Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Executive Engineer vs Ombudsman-Ii Of Electricity
2023 Latest Caselaw 5584 Ori

Citation : 2023 Latest Caselaw 5584 Ori
Judgement Date : 10 May, 2023

Orissa High Court
The Executive Engineer vs Ombudsman-Ii Of Electricity on 10 May, 2023
          A.F.R.          IN THE HIGH COURT OF ORISSA, CUTTACK

                                      W.P.(C) No.15006 of 2017

              In the matter of an application under Articles 226 and 227 of
              the Constitution of India.
                                        ---------------------

The Executive Engineer, (Electrical), (erstwhile NESCO),Presently-TPNODL, Jajpur Road Electrical Division, Dist-Jajpur ........ Petitioner

-Versus-

OMBUDSMAN-II of Electricity, Bhubaneswar and another ........ Opp.Parties

For Petitioner : Mr. S.C.Dash, Advocate

For Opp.party no. 2 : Mr. S.K.Patnaik, Sr. Advocate Instructed by Mr. P.K.Pattnaik

------------------

P R E S E N T:

THE HONOURABLE SHRI JUSTICE BISWANATH RATH AND THE HONOURABLE SHRI JUSTICE M.S. SAHOO

------------------------------------------------------------------------------------------

Date of hearing: 05.05.2023 Date of judgment: 10.05.2023

------------------------------------------------------------------------------------------ M.S.SAHOO, J

Introduction

The writ petition has been filed by the petitioner- Distribution Licensee challenging the order/award dated 25.02.2017 passed in Consumer Representation (C.R.) Case No.37 of 2015 by the Ombudsman-II, Orissa Electricity Regulatory Commission (Annexure-5), exercising powers under Clause-7 of OERC (GRF & Ombudsman) Regulations, 2004 (hereinafter in short, "Regulations, 2004").

// 2 //

2. The judgment of Ombudsman passed in C.R. Case is result of the petition filed by the present opposite party no.2.-Consumer.

3. It has to be noted that the present petitioner has stepped into the shoes of the earlier licensee, namely, NESCO and the present opposite party no.2 has stepped into the shoes of its predecessor, Idea Cellular Infrastructure Ltd. Both the petitioner and opposite party no.2 have been substituted duly in view of they coming to existence in place of the earlier distribution licensee and the consumer respectively by due process of law.

Brief Facts

4. The Distribution licensee and the consumer entered into an agreement dated 05.10.2009 for supply of 15KW load and voltage of supply at 11 KV for purpose of VTS Tower at Sathipur in the district of Jajpur.

Proceeding before the Grievance Redressal Forum 4.1 The consumer/opposite party no.2 raised a complaint before the Grievance Redressal Forum, Jajpur Road, alleging;

(i) that the distribution licensee in contravention of Regulation 13(1) of the OERC Distribution (Conditions of Supply) Code, 2004 (hereinafter in short, "Code, 2004") did not extend remunerative benefit to the consumer;

(ii) Instead of licensee providing the supply system as the contract demand was less than 70 KVA, in contravention of Regulation-76(1) (c) of the Code, 2004,

// 3 //

the petitioner was asked and compelled for construction of his electricity supply line;

(iiii) the billing for the consumer was done at low tension (LT) tariff, as per the different tariff orders of the OERC and the consumer could not have been imposed transformer loss along with its energy charges being billed on LT tariff. However, the licensee charged transformer loss in each bill, which is in contravention of Regulation 93(9) of the Code, 2004;

(iv) in contravention of Regulation 54(3) of the Code, 2004, the licensee did not provide HT metering set. 4.2 Based on the above contentions, the consumer in its petition before the GRF made the following prayer:

Extend remunerative benefit to the petitioner.

1. Withdraw transformer loss from the bill and accordingly bill to be revised.

2. Extend TOD benefit from the available dump data or 1/4th units of the petitioner's consumption of the meter as off-peak is being 6 hours only i.e., 1/4th of a day.

3. Revise demand charges as per different tariff orders of Hon'ble OERC but not on the basis of contract demand.

4. Extend OYT benefit from April, 2011 onwards as such scheme as applicable from the RST order from 2011-12."

5. The present petitioner-opposite party before the GRF/Distribution licensee, filed their counter denying that remunerative benefit can be extended to the consumer. Regarding LT/HT billing, it was stated :

that as per Retail Supply tariff order in force, General purpose consumers with Contract Demand (CD)

// 4 //

less than 70 KVA shall be treated as LT consumers for Tariff purposes irrespective of level of supply of voltage. This implies that instead of flat rate of energy charge @ Rs.5.05 per unit billing is being done on slab rate applicable to General purpose category. Monthly energy bill in respect of the consumer is prepared by summation of units consumed and applicable transformer loss units since supply voltage is 11000 volts and metering is done on LT side of the transformer. Contract demand of the consumer being 15 KW Service Connection estimate with installation of TP Box for whole current meter is provided and a whole current meter bearing No.NDT 00842 is also installed in the consumer's premises. 5.1 In response to the prayer no.iii before the GRF, the licensee denied the same on the following reasoning :

"In reply to prayer at © it is submitted that TOD benefit extended to the consumers on record based data of the static meter installed having facility of recording hourly consumption with a memory of 31 days and downloading print out drawing power during off peak hours. Hence prayer made by the petition for extending TOD benefit proportionately so ¼th of the consumption is baseless and may be rejected."

5.2 In response to prayer no.4, the distribution licensee stated before the GRF as follows :

"iv. As regards to revision of demand charge as prayed at (d) it is submitted that the matter is pending before the Hon'ble High Court of Odisha in W.P.(C) No.3881 of 2013 & Misc. Case No.3758 of 2013 between Flexi Multi Products and NESCO Ltd. Action will be taken for revision if due on receipt of necessary order."

// 5 //

5.3 Regarding installation of the transformer, it was stated by the distribution licensee before the GRF that the date of power supply of the concerned consumer is 24.10.2009 and the consumer has been permitted to install his own transformer prior to the effective date of Retail supply tariff order dated 18.03.2011 and had also installed his own transformer well before. Hence neither the petitioner is an intending consumer nor has deposited such cost of high voltage distribution scheme.

6. The GRF disposed of C.C.No.171 of 2014 with the following order :

"Heard both the parties. Perused all the corresponding documents. Having done so, it is felt by the members of the Forum that OYT benefit as applicable from April, 2011 onwards should be made admissible to the petitioner with immediate effect. Other prayers of the petitioner are disposed off without any result for the reasons elaborated in the "OBSERVATION".

Proceeding before Ombudsman of OERC

7. Thereafter, the consumer moved the Ombudsman - II, OERC, Bhubaneswar by filing C.R.Case No.37 of 2015 dated 17.07.2015 against the order passed by the GRF with the following prayer :

"For the interest of justice and equity the Hon'ble Ombudsman-II may graciously be pleased to admit the case and direct the respondent to :

a) Extend OYT scheme benefit as per Order No.112(2) dated 10.03.2015 of the GRF, NESCO, Jajpur Road in Case No.171 of 2014. And adjudicate the matter on the following prayers of the petitioner for extending following benefits:

b) To extend remunerative benefit to the petitioner.

// 6 //

c) To withdraw transformer loss from the bill and accordingly bill to be revised.

d) To extend TOD benefit from the available dump data or 1/4th units of the petitioner's consumption of the meter as off-peak is being 6 hours only i.e., 1/4th of a day.

e) To revise demand charges as per different tariff orders of Hon'ble OERC but not on the basis of contract demand."

8. The distribution licensee by their counter reply dated 24.08.2015 filed before the Ombudsman denied the claim of the consumer stating in response to the prayer (a) to (e) that the consumer is not entitled for availing remunerative benefit. Even though the consumer billed as LT, still is liable to be imposed transformer loss; the petitioner is not entitled to TOD benefit; the demand charge revision is pending adjudication before the High Court of Orissa in W.P.(C) No.3881 of 2013 (Flexi Multi Products and NESCO Ltd.) and action can be taken after the orders of the High Court and lastly it was stated the petitioner-consumer was required to install the transmission line and transformer, there being no irregularity as alleged.

9. The Ombudsman after dealing with the pleadings of the consumer as well as the distribution licensee in detail especially the technical aspects which the Ombudsman is competent to deal with, held that :

9.1 Non-extension of remunerative benefit to the consumer, is in contravention of Regulation 13(1) of the Code, 2004 as per the tariff orders of the statutory authority, i.e., OERC, the remunerative benefits should

// 7 //

be attached with the estimate of the power consumption of the consumer.

There is no provision for transformer loss for LT consumer. It remains undisputed that the consumer is billed as a LT consumer but the licensee has imposed 183 Units as transformer loss in each bill which is to be held as illegal.

9.2 For such findings, the Ombudsman relied on the Note-xiii of RST order for the year 2015-16 with a further finding that while deciding the LT tariff, the transformer loss has already been taken into consideration, therefore, imposition of transformer loss of a consumer billed in LT tariff, would amount to double recovery towards transformer loss which cannot be justified. 9.3 Regarding TOD benefit whether to be granted to the consumer or not, the Ombudsman has given the following reasoning and finding :

"TOD benefit:

As per the RST order 2005-06 at para-8.31.2, three phase consumers with static meters are allowed to avail TOD rebate excluding the public lighting and emergency power supply to CGP @ 10 paisa per unit for energy consumed during off peak hours. Off-peak hours has been defined as 10 PM to 6 AM which has been modified to 12.00 midnight to 6AM subsequently.

The above incentive is allowed to the consumers to increase their drawal during off peak hours so as to reduce the difference between peak and off-peak demand and flatten the load curve so that the generation capacity will be better utilized. The petitioner has complained that TOD benefit has not been given to him so far. The respondent is directed to extend TOD benefit to the consumer

// 8 //

based on the prevailing tariff order prospectively and based on the dump data available with the licensee for the retrospective period."

9.4 Regarding demand charges, the Ombudsman has given the following finding :

"Demand charges:

As per Regulation-64 as well as RST order for 2005-06 the demand charge/MMFC charges are to be raised based on recorded demand for the consumers below 110 KVA having static meter. As complained by the consumer, the licensee is not raising demand charge on recorded demand but claiming the same on the contracted demand which is violating the Regulation as well as tariff orders of Hon'ble OERC. The respondent is directed to raise the demand charge/MMFC based on orders of Hon'ble OERC prospectively and for the retrospective period starting from the date of power supply onwards based on the dump data available with them & considering applicable tariff orders for the period. The amount of refund or claim if any should be reflected in the next bill."

10. Based on the above findings, the Ombudsman has given the award as follows :

"1. To withdraw the claim towards transformer loss from the bill of the consumer from the date of power supply to till date and stop billing against transformer loss in future bills.

2. To extend TOD benefit to the consumer based on the prevailing tariff order prospectively and based on the dump data available with the licensee for the retrospective period starting from the date of power supply.

3. To raise the demand charge based on the recorded maximum demand as per the orders of Hon'ble OERC prospectively and for the retrospective period starting from the date of power supply onwards based on the dump data

// 9 //

available with them & tariff orders of OERC for respective years.

4. To allow OYT rebate to the consumer as per orders of GRF, Jajpur Road vide order dated 10.03.2015 in Case No.171 of 2014.

The respondent is directed to revise the bills of the petitioner as per above direction and serve to the petitioner within 30 days from the date of receipt of letter of acceptance from the petitioner and file compliance to this Forum within 45 days. The petitioner is directed to pay the revised bill amount within 30 days from the date of receipt of revised bill from the respondent."

Submissions of the learned counsel

11. Heard Mr. S.C. Dash, learned counsel for the petitioner-distribution licensee and Mr. S.K. Patnaik, Senior Advocate instructed by Mr. P.K.Pattanaik for opposite party-consumer.

Mr. Dash, learned counsel for the petitioner with all vehemence submitted that the order passed by the Ombudsman is unsustainable as the judgment was delivered after the expiry of stipulated time of 60 days hearing prescribed under Clause-7(4) of the Regulation, 2004. The Ombudsman has not taken into consideration the objection filed by the licensee in response to the consumer representation case. The Ombudsman did not make an effort for conciliation between the parties. It is further submitted that the order passed by the Ombudsman is unsustainable in law and is liable to be set aside.

12. Learned Senior Counsel appearing for the consumer submits that the order passed by the Ombudsman is just and proper. The High Court in exercise of the jurisdiction

// 10 //

under Article 226 of the Constitution of India, can interfere with the order passed by the statutory authority only if there is error apparent on the face of the record as per the law laid down by the Hon'ble Supreme Court. It is further submitted that this Court does not sit in appeal over the finding of the fact and the technical issues dealt with by the Ombudsman of OERC and this Court cannot substitute its own views as far as the finding of facts by the GRF & Ombudsman are concerned. It is finally submitted there being no error apparent on the face of the record, the order passed by the Ombudsman being just and proper, the attempt of the distribution licensee to challenge the same, should fail.

Analysis & Conclusion The relevant provisions of laws dealt with by the Forums such as the Ombudsman and the GRF are quoted herein :

"54(3). In the case of all new high-tension supplies, HT metering units shall be provided and installed. In case where LT metering unit is provided at L.T. side, all L.T. metering units shall be converted to H.T. metering units. For existing L.T. metering units connected on the L.T. side of the consumer's transformers, the reading of such metering units, shall be added with the average losses in the transformers calculated as below:

(a) Energy loss in transformer in units per month = (730 X rating of the transformer in KVA) /100,

(b) Demand loss in transformer in KVA = One percent of the rating of the transformer in KVA

93(9) In the case of High Tension supply, if HT metering set can not be readily provided and installed, LT metering set shall be provided and connected on the LT side of the

// 11 //

consumer's transformers. To the reading of such metering set, will be added the average losses in the transformers calculated as follows:

(a) Energy loss in transformer in units per month = (730 X rating of the transformer in KVA)/100,

(b) Demand loss in transformer in KVA = One percent of the rating of the transformer in KVA. Pass Book/ Meter reading Card"-

Connected Load and Contract Demand

64. Contract demand for loads of 110 KVA and above shall be as stipulated in the agreement and may be different from the connected load. Contract demand for a connected load below 110 KVA shall be the same as the connected load. However in case of installation with static meter/meter with provision of recording demand, the recorded demand rounded to nearest 0.5 Kw shall be considered as the contract demand requiring no verification.

85. (1) Monthly demand charges shall be payable by the consumer on the basis of maximum demand and contract demand as determined in the tariff notification. In case maximum demand meter is not provided or the meter has become defective, the monthly demand charges shall be payable on the basis of contract demand as determined in the tariff notification.

(2) Such monthly demand charges shall be payable during the continuance of the agreement under Regulation 15 even if no electricity is consumed for any reason whatsoever or supply has been disconnected due to default of the consumer.

(3) During statutory power-cuts and power restrictions imposed by the licensee, if the restriction on demand is imposed for a period exceeding sixty hours in a month, the 44 monthly demand charges shall be prorated in accordance with the period and quantum of demand restrictions imposed. In all other cases the consumer shall be liable to pay the full demand charges.

13. Having heard learned counsel for the parties and having gone through the pleadings before the GRF as

// 12 //

well as Ombudsman, this Court is of the view that there is no error apparent on the face of the record as the Ombudsman has dealt with the rival contentions of the consumer-opposite party no.2 herein and the supplier of the electricity/distribution licensee/petitioner herein. The relevant factual aspects have been noted in detail and the provisions of law have also been referred to.

14. The claim of the consumer regarding remunerative benefit has been rejected by the GRF and the Ombudsman.

15. Regarding TOD benefit, in our opinion, it has been correctly observed by the Ombudsman that the licensee shall extend the benefit based on the prevailing tariff order prospectively and the calculation is to be based on the dump data available with the licensee for the period. The consumer being a cellular telephone service provider through the tower which has been supplied electricity by the licensee and the consumption is throughout the day, uniform, therefore, there is no difference between peak hours and off-peak hours, i.e., off-peak being defined as 12 midnight to 6 A.M. of the next day.

16. Regarding the prayer of the consumer to charge it MMFC charges based on recorded payment, on the basis of Regulation-64 of the 2004 Regulation as well as the RST order for 2005-06, the decision of the Ombudsman is upheld as it has directed licensee to raise the demand charge and MMFC on basis of the orders of the OERC, the order of the OERC being binding on the licensee which notifies the applicable tariff orders. The order of

// 13 //

the Ombudsman has also clarified that on basis of such calculation, there may be amount of refund towards consumer or there may not be claim by the licensee which in considered view of this Court, is just and proper.

17. Regarding the duty to hold conciliation between the parties, the Ombudsman in its order has specifically noted that on 16.09.2015 attempt for conciliation failed. Till 16.09.2015, on various dates i.e., 10.08.2015, notices were issued to attend the conciliation. On 13.08.2015, 11.08.2015, the petitioner-licensee filed time petition, the matter was adjourned to 24.08.2015. On 24.08.2015, the petitioner-licensee filed counter, opposite party no.2 wanted time to prepare the rejoinder and the matter was adjourned to 16.09.2015. Therefore, this Court rejects the contention of the petitioner that there was no attempt for conciliation

18. The finding of fact by the Ombudsman that amount towards transformer loss is included in the tariff determined by the OERC remains uncontroverted inasmuch as the licensee failed to produce any of the tariff orders of the OERC before the GRF or the Ombudsman to support its contention to indicate that in fact for determination of LT tariff, transformer loss was not included. The consumer's assertion that he is being billed on the basis of LT tariff, has been consistently accepted by the petitioner-licensee. But for reasons best known to the licensee, it did not bring any material much less any tariff order of the OERC to at least demonstrate

// 14 //

before the GRF or the Ombudsman that transformer loss has not been taken into account in LT tariff.

19. Therefore, finding of the Ombudsman that after the licensee has collected electricity duty/charges for transformer loss having billed to the consumer in LT tariff which includes transformer loss, further imposition of charges towards transformer loss would amount to collection of the amount twice and should not be permitted, has to be upheld by this Court being just and proper.

20. In our considered opinion though there has been apparent delay in delivering the order by the Ombudsman, since the order is passed after detailed consideration of all the pleadings after thorough participation of both the parties, setting aside the same only on the ground that more time was taken than the prescribed period for delivery of order/judgment, would not be in the interest of justice and shall also cause hardship to both the parties, who are pursuing the litigation since 2014 and in the meanwhile nine years have passed.

The relevant provisions prescribing the time for the Ombudsman to deliver an order after adjudication is quoted herein :

7(4) The Ombudsman shall decide the representation generally within two months from the date of receipt of the representation of the consumer. In the event the representation is not decided within two months, the Ombudsman shall record the reasons therefor including the cost to be paid by the Licensee if the inability to decide within the time is attributable to the Licensee. In case the delay is for reasons attributable to the

// 15 //

Consumer, the Ombudsman may reject the representation of the consumer."

The contention of the opposite party no.2-consumer-

petitioner that he is not responsible for any delay that has occurred while delivering the order is correct, as is evident from the proceedings before the Authority.

It is also not brought to the notice of this Court if at all any of the parties ever appeared/approached/filed petition before the Ombudsman regarding pendency of the matter beyond the time limit for pronouncement of the order, so as to prove the bonafides of the stand taken in this regard by the licensee before this Court. As it appears, only after the order of the Ombudsman went against the licensee to certain extent they have raised such a plea.

Further, there is no denial before any forum or this Court regarding the assertions that the consumer was billed on LT tariff.

Scope of judicial review of the findings given by expert statutory bodies like GRF/Ombudsman of OERC

21. It would be apt to refer to the decision rendered by the Hon'ble Supreme Court in Civil Appeal No. 11095 of 2018 (GMR WARORA Energy Limited v. Central Electricity Regultory Commission (CERC) & others) : decided on 20.04.2023, regarding "concurrent finding of fact. In GMR (supra), the Hon'ble Supreme Court has observed as follows (paragraphs-127. 129 and 130) :

Concurrent Finding of Fact

// 16 //

127. Apart from the aforesaid issues, there is one another common thread in all these appeals. Many of these appeals arise out of concurrent findings recorded by the Central/State Electricity Regulatory Commissions and the learned APTEL.

128. This Court, in the case of MSEDCL v. APML & Ors.a (supra), after considering the statutory provisions in the Electricity Act, 2003, held that the CERC, SERCs and the learned APTEL are bodies consisting of experts in the field.

129. This Court, in the said case, observed thus:

"120. It could thus be seen that two expert bodies i.e. the CERC and the learned APTEL have concurrently held, after examining the material on record, that the factors of SHR and GCV should be considered as per the Regulations or actuals, whichever is lower. The CERC as well as the State Regulatory bodies, after extensive consultation with the stakeholders, had specified the SHR norms in respective Tariff Regulations. In addition, insofar as GCV is concerned, the CEA has opined that the margin of 85-100 kcal/kg for a non-pit head station may be considered as a loss of GCV measured at wagon top till the point of firing of coal in boiler.

121. In this respect, we may refer to the following observations of this Court in the case of Reliance Infrastructure Limited v. State of Maharashtra [(2019) 3 SCC 352].

"38. MERC is an expert body which is entrusted with the duty and function to frame regulations, including the terms and conditions for the determination of tariff. The Court, while exercising its power of judicial review, can step in where a case of manifest unreasonableness or arbitrariness is made out. Similarly, where the delegate of the legislature has failed to follow statutory procedures or to take into account factors which it is mandated by the statute to consider or has founded its determination of tariffs on extraneous considerations, the Court in the exercise of its power of judicial review will ensure that the statute is not breached. However, it is no part of the function of the Court to substitute its own determination for a

// 17 //

determination which was made by an expert body after due consideration of material circumstances.

39. In Assn. of Industrial Electricity Users v. State of A.P. [Assn. of Industrial Electricity Users v. State of A.P., (2002) 3 SCC 711] b three-Judge Bench of this Court dealt with the fixation of tariffs and held thus : (SCC p. 717, para 11) "11. We also agree with the High Court [S. Bharat Kumar v. State of A.P., 2000 SCC OnLine AP 565 : (2000) 6 ALD 217] that the judicial review in a matter with regard to fixation of tariff has not to be as that of an appellate authority in exercise of its jurisdiction under Article 226 of the Constitution.

All that the High Court has to be satisfied with is that the Commission has followed the proper procedure and unless it can be demonstrated that its decision is on the face of it arbitrary or illegal or contrary to the Act, the court will not interfere. Fixing a tariff and providing for cross-subsidy is essentially a matter of policy and normally a court would refrain from interfering with a policy decision unless the power exercised is arbitrary or ex facie bad in law."

xxx xxx xxx

123. Recently, the Constitution Bench of this Court in the case of Vivek Narayan Sharma v. Union of India [2023 SCC OnLine SC 1] has held that the Courts should be slow in interfering with the decisions taken by the experts in the field and unless it is found that the expert bodies have failed to take into consideration the mandatory statutory provisions or the decisions taken are based on extraneous considerations or they are ex facie arbitrary and illegal, it will not be appropriate for this Court to substitute its views with that of the expert bodies."

130. As is indicated in the aforesaid judgments, this Court should be slow in interfering with the concurrent findings of fact unless they are found to be perverse, arbitrary and either in ignorance of or contrary to the statutory provisions.

[Emphasis supplied]

// 18 //

22. By applying the principles enunciated and laid down in aMSEDCL (supra), it is held that this Court has to be slow in interfering with the findings given by an expert body like Ombudsman-II, OERC. As has been held in Association of Industrial Electricity users v. State of A.P. b(2002) 3 SCC 711, all that this Court has to be satisfied is that the Ombudsman has followed the proper procedure and unless it can be demonstrated that the decision on the face of it is arbitrary or illegal or contrary to the Act, this Court would not interfere.

23. Following the principle laid down in the decision rendered by the Constitution Bench of the Hon'ble Supreme Court in Vivek Narayan Sharma v. Union of India; 2023 SCC Online SC 1, it is held that this Court should be slow in interfering the decision taken by expert in the field, i.e., Ombudsman, OERC and it would not interfere unless it is found that the expert body has failed to take into consideration the mandatory statutory provision or the decisions taken is, based on extraneous considerations or it is ex-facie arbitrary and illegal. It would not be appropriate for this Court to substitute its views with that of the expert body.

_________________

a.MSEDCL V. APML & Others : 2023 SCC Online 233

b[Assn. of Industrial Electricity Users v. State of A.P., (2002)

3 SCC 711]

// 19 //

24. Applying these principles to the present case, it has to be held that the petitioner has failed to bring to the notice of this Court that any of the mandatory statutory provisions have not been considered by the Ombudsman. The petitioner has also failed to show that the decision of the Ombudsman is based on extraneous consideration. To reiterate the principles laid down in Vivek Narayan Sharma (supra), this Court should slow in interfering with the findings of the fact unless they are found to be perverse, arbitrary and in ignorance of contrary to the statutory provisions.

As discussed above, the petitioner distribution licensee has failed in its efforts to make out any case before this Court to interfere with the order passed by the Ombudsman.

25. In view of the above, the writ petition is dismissed being devoid of any merit. Interim order dated 23.04.2018 passed by this Court has not been extended beyond 25.6.2019. In dismissal of the writ petition interim order also stands vacated. The order passed by the Ombudsman be complied with forthwith.

In the facts and circumstances of the case, there shall be no order as to costs.

........................... ........................

Biswanath Rath, J.                                     M.S.Sahoo, J.



Orissa High Court, Cuttack     AJIT  Digitally signed
                                     by AJIT KUMAR
The 10th May, 2023/dutta
                               KUMAR DUTTA
                                     Date: 2023.05.11

 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter