Citation : 2023 Latest Caselaw 4183 Ori
Judgement Date : 24 April, 2023
IN THE HIGH COURT OF ORISSA AT CUTTACK
WP(C) No.11339 of 2016
Hindustan Petroleum Corporation .... Petitioner
Limited
-versus-
Presiding Officer, Labour Court, .... Opposite Parties
Odisha, Bhubaneswar and others
Advocates appeared in this case :
For Petitioner : Mr. Narendra Kishore Mishra,
Senior Advocate with
Mr. Nitish Kumar Mishra, Advocate
For Opposite Party No.1 : Mr. A.K. Sharma, Advocate,
(Additional Government Advocate)
For Opposite Party Nos.2 to 7: Mr. A.N. Das, Advocate
CORAM:
JUSTICE ARINDAM SINHA
JUSTICE SANJAY KUMAR MISHRA
---------------------------------------------------------------------------------------
Dates of hearing: 27.02.2023, 13.03.2023 and 24.04.2023
Date of Judgment: 24.04.2023
---------------------------------------------------------------------------------------
ARINDAM SINHA, J.
1. Mr. Mishra, learned senior advocate appears on behalf of
petitioner (management). He submits, there has since been set up
Central Government Industrial Tribunal-cum-Labour Court (CGIT) at
Bhubaneswar. He submits, the industrial dispute is between the oil
company and, inter alia, its contractor. Therefore, appropriate
government as per section 2 in Industrial Disputes Act, 1947 is the
Central Government. Hence, upon setting up of the Tribunal, the
Labour Court lost its jurisdiction to deal with the industrial dispute
and any miscellaneous case arising or connected therewith. On query
from Court he submits, section 7 provides for constitution of Labour
Courts by the appropriate government.
2. He files a brief of documents with copies to Mr. Das, learned
advocate appearing on behalf of the workman and Mr. Sharma,
learned advocate, Additional Government Advocate appearing on
behalf of opposite party no.1. The documents include, inter alia, order
dated 15th December, 2000, text of which is reproduced below.
"Consequent upon the setting up of a Central Government Industrial Tribunal-cum-Labour Court in Bhubaneswar under section 7 to the Industrial Disputes Act, 1947, all the central sphere cases numbering 302+90 pending in the State Industrial Tribunal of Bhubaneswar and Rourkela respectively as per the list furnished by these Tribunals may be
transferred for adjudication to the CGIT-cum- Labour Court, Bhubaneswar under section 33-B of Industrial Disputes Act, 1947."
On query from Court, Mr. Mishra submits, the I.D. case was not
transferred pursuant to above order because before that, award dated
1st December, 2000 had been made and published, under challenge by
his client in OJC no.1883 of 2001.
3. He submits, the Misc. Case under section 33-C(2) could not
have been filed in year 2012 before the Labour Court. As such, his
client made application challenging maintainability of the proceeding
in said Court, on constitution of the CGIT at Bhubaneswar. The
application is annexure-3, while impugned order dated 21st
November, 2014 made by the Labour Court, rejecting it, is
annexure-4.
4. Mr. Das submits, award dated 1st December, 2000 was
challenged by the management, in this Court. Interim order dated 22nd
February, 2001 was made staying the award. His client filed Misc.
Case under section 17-B. The interim order then stood vacated on 11th
August, 2011 and impugned order came to be passed, under section
33-C(2). He adds, there be direction for the Misc. Case to be
transferred to the CGIT. Mr. Mishra replies, in that event it be made
clear that the Misc. Case be proceeded with by the transferee Court on
and from the position, restored by setting aside impugned order.
5. Perused the order sheet. Petitioner (management) had
obtained interim order on 21st July, 2016, having moved the writ
petition presented earlier on 1st July, 2016 against order dated 21st
November, 2014. By interim order dated 21st July, 2016, there was
direction that in case petitioner files application before the Labour
Court in the Misc. Case seeking adjournment, in such event the Court
below shall stay further proceeding till 23rd August, 2016. The interim
order was continued from time to time and lastly by order dated 16th
February, 2017, made by coordinate Bench. Thereby it was to
continue till the next listing. Order sheet bears subsequent order dated
12th May, 2017, which did not continue the interim order. We, by our
order dated 27th February, 2023 continued the interim order till next
date of hearing on the management having filed interim application
being I.A. No.15594 of 2022.
6. Clearly, the industrial dispute case, culminating in said award
dated 1st December, 2000, was not counted for transfer by aforesaid
order dated 15th December, 2000. It was not one of the 302 cases
directed to be transferred thereby to the CGIT, simply because the
reference stood concluded earlier on 1st December, 2000. In the writ
petition challenging said award, interim order of stay stood vacated
on 11th August, 2011. Opposite party (workman) thereafter
approached the Labour Court under section 33-C(2). On query from
Court, we have ascertained that petitioner (management) was
represented in the Labour Court. We have already pointed out, there
was delay of almost two years, in presenting this writ petition,
challenging impugned order. Furthermore, there were gaps when the
interim order, obtained herein, was not operating. In the
circumstances the Labour Court proceeded with the Misc. Case, as is
submission on behalf of both, petitioner (management) as well as the
workman.
7. Sections 38 to 42 in Code of Civil Procedure, 1908 provide
for execution of decree by the Court, which passed it, the transferee
Court and their respective powers. The workman had filed the Misc.
Case for computation of the relief flowing out of the award, available
to him as entitled thereunder. It is in the nature of execution of the
award. The Code says a decree may be executed either by the Court,
which passed it or by the Court, to which it is sent for execution and
the transferee Court will have the same power as the original Court.
In this case, regarding the transfer, no order has been passed under
section 33-B. In the circumstances, by reason of parties having
participated in the Misc. Case and the Labour Court as may have
proceed therewith, in the time interim order was not obtained and
thereafter had not been extended, having power to do so, we direct
transfer of the Misc. Case to the CGIT, for the case to be proceeded
with prospectively. The record in ID Misc. Case no.61 of 2012 be
transmitted forthwith from Labour Court, Bhubaneswar to the CGIT,
for the Tribunal to proceed from the stage, up to which the case stands
dealt with by the Labour Court. Our direction for transfer is made
under section 24 in the Code. That it can be made may be seen from
order dated 25th January, 2022 in WP(C) no.2840 of 2002 (Prafulla
Chandra Pradhan v. The Presiding Officer, Industrial Tribunal
and another).
8. The transferee Court will expeditiously deal with the Misc.
Case, preferably within three months from date. The Registry is to
communicate this order to the Labour Court, Bhubaneswar for
immediate transmission of the record in ID Misc. Case no.61 of 2012
to the Central Government Industrial Tribunal-cum-Labour Court,
Bhubaneswar. On transfer the case be registered on re-number and
proceeded with as directed.
9. The writ petition is disposed of.
( Arindam Sinha ) Judge
( S. K. Mishra ) Judge
P. Pradhan
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!