Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Executive Engineer vs M/S. Modern Zipfasto Pvt. Ltd. & ...
2023 Latest Caselaw 6403 Ori

Citation : 2023 Latest Caselaw 6403 Ori
Judgement Date : 18 May, 2023

Orissa High Court
The Executive Engineer vs M/S. Modern Zipfasto Pvt. Ltd. & ... on 18 May, 2023
               IN THE HIGH COURT OF ORISSA, CUTTACK

                               W.P.(C) No. 5352 of 2020

       In the matter of an application under Articles 226 and 227 of
       the Constitution of India.

                              ---------------------

The Executive Engineer, Electrical (TPNODL), Bhadrak North Electrical Division, Bhadrak ........ Petitioner

-Versus-

       M/s. Modern Zipfasto Pvt. Ltd. & others
                                     ........                                       Opp. Parties

                For Petitioner                  :      Mr. S.C. Dash, Advocate

                For Opp. Parties                 :       None

                                                     ------------------
       P R E S E N T:

THE HONOURABLE SHRI JUSTICE BISWANATH RATH AND THE HONOURABLE SHRI JUSTICE M.S. SAHOO

----------------------------------------------------------------------------------------- Date of hearing: 05.05.2023 Date of Judgment : 18.05.2023

------------------------------------------------------------------------------------------ M.S.SAHOO, J

Introduction

The petitioner in the writ petition has stepped into the shoes of distribution licensee in place of the earlier licensee (NESCO Utility), which had filed the writ petition challenging the order dated 29.03.2019 passed in Consumer Representation (CR) Case No.OM(II)(N)-02 of 2018 by the Ombudsman-II, Orissa Electricity Regulatory Commission, // 2 //

Bhubaneswar vide Annexure-8 as well as the order dated 08.12.2017 passed by the Grievance Redressal Forum, Balasore in G.R.F.CC No.189 of 2017 vide Annexure-5.

Brief Facts

2. The predecessor of distribution licensee executed an agreement with the opposite party no.1-consumer on 09.05.1989 for a contract demand of 78KVA. Prior to such agreement the required electrical transformer for supply of electricity was installed by then Orissa State Electricity Board. It is alleged by the consumer that against his wishes, he was compelled to construct the electricity supply line and substation for the petitioner-distribution licensee in terms of a scheme known as Peoples Participation Scheme (PPS). It is further alleged that at the initial stage the transformer loss was added to the bills of the consumer as 730 units per month, which was opposed by the consumer and all on a sudden a bill was raised adding extra 365 units per month from January,1990 to July, 1997 as transformer loss in addition to the previous 730 units per month. Such a bill amounting to Rs.43,408.65 was served on the consumer.

Earlier writ petition before this Court and proceeding before GRF

3. Consumer-opp.party no.1 objected the revised bill vide his letter dated 21.04.1998, the imposition of meter rent was also objected by the consumer-opposite party no.1 by earlier letter dated 15.01.1998. Objection was filed by the petitioner vide letter dated 21.04.1998 objecting the demand for transformer loss. Then the opposite party no.1-Consumer approached this Court by filing OJC No.19456 of 1998. This Court by order dated 10.08.1998 directed the Consumer- opposite party no.1 for payment of Rs.20,000/-, as an interim

// 3 //

measure, which was paid by the petitioner on 17.08.1998, this Court vide order dated 22.06.2017 finally observed that the petitioner may approach the statutory forum, i.e., GRF. Following the direction of this Hon'ble Court, GRF Complaint Case No.189 of 2017 was filed before the GRF, NESCO, Balasore under Regulation-4 of OERC (Grievance Redressal Forum and Ombudsman) Regulation 2004 (herein after, in short 'Regulation 2004') contained the following prayers :

"A) Withdraw transformer loss from the account of the petitioner.

(B) Refund excess meter rent collected from the petitioner.

(C) Revised bills up to 08/1994 by extending 5% relief on the energy bill to the petitioner."

4. The distribution licensee filed their counter before the GRF giving detailed reply to the facts stated and contentions raised by the consumer.

The GRF by a detailed order dated 08.12.2017 passed in Complaint Case No.189 of 2017 analyzed the technical aspects in terms of the statute and definition particularly energy loss in transformer. The GRF relied on the provisions as indicated herein :

"Regulation 54(3) read with Regulation 93(9) of the OERC Distribution Code states that in case of High Tension supply, if HT metering set cannot be readily provided and installed, LT metering shall be provided and connected on the LT side of the consumer's transformer, the reading of such metering units shall be added with the average losses in the transformer."

5. As final order, the GRF directed the following :

"In the above facts and circumstances, we are inclined to direct the respondent to provide relief of 5% rebate on energy charges in terms of provisions of the applicable tariff order.

The respondent is directed to implement the order within 30 days from the date of receipt of it.

// 4 //

Proceeding before Ombudsman of OERC

6. Being aggrieved by the order passed by the GRF, the consumer moved the Ombudsman-II, OERC, Bhubaneswar by filing C.R. Case No.OM(II)(N)-2 of 2018 under Section 42(5) of the Electricity Act, 2003 read with Odisha Electricity Regulatory Commission, Distribution (conditions of supply) Code, 2004 (herein after in short, 'Code, 2004') with the following prayer :

"(a) To withdraw Tr. Loss units since 1/1990 to date of installation of HT meter, i.e., 01.04.2006

(b) To refund the excess meter rent after deducting the landing cost of meter.

(c) To provide 5% relief to comply the order of learned GRF, NESCO, Balasore."

7. Before the Ombudsman, the then distribution licensee filed their counter dated 06.03.2018 and additional reply- objection dated 07.05.2018. The Ombudsman delved into all the relevant aspects like pleadings of the parties, relied on the relevant notification : Orissa State Electricity Board Notification of 1992 and Regulation 54(3) read with Regulation 93(9) of OERC Distribution Code, 2004.

The Ombudsman, after analyzing the order and reasoning given by the GRF, gave the following finding ; that the GRF has not given the supporting facts and reason as to how they have come to the conclusion that the consumer was availing High Tension supply from the distribution licensee. Hence, the issue of supply voltage, whether High Tension or Low Tension needs to be examined in detail by the Ombudsman. Only after the issue of supply voltage is settled by the Ombudsman then the Ombudsman can go into the issue of transformer loss or otherwise.

After a detail scrutiny and reasoning, the Ombudsman has observed the following :

// 5 //

"The transformer loss arises only when the supply is at HT and it is billed under HT tariff whereas the meter is installed on the LT side. By addition transformer loss to the energy measured by the LT meter, one can arrive at the energy flowing at the supply point on HT side of the transformer, and by multiplying that total energy quantity to the HT supply tariff rate, the energy consumption charges to be collected from the HT consumer can be calculated. Thus, the energy consumption quantity and the tariff/rate applicable thereon, both of these are to be considered at the same point of sale/supply. Hence, energy is to be measured/quantified at the same point where the tariff rate is charges and/or being made applicable. If the consumer is being charged at LT tariff rate, then the supply is at LT and transformer loss cannot be added to the energy being measured by the LT meter, and only LT tariff rate is to be multiplied by energy measured in LT meter to arrive at the energy consumption charges to be collected from the LT consumer. In this regard, the argument of the Respondent referring Regulation 54 (3) and 93(9) of the O.E.R.C. Distribution (Conditions of Supply) Code 2004, is not appropriate, since this clause is applicable for HT supply consumers. Further, the argument of the respondent relying on their permission letter dated 13.03.1989 in paragraph-6 of the then Executive Engineer, BED, Bhadrak, is also not appropriate since this is in violation of the prevailing rules and regulations and also against the subsequently executed agreement dtd. 09.05.1989, which clearly states the supply to be at LT and rightly does not speak of any addition of transformer loss. Hence, the finding of GRF in this matter is over-ruled. Now, it needs to be examined as to when the petitioner consumer under MI category got convert from LT to HT supply, especially when there is no subsequent explicit written agreement executed by the parties in this respect.

Therefore, in consideration of the above facts and reasons, as regards reclassification of consumer from MI (LT) to MI (HT) category, both the parties are directed to execute a supplementary agreement for HT supply in accordance to Regulation 82 of OERC Supply Code 2004 with retrospective effect from May, 2004, in order to formalize the unwritten agreement continuing since then by treating the consumer as HT category consumer. Other requirements of Regulation 82 in this respect are deemed to have been complied with and prior to the month of May 2004. Further, since the consumer os treated to be under MI (HT) category since May 2004, when the metering is continuing on LT side till December, 2005, hence transformer loss can be kept added during the above period for calculation of electricity/energy consumption bill.

// 6 //

Accordingly, the order of the learned GRF in this matter is set aside."

8. Regarding revision of excess rent collected by the licensee towards meter after deducting the landing cost of the meter, Ombudsman has observed the following :

"From the aforesaid arguments of both the parties and after going through the observation of the learned GRF, it has been observed that the Hon'ble OERC in their RST order for FY 2013-14 at its Note (ii) allowed the respondent to collect meter rent for 60 months from the existing and new consumers, and the same order is continuing till date. As the petitioner is now claiming for refund of excess meter rent, this Authority is of opinion that the aforesaid Tariff Order is applicable to the present petitioner. Hence the respondent is allowed to collect/retain meter rent from the petitioner for 60 months since its installation/replacement by the respondent through monthly energy bills and not to collect meter rent any further after lapse of 60 months. It is seen from the submission of the parties that the respondent licensee has installed it's LT meter replacing the original LT meter belonging to the consumer on 20.10.1997. Hence, excess meter rent collected from the petitioner beyond 60 months, (i.e., from November 1997) by the respondent is to be refunded to the petitioner through adjustment in the subsequent monthly energy bills of the petitioner. Accordingly, the order of the learned GRF in this respect is set aside.

9. Regarding the prayer to provide 5% rebate on energy bill by the licensee to comply the order of GRF, Balasore, the Ombudsman has observed the following :

"From the aforesaid arguments of both the parties, it is seen that the petitioner has prayed before this Authority to allow 5% rebate during the aforesaid period (i.e. in effect treating himself as taking supply on HT), whereas simultaneously and surprisingly he has also prayed for revision of bills withdrawing transformer loss since he demands to be considered as LT consumer during the said period. Both these prayers of the petitioner appear to be contradictory in nature. This Authority, in its above observations, has already concluded that the petitioner is a LT consumer till 04/2004, and accordingly have set aside the order of the learned GRF in this respect. Only in case of HT consumer, 5% rebate is allowed to the consumers, which is as per the then rules and regulations

// 7 //

in force and accordingly the learned GRF has ordered for providing 5% rebate to the consumer. Since now it has clearly been established that the petitioner is a LT consumer during the relevant period, relief regarding 5% rebate is not allowed to the present petitioner. In this regard, the order dated 08.12.2017 in Case No.189 of 2017 of the learned GRF, Balasore is set aside.

10. The operative portion of order passed by the Ombudsman is reproduced herein :

"In view of the above facts and circumstances, this Authority pronounces the following :

1. The respondent is directed to revise the bills of the petitioner by treating him as LT consumer and withdrawing the transformer loss units from the account of the petitioner from the month of initial power till April, 2004, and as HT consumer including transformer loss from May 2004 till December, 2005.

2. The respondent is directed to retain 60 months meter rent from the petitioner w.e.f. the month of 11/1997 with prevailing rate of meter rent as applicable during that period in accordance to rules and regulations in force, and refund the excess meter rent collected beyond 60 months to the petitioner through adjustment in the subsequent monthly energy bills on account of the petitioner.

3. The DPS amount on excess billing needs to be accordingly withdrawn/adjusted and the revised bill is to comply with the provisions of Regulation 92 of OERC Supply Code 2004, read with other applicable statutory provisions in force."

Submission and contentions raised on behalf of the petitioner

11. Heard Mr. S.C. Dash, learned counsel for the Distribution Licensee.

Since the notice have not yet been issued and the matter is pending since 2020, in view of the conclusions of this Court as would subsequently follow that the matter does not involve any substantial question of law, no notice were issued to the opposite parties as the matter is dealt with and disposed of based on the pleadings of the parties already on record before GRF and the Ombudsman. It be made clear

// 8 //

that the case at hand has been decided at the stage of fresh admission.

12. Learned counsel for the petitioner with all vehemence at his command submitted that both the GRF and Ombudsman have exceeded their respective statutory power and jurisdiction to entertain the complaints which are barred by time and the claim raised by the consumer are fake, vague and baseless. The Ombudsman's calculation on transformer loss is based on wrong adoption of method of calculation. It is further contended that the direction of the Ombudsman to refund the excess rent collected as meter rent by the licensee, is contrary to the Regulations of Orissa State Electricity Board (General Conditions of Supply) Regulations, 1981.

13. Learned counsel for the petitioner-licensee further relies on paragraph-23 of an order passed by a Division Bench of this Court dated 26.08.2022 in W.P.(C) No.12735 of 2019 (The Executive Engineer, Electrical (NESCO Utility) Baripada Electrical Divn., Baripada, Dist. Mayurbhanj v. M/s. Kamadhenu Agro based Ind.(P) Ltd., Mayurbhanj) which is quoted herein :

"23.In this regard, we may refer to Regulation 54(3) of the Code, 2004 which provides that in the case of all new high-tension supplies, HT metering units shall be provided and installed. In case where LT metering unit is provided at L.T. side, all L.T. metering units shall be converted to H.T. metering units. For existing L.T. metering units connected on the L.T. side of consumer's transformers, the reading of such metering units, shall be added with the average loss in the transformers calculated in terms of the formula given thereunder. As such, the opinion that no transformer loss can be charged on the consumer if it is below 70 KVA is without any tangible basis. Even it has not been demonstrated that the consumer had asked for reassessment of terminating the conditions of supply."

// 9 //

Analysis and Conclusion

14. Having heard learned counsel for the petitioner and having gone through the pleadings before the GRF as well as Ombudsman, this Court is of the view that there is no error apparent on the face of the record in the order passed by the Ombudsman as the statutory authority has dealt with the rival contentions of the consumer-opposite party no.2 herein and the supplier of the electricity/distribution licensee/petitioner herein. The relevant factual aspects have been noted in detail and the provisions of law have also been referred to.

15. A careful scrutiny of the pleadings of the erstwhile distribution licensee would show that the objection regarding the claims being barred by time, were raised before the GRF, but the GRF went on to adjudicate the matter on merit thereby rejecting the plea of the limitations by the licensee, and the order passed by the GRF to a large extent was in favour of the licensee.

It has also to be noticed, the bill was raised by the licensee for the period from January, 1990 to July, 1997 on 10th December, 1997 and the consumer objected the said bill on 21.02.1998, i.e., within two months the consumer issued a letter in objection thereafter on 21.04.1998 approached this Court by filing OJC No.10456 of 1998 which was disposed of by order dated 22.06.2017 directing the petitioner to approach GRF.

16. Considering the above sequence of representation and litigation, the plea of petitioner before the GRF and the Consumer Representation Case before the Ombudsman being barred by limitation which was rejected by both the forums, is also rejected by this Court. It has also to be noted

// 10 //

that after disposal of the writ petition on 22.06.2017, directing the consumer to approach the statutory forum 'GRF', the Consumer Complaint case was filed before the GRF on 21.08.2017.

17. The following has been stated at paragraph-18 of the writ petition to assail the order passed by the Ombudsman. The averments are reproduced herein :

"18. For that the learned Ombudsman while deciding the 2nd issue/claim for refund of excess meter rent as alleged to have been collected w.e.f. the month of 11/1997 has based his finding on the RST Order of OERC for the FY. 013-14 which speaks for collection of meter rent for 60 months only where cost of the meter to be realized from the consumer is not ascertained. The above tariff order of OERC has no retrospective application for the past periods from 1997 being contrary to Regulation-22 (a) of the OSEB (General Conditions of supply) Regulations, 1981 as was prevalent then. Since the meter was supplied by the Board, the Consumer was liable to pay the meter rent so long the meter functions 'OK'. Hence the impugned Order vide Annexure-8 being contrary to the aforesaid Regulation is not sustainable in law & as such liable to be quashed."

Evidently, such plea as contained in para-18 of the writ petition was not raised by the licensee in their counter dated 06.03.2018 and additional reply-objection dated 07.05.2018 (Annexure-7 series) before the Ombudsman.

Further, the finding by the Ombudsman regarding tariff order of the Financial Year 2004-05 and onwards, issued by the Orissa Electricity Regulatory Commission clarifying about the meter rent, i.e., no meter rent should be collected by the licensee after recovery of the landing cost of the meter, has not been denied by the petitioner-licensee.

18. On going through the order relied on by the petitioner- licensee dated 26.08.2022 passed by a Division Bench of this Court in WPC No.12735 of 2019, particularly paragraph-23, it has to be held that the said decision is of no avail to the

// 11 //

distribution licensee as in the case at hand, the Ombudsman in its award has directed that the consumer is to be treated as LT consumer from the date of initial power supply till April, 2004 and as HT consumer from May, 2004 till December, 2005. Once the consumer is treated to be as LT consumer as per the existing agreement, the principle followed in :Kamadhenu Agro (supra) will not apply. Further if the petitioner is treated as HT consumer, the principles of Kamadhenu Agro (supra) would also not apply inasmuch as the order in Kamadhenu Agro (supra) was rendered in the peculiar facts of that case where the HT meter unit could not be provided by the licensee and instead LT metering unit was provided though the consumer was treated as HT consumer as per the agreement.

In the present case, the consumer is treated as a LT consumer as per the agreement between the consumer and the licensee for a certain period up to April, 2004 and thereafter it is directed to be treated as HT consumer from April, 2004 till December, 2005.

Scope of Judicial Review by this Court of the findings by the statutory bodies like GRF and Ombudsman of OERC

19. It would be apt to refer to the decisions rendered by the Hon'ble Supreme Court. In the case of Reliance Infrastructure Limited v. State of Maharashtra [(2019) 3 SCC 352], the Hon'ble Supreme Court observed regarding the scope of judicial review of the findings of an expert body like Electricity Regulatory Commissioin. It was held at paragraphs 38 & 39 of SCC :

"38. MERC is an expert body which is entrusted with the duty and function to frame regulations, including the terms and conditions for the determination of tariff. The Court, while exercising its power of judicial

// 12 //

review, can step in where a case of manifest unreasonableness or arbitrariness is made out. Similarly, where the delegate of the legislature has failed to follow statutory procedures or to take into account factors which it is mandated by the statute to consider or has founded its determination of tariffs on extraneous considerations, the Court in the exercise of its power of judicial review will ensure that the statute is not breached. However, it is no part of the function of the Court to substitute its own determination for a determination which was made by an expert body after due consideration of material circumstances.

39. In Assn. of Industrial Electricity Users v. State of A.P. [Assn. of Industrial Electricity Users v. State of A.P., (2002) 3 SCC 711] b three-Judge Bench of this Court dealt with the fixation of tariffs and held thus : (SCC p. 717, para 11) "11. We also agree with the High Court [S. Bharat Kumar v. State of A.P., 2000 SCC OnLine AP 565 : (2000) 6 ALD 217] that the judicial review in a matter with regard to fixation of tariff has not to be as that of an appellate authority in exercise of its jurisdiction under Article 226 of the Constitution.

All that the High Court has to be satisfied with is that the Commission has followed the proper procedure and unless it can be demonstrated that its decision is on the face of it arbitrary or illegal or contrary to the Act, the court will not interfere. Fixing a tariff and providing for cross-subsidy is essentially a matter of policy and normally a court would refrain from interfering with a policy decision unless the power exercised is arbitrary or ex facie bad in law."

xxx xxx xxx

20. Recently, the Constitution Bench of the Hon'ble Supreme Court in the case of Vivek Narayan Sharma v.

Union of India [2023 SCC OnLine SC 1] has held that the Courts should be slow in interfering with the decisions taken by the experts in the field and unless it is found that the expert bodies have failed to take into consideration the mandatory statutory provisions or the decisions taken are

// 13 //

based on extraneous considerations or they are ex facie arbitrary and illegal, it will not be appropriate for this Court to substitute its views with that of the expert bodies."

21. Relying in the above judgments, the Hon'ble Supreme Court in Civil Appeal No. 11095 of 2018 (GMR WARORA Energy Limited v. Central Electricity Regultory Commission (CERC) & others) : decided on 20.04.2023 has held :

130. As is indicated in the aforesaid judgments, this Court should be slow in interfering with the concurrent findings of fact unless they are found to be perverse, arbitrary and either in ignorance of or contrary to the statutory provisions.

[Emphasis supplied]

22. By applying the principles laid down in MSEDCL v. APML & Others : 2023 SCC Online 233, we hold that this Court has to be slow in interfering with the findings given by an expert body like Ombudsman-II, OERC. As has been held in Association of Industrial Electricity users v. State of A.P. (2002) 3 SCC 711, all that this Court has to be satisfied is that the Ombudsman has followed the proper procedure. Unless it can be demonstrated that the decision is on the face of it arbitrary or illegal or contrary to the Act, this Court would not interfere.

23. Following the principle laid down in the decision rendered by the Constitution Bench of the Hon'ble Supreme Court in Vivek Narayan Sharma v. Union of India (supra), it is held that this Court should be slow in interfering the decision taken by expert in the field, i.e., Ombudsman of OERC and unless it is found that the expert body has failed to take into consideration the mandatory statutory provision or the

// 14 //

decisions taken is, based on extraneous considerations or it is ex-facie arbitrary and illegal. It would not be appropriate for this Court to substitute its views with that of the expert body.

24. To sum up, applying the principles discussed above to the present case, it has to be held that the petitioner has failed to bring to the notice of this Court that any of the mandatory statutory provisions have not been considered by the Ombudsman. The petitioner has also failed to show that the decision of the Ombudsman is based on extraneous consideration. To reiterate the principles laid down in Vivek Narayan Sharma (supra), this Court should be slow in interfering with the findings of the fact unless they are found to be perverse, arbitrary and in ignorance or contrary to the statutory provisions.

Further, in considered opinion of this Court no case has been made out by the petitioner-licensee to interfere with the findings of the Ombudsman being the competent authority technically to analyze the technical aspect of the pleadings of the parties. Therefore, it is held that this Court cannot substitute the findings of the Ombudsman without any material being brought to dislodge the findings.

25. In view of the above discussions, the writ petition fails. The order passed by the Ombudsman be complied with forthwith. In the facts and circumstances of the case, there shall be no order as to costs.

.......................... ....................... Biswanath Rath, J.

Signature Not Verified                                                     M.S.Sahoo, J.
Digitally Signed
Signed by: AJIT KUMAR DUTTA
Designation: Secretary

Reason: AuthenticationOrissa High Court, Cuttack Location: ohc The 18th May, 2023/dutta Date: 23-May-2023 14:07:51

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter