State Agencies demarcated

         the said property/premises which was proposed to be boundary

         walled.

                      11. The claimant respondent accordingly started

         construction work without any hindrance and being satisfied

         with the performance of the claimant-respondent, the appellants

         cleared the 1st Running Account Bill(R/A Bill) without any

         dispute for the work done up to 31.03.2017.

                      12. On 03.04.2017, the claimant respondent reported

         to the Assistant G.M. (E-C) that on the previous day,

         02.04.2017

, a mob of around 250 people led by one Shri Bhism

Narayan Rai reached at the site and threatened the Supervisor

and the labourers to face consequences if they would not

demolish the structure constructed at the site within 7-8 days. Patna High Court MA No.449 of 2025 dt.11-12-2025

13. On 04.04.2017, the claimant

respondent/contractor lodged an FIR in Bodh Gaya P.S. Case

No-207/17 u/s 147 149, 34, 323 & 504 IPC as the mob of about

75-100 persons came to the site and created hooliganism/

quarrel/nuisance with his workmen. On 05.04.2017, the same

was reported to 'the AAI' which followed the Director, AAI,

Gaya Airport apprising the S.S.P., Gaya with a request to

maintain the law and order on spot.

14. As the story further unfolds, on 14.04.2017, the

claimant respondent approached the applicants with reference to

letter dated 03.04.2017 & 05.04.2017 to take necessary steps for

removal of hurdles caused by local people bringing the

construction works at total stand still.

15. On 26.04.2017, the claimant respondent referring

to the letters dated 03.04.2017; 05.04.2017 and 14.04.2017

claimed that though he tried to restart the construction of work

at the site but due to agitation of the villagers, the work could

not be started. The claimant respondent further recorded that he

has suffered loss to the tune of Rupees 1,50,000/-(approx)

towards the establishment and labours cost and further as there

was no possibility of execution of work at the site.

16. In view of the representations/letters dated Patna High Court MA No.449 of 2025 dt.11-12-2025

03.04.2017; 05.04.2017; 14.04.2017 & 26.04.2017 as well as

FIR dated 04.04.2017, the Airport Director, Gaya Airport, Gaya

vide letter dated 05.05.2017 addressed to Sub-Divisional

Officer, Sadar, Gaya requested for arrangements to ensure

restarting of construction of Boundary Wall at 'the AAI' land at

Techno Farm, which was stopped since 04.04.2017.

17. Further, after the meeting with the District

Magistrate, Gaya, he directed vide letter dated 15.06.2017 to the

Sub-Divisional Officer, Sadar, Gaya to ensure the construction

work of the boundary wall of 'the AAI' land by providing police

force at the site.

18. The contention is/was that while the appellants

were taking steps to resume the construction work at the said

site, the claimant-respondent was more interested in closure of

the construction work and payment towards the work executed

by him as would be evident from letters dated 03.06.2017 &

19.06.2017. The claimant respondent never co-operated with the

appellants in order to resume the construction work on 'the

AAI' land.

19. The case of the appellants is/was that the

claimant-respondent for the reasons best known to him did not

resume the construction work despite the best efforts extended Patna High Court MA No.449 of 2025 dt.11-12-2025

by the applicants and the local Administration. However it is

pertinent to mention here that the applicants had granted several

extension of contract for completion of the work under Clause-

5 of Clauses of Contract starting with the first letter dated

13.07.2017 by which the contract got extended up to 10.08.2017

which was extended from time to time till 05.11.2018 when it

was extended till 04.12.2018. However, the claimant-respondent

chose not to resume work.

20. The claimant respondent submitted representation

before the appellants on 06.09.2017 demanding the

measurement of work done, preparation of bills as also

payments and issuance of letter of foreclosure beside payment

of Compensation and permission for withdrawal of men and

machineries as well as different materials stocked at the site and

further to refund the Security Deposit amount.

21. The AGM Engg.(C) thereafter vide letter dated

11.09.2017 asked the claimant respondent to submit the bill for

construction work done in between 01.04.2017 and 03.04.2017

but the claimant respondent failed to comply.

22. In the aforesaid facts and circumstances, a joint

meeting was held on 05.12.2017 between the claimant

respondent and 'the AAI' in which the claimant respondent Patna High Court MA No.449 of 2025 dt.11-12-2025

assured construction work and the applicants had apprised him

about the assurance given by the State Administration for

extending security to the claimant respondent and his men as

well as materials. The claimant respondent informed that he

requires a week's time for mobilization and assured to intimate

the date by 12.12.2017.

23. However, instead, the claimant respondent served

a legal notice to the applicants vide Notice/378 dated

11.12.2017, which was promptly replied vide Reference no.-

AAI/Gaya/Tekuna/B-Wall/Legal/ AGM/Engg.(C)/1617-22 dated

31.01.2018 by the AGM Engg. (C), Gaya Airport denying to

each and every point.

24. This followed the notices to the Claimant

respondent vide letters nos.-1643-46 dated 07.02.2018 & 1786-

89 dated 06.03.2018. The claimant respondent again served a

legal notice no.-58 dated 08.02.2018 which was also replied

vide letter dated 22.02.2018.

25. As the claimant respondent chose not to reply to

the Show-Cause notices dated 07.02.2018 & 06.03.2018, instead

served a Demand dated 10.03.2018 through his Advocate for the

following:

(i) measurement of the remaining work executed after the measurement done Patna High Court MA No.449 of 2025 dt.11-12-2025

under 1st on Account Bill,

(ii) preparation of Final Bill,

(iii) payment of the amount under the Final Bill and

(iv) compensation to compensate the losses suffered by the contractor. 'The AAI' through its lawyer sent an explanatory reply of the said Notice of Demand on 10.04.2018.

26. The contention is that the claimant respondent left

the work without any sufficient reasons and estimated cost of

leftover construction work to Rs. 1,96,08,019.00 and served an

additional Notice of Demand on 30.04.2018 to the appellants.

27. The appellants had sanctioned the amount to the

claimant respondent as per clause of payment in the work order

dated 04.01.2017 in respect of 2nd RA Bill on 11.05.2018 which

was transferred in the Bank account.

28. The claimant respondent thereafter sent legal

notices vide no. 314 and 315 dated 21.09.2018/23.10.2018 as

well as 05.01.2019 to the appellants requesting for appointment

of Dispute Resolution Committee in terms of Clause-25(i)

arising out of the Agreement dated 19.01.2017 for

conciliation/adjudication of the dispute of the subject matter,

which was received by the applicants on 25.10.2018.

29. The appellants took cognizance of the legal Patna High Court MA No.449 of 2025 dt.11-12-2025

notices dated 21.09.2018/23.10.2018 & 05.01.2019, which was

served to Chairman, 'the AAI' for appointment of Dispute

Resolution Committee(DRC) in terms of Clause-25(i) arising

out of the said Agreement and Work Order bearing No-AAI/

GAYA/B-WALL/AGM(Engg-C)/w.o-02/2016-17/1891-96 dated

04.01.2017 and referred the matter to RHQ-ER vide letter dated

30.11.2018. The order dated RHQ-ER constituted the DRC vide

22.12.2018 comprising three members namely:

1. Sh. K. K. Singh, GM, Project.

2. Sh. Nayak, DGM, Finance.

3. Sh. Gorai, DGM, Law.

The same information was given to all

concerned vide letter dated 08.01.2019.

30. In the meantime, Sri. Gorai, one of the members

of the DRC, was transferred and relieved from RHQ-ER. He

was replaced with Sri. Amit Kumar, Manager, (Law) vide order

dated 11.04.2019 of RHQ-ER and approved by the GM (Engg)

on 12.04.2019. The proceedings of the DRC commenced on

16.05.2019. The appellants had submitted their reply on the

same date which was duly signed on 30.04.2019.

31. The DRC adjourned the matter with the direction

to the claimant respondent to go through the reply of the Patna High Court MA No.449 of 2025 dt.11-12-2025

appellants and submit rejoinder if any and observed that the next

meeting would be fixed after submission of the claimant

respondent's reply.

32. In the meanwhile, the appellants under Clause-3

of the agreement dated 19.01.2017 took action against the

claimant respondent and terminated the Agreement vide letter

no-1148-54 dated 26.12.2018 in view of apathy shown by the

claimant respondent either in completion of work or in replying

the issues raised in the show cause notices dated 07.02.2018 &

06.03.2018.

33. Thereafter, the appellants submitted their reply on

16.05.2019 which was duly signed on 30.04.2019. The DRC

adjourned the matter with the direction to the claimant

respondent to go through the reply of appellants and submit

rejoinder if any and observed that the next meeting would be

fixed after submission of the claimant respondent's reply.

34. In response to the reply submitted by the

appellants, the claimant respondent vide a petition dated

10.06.2019 appeared before the Disputes Committee through his

lawyer and intimated that the copy of reply of appellants is not

legible. Hence, he requested to send a legible copy of the reply

of the appellants with a request to postpone further proceedings Patna High Court MA No.449 of 2025 dt.11-12-2025

& extend the period of six weeks to submit the reply of the

claimant respondent. He also raised the issue of appointment of

DRC after the expiry of limitation period with respect to Clause-

25(i) of the Agreement.

35. He further prayed for appointment of an Arbitrator

by filing a Request Case bearing Req. Case no. 44/2019

before the Hon'ble Patna High Court, which was disposed of

vide an order dated 27.09.2019 passed by Hon'ble the then

Chief Justice with the following observation:

"In view of the arbitration clause available and in view of the provisions of the Arbitration and Conciliation Act, 1996 and Appointment of Arbitrator by the Hon'ble Chief Justice of Patna High Court Scheme, 1996, I hereby appoint Hon'ble Mr. Justice V.N. Sinha (Retd.), as an Arbitrator to enter upon the dispute and render his award. The Registrar General to take steps accordingly for information as well as for sending the records to the Arbitrator."

(emphasis added)

36. The sole Arbitrator thereafter took up the matter

and passed the AWARD on 26.04.2022 in which he

propounded/allowed the claim or the claimants while dismissing

the stand taken by 'the AAI'.

Patna High Court MA No.449 of 2025 dt.11-12-2025

37. Thereafter the claimant respondent filed a petition

u/s 33 of Arbitration & Conciliation Act, 1996 (henceforth for

short 'the Act') on 30.05.2022 which was rejected vide an order

dated 31.05.2023 with the following observations:

"In the circumstances, there is also no

substance in the other prayer made by the

claimant in the application to adjudicate claims

no. 19, 21,23 & 24 and to publish additional

award. The application under section 33 (1) (a)

and (b) is accordingly rejected."

The Award dated 26.04.2022 passed

by the learned Sole Arbitrator attained finality

on 31.05.2023 with the passing of Additional

Award on petition u/s 33 of the Arbitration &

Conciliation Act 1996.

38. Thereafter, the Arbitration Case No-18/2024 was

filed u/s 34 of Arbitration & Conciliation Act, 1996 on behalf

of appellants for setting aside the arbitral award dated

26.04.2022, which attained finality on 31.05.2023 after passing

of the arbitral award u/s 33 of Arbitration & Conciliation Act

1996 passed in Arbitration proceedings arising out of Request

Case No-44/2019 by the sole Arbitrator. It was filed on Patna High Court MA No.449 of 2025 dt.11-12-2025

14.03.2024 along with application for condonation of delay

Upon scrutiny of the instant application, 'Sheristedar' reported

that there is a delay of 197 days in filing the application.

39. The contention is/was that the delay in filing the

petition u/s 34 of 'the Act' has to be attributed to the

organization such as processing of the case through proper

channels and after obtaining the order dated 31.05.2023 passed

by the Arbitrator. Thereafter, the Award as a whole was analyzed

which followed a decision to challenge it by way of filing the

petition u/s 34 of 'the Act'.

40. The Arbitration Case No. 18 of 2024 (The

Union of India & Ors. vs. Brajesh Kumar Sinha) was heard

by the learned Principal District Judge, Patna and dismissed on

07.04.2025. The conclusion arrived at have been incorporated in

paragraph nos. 17 and 18 which read as follows:

17. Thus, applying the aforesaid provision and proposition to the present case, it unfolds that award has been passed on 26th April, 2022 which attained finality on 31 May, 2023 after passing of the additional award under Section 33 of Arbitration and Conciliation Act, 1996, whereas, the present application has been filed on 14th March, 2024, ie., after a period of 197 days. Proviso to Section 34(3) provides that even if the Court is satisfied that the applicant Patna High Court MA No.449 of 2025 dt.11-12-2025

was prevented by 'sufficient cause', from making the application within the said period of three months, it can entertain the application only within a further period of thirty days, and not thereafter. Therefore, in this case under no event, this Court can entertain the application of the applicants beyond 28th September, 2023 whereas, the present application under Section 34 Arbitration Act has been filed on 14th March, 2024.

18. Therefore, in view of the foregoing discussions, this Miscellaneous (Arbitration) case under Section 34 of the Arbitration Act, being time barred under sub-section (3) of Section 34 of the Arbitration Act, stands dismissed.

(emphasis added)

41. Aggrieved, the present appeal.

42. Learned counsel for the appellants submit that in

view of the fact that it is an organization, they took some time to

come to a decision to file an application under Section 34 of 'the

Act'. This must have been taken into account while deciding the

case. The further submission is that though there has been delay

of 197 days as pointed out, every delay does not reflect malafide

or dilatory attitude of the litigant to delay proceeding and it is

the circumstance governing each case that has to be tested on

its merit.

43. Further, in the case of the State or an organization, Patna High Court MA No.449 of 2025 dt.11-12-2025

various factors including the functioning of the Government

which is not individual but institutional involving decision

making process at various levels should also have been taken

into consideration.

44. The submission is that unfortunately, this was not

taken into account when the case was dismissed on the ground

of delay in filing of the petition under Section 34(3) of 'the Act'

and thus it needs interference.

45. This Court has taken note of the facts of the case,

the submissions of the appellants as recorded above as also the

order passed by the learned Principal District Judge, Patna in

Arbitration Case No. 18 of 2024 (the Union of India & Ors.

vs. Brajesh Kumar Sinha) dated 07.04.2025.

46. The admitted position is that the Award came to be

passed on 26.04.2022. Subsequently, a petition under Section 33

of 'the Act' was preferred which was dismissed on 31.05.2023.

The application under Section 34 of 'the Act' was filed on

14.03.2024. The appellants thus took 197 (195 days?) more days

than what is mandated in 'the Act'.

47. At this stage, it would be appropriate to

incorporate Section 34(3) of 'the Act' which read as follows:

34(3). An application for setting aside may not be made after three months Patna High Court MA No.449 of 2025 dt.11-12-2025

have elapsed from the date on which the party making that application had received the arbitral award or, if a request had been made under section 33, from the date on which that request had been disposed of by the arbitral tribunal:

Provided that if the Court is satisfied that the applicant was prevented by sufficient cause from making the application within the said period of three months it may entertain the application within a further period of thirty days, but not thereafter.

48. The language of Section 34(3) of 'the 1996 Act' is

very clear. After the lapse of three months, if the Court is

satisfied that sufficient cause is there and the reasons have been

explained which prevented them to file a petition within the said

period, it can entertain the application for further period of thirty

days but not thereafter. Thus, 'the Act' completely bars

entertaining any petition after lapse of thirty days.

49. This Court is further guided by the order passed

by the Hon'ble Apex Court in the case of Union of India vs.

Popular Construction Company reported in (2001) 8 SCC

470. Paragraphs 12, 14 and 16 of the said order read as

follows:

Patna High Court MA No.449 of 2025 dt.11-12-2025

12. As far as the language of Section 34 of the 1996 Act is concerned, the crucial words are "but not thereafter" used in the proviso to sub-section (3). In our opinion, this phrase would amount to an express exclusion within the meaning of Section 29(2) of the Limitation Act, and would therefore bar the application of Section 5 of that Act. Parliament did not need to go further. To hold that the court could entertain an application to set aside the award beyond the extended period under the proviso, would render the phrase "but not thereafter" wholly otiose. No principle of interpretation would justify such a result.

14. Here the history and scheme of the 1996 Act support the conclusion that the time-limit prescribed under Section 34 to challenge an award is absolute and unextendible by court under Section 5 of the Limitation Act. The Arbitration and Conciliation Bill, 1995 which preceded the 1996 Act stated as one of its main objectives the need "to minimise the supervisory role of courts in the arbitral process". This objective has found expression in the Section 5 of the Act which prescribes the extent of judicial intervention in no uncertain terms:

"5. Extent of judicial intervention. Notwithstanding anything contained in any Patna High Court MA No.449 of 2025 dt.11-12-2025

other law for the time being in force, in matters governed by this Part, no judicial authority shall intervene except where so provided in this Part."

16. Furthermore, Section 34(1) itself provides that recourse to a court against an arbitral award may be made only by an application for setting aside such award "in accordance with" sub-section (2) and sub-section (3). Sub-section (2) relates to grounds for setting aside an award and is not relevant for our purposes. But an application filed beyond the period mentioned in Section 34, sub-section (3) would not be an application "in accordance with" that sub-section. Consequently by virtue of Section 34(1), recourse to the court against an arbitral award cannot be made beyond the period prescribed. The importance of the period fixed under Section 34 is emphasised by the provisions of Section 36 which provide that "where the time for making an application to set aside the arbitral award the award shall be enforced under the Code under Section 34 has expired of Civil Procedure, 1908 in the same manner as if it were a decree of the court"

This is a significant departure from the provisions of the Arbitration Act, Patna High Court MA No.449 of 2025 dt.11-12-2025

1940. Under the 1940 Act, after the time to set aside the award expired, the court was required to "proceed to pronounce judgment according to the a award, and upon the judgment so pronounced a decree shall follow" (Section 17). Now the consequence of the time expiring under Section 34 of the 1996 Act is that the award becomes immediately enforceable without any further act of the court. If there were any residual doubt on the interpretation of the language used in Section 34, the scheme of the 1996 Act would resolve the issue in favour of curtailment of the court's powers by the exclusion of the operation of Section 5 of the Limitation Act.

50. Hon'ble Apex Court made it clear that one of the

main objective of 'the Act' is "to minimise the Supervisory role

of the Courts in the arbitral process."

51. The Hon'ble Apex Court further took note of

Section 36 of 'the Act' and recorded that once the time under

Section 34 of 'the Act' expires, the award immediately becomes

enforceable without any futher act of the Court.

52. There is a recent judgment of the Hon'ble Apex

Court in the case of State of West Bengal represented

through the Secretary & ors. vs. Rajpath Contractors and Patna High Court MA No.449 of 2025 dt.11-12-2025

Engineers Limited reported in (2024) 7 SCC 257 wherein

paragraph nos. 8 and 9 recorded as follows:

8. As per Section 12(1) of the Limitation Act, the day from which the limitation period is to be reckoned must be excluded. In this case, the period of limitation for filing a petition under Section 34 will have to be reckoned from 30-6-2022, when the appellants received the award. In view of Section 12(1) of the Limitation Act, 30-6-2022 will have to be excluded while computing the limitation period. Thus, in effect, the period of limitation, in the facts of the case, started running on 1-7-2022. The period of limitation is of three months and not ninety days. Therefore, from the starting point of 1-7-2022, the last day of the period of three months would be 30-9-2022. As noted earlier, the pooja vacation started on 1-10-2022.

9. We may note here that Section 43 of the Arbitration Act provides that the Limitation Act shall apply to the arbitrations as it applies to proceedings in the Court. We may note here that the consistent view taken by this Court right from the decision in Union of India v. Popular Construction Co.

is that given the language used in the proviso to sub-section (3) of Section 34 of Patna High Court MA No.449 of 2025 dt.11-12-2025

the Arbitration Act, the applicability of Section 5 of the Limitation Act to the petition under Section 34 of the Arbitration Act has been excluded.

(emphasis added)

53. As observed above, the admitted position is that

the award/order came to be passed on 26.04.2022, the petition

under Section 33 of 'the Act' filed thereafter too was rejected

on 31.05.2023. The three months period ended on 31.08.2023

by which an application under Section 34 of 'the Act' should

have been filed by the appellants. Further, alongwith the

sufficient reason explaining the delay, the petition could have

been filed upto 30.09.2023 and not thereafter. However, the

petition was filed only on 14.03.2024. Section 34(3) of 'the Act'

records three months and not 90 days and as such, there was

delay of 195 days in filing the petition. The award became

enforceable after the period under Section 34(3) of 'the Act'

came to an end.

54. In that background, the learned Principal District

Judge, Patna was fully justified in coming to the conclusion that

under no circumstances, it can entertain the application of the

apellants beyond the period mandated under Section 34(3) of

'the Act'. The well reasoned order dated 07.04.2025 passed in

Arbitration Case No. 18 of 2024 need no interference.

Patna High Court MA No.449 of 2025 dt.11-12-2025

55. M.A. No. 449 of 2025 stands dismissed.

56. Before parting, this Court must record its

disappointment in the manner, the Gaya International Airport is

being manned. People across the world specially those

following the teachings of Gautam Buddha take this Airport

route to visit Bodh Gaya, the place of Lord Buddha's

enlightenment. The moment they board the plane from their

respective countries, are in a pious mood thinking of visiting

their most reverred place. After alighting from the plane, they

touch the reverred ground of Lord Buddha and as such, the

Airport authorities are duty-bound to respect their sentiments

and extend best services in line with the purpose of their visit

and not in an unprofessional manner by treating them just as

normal passengers. It not only affects the prestige of the nation,

it hurts the sentiments of the devotees too. The Director, Gaya

Airport is expected to look into the matter and do the needful.

(Rajiv Roy, J) Vijay Singh/-

AFR/NAFR                AFR
CAV DATE                NA
Uploading Date          18.12.2025
Transmission Date
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter