Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

(Through Hybrid Mode) vs Shri R. K. Goyal
2022 Latest Caselaw 3536 Ori

Citation : 2022 Latest Caselaw 3536 Ori
Judgement Date : 28 July, 2022

Orissa High Court
(Through Hybrid Mode) vs Shri R. K. Goyal on 28 July, 2022
                 IN THE HIGH COURT OF ORISSA AT CUTTACK
                                   ARBA No.06 of 2003
                                 (Through Hybrid mode)
            State of Orissa                          ...                    Appellant
                                                            Mr. S. N. Das, Advocate
                                                           (Addl. Standing Counsel)
                                             -versus-

            Shri R. K. Goyal                         ...                 Respondents

                                                         Mr. A. Sanganeria, Advocate

                        CORAM: JUSTICE ARINDAM SINHA
                                        ORDER
Order No.                              28.07.2022

  25.       1.      State is appellant. It is aggrieved by judgment dated 7th

September, 2001. The Court below said that award dated 15th April,

1998 had been received from the Tribunal to be made rule of Court. As

against such award, State initiated misc. case under sections 30 and 33

of Arbitration Act, 1940, to set it aside.

2. Mr. Das, learned advocate, Addl. Standing Counsel appears on

behalf of appellant and submits, the award is on majority view taken by

two out of three members in the Tribunal. By the view, the Tribunal

misconducted itself and the proceeding, in awarding claim for

escalation. Challenge in the appeal is confined to that claim. He draws

// 2 //

attention to majority view taken on claim item no.30 in the reference. It

is reproduced below.

"The claimant claims Rs.14,18,041.75/- towards the statutory rise in prices by 30% due to change of Schedule of Rates in 1972 and 1975. The Respondent denies that the claimant quoted his rates for this work on 15.04.72 at the 1964 Schedule of rate and as he has signed the agreement in July, 1972 and the 1972 Schedule of Rates came into force with effect from 1.1.1972. In our considered opinion, in view of existence of Fair Wage clause in the Agreement and time was not the essence of the contract and the delay in execution of the work was due to the fault of the Respondent and the agreement having been signed on 29.8.1972 and the 1972 Schedule of Rate having come into force on 10.11.1972 (not on 1.1.1972) and the 1975 Schedule of Rate having come into force on 20.1.1975, the claim of statutory rise 20% excess appears to be reasonable in view of the compulsive rise in prices as has been held in the case of State of Orissa Vs. Birat Chandra Dagara reported in AIR 1977 Orissa 142, on the value of work executed on or after 10.11.72 from the 2nd R/A bill dt. 22.11.72 upto the final bill dt.23.7.76 i.e. on Rs.24,82,022/- which comes to Rs.4,96,404/-."

// 3 //

3. According to Mr. Das, the minority view is the view that ought

to have been view of the Tribunal. Said view is a well reasoned one,

which does not reveal misconduct. He places the view on said claim.

He submits, the contractor had upon earlier quoting higher rates, agreed

to the 1964 schedule of rates. The view says that claim of price

escalation is of reimbursement in nature and claimant had to furnish

documents of actually incurring expenditure co-relating to the

agreement rate, so as to claim extra payment. Material was supplied by

the department and cost recovered at agreed scheduled rates. No

documents like purchase voucher, cash memo or other similar types of

receipts were produced by claimant towards price rise on materials. So

also, similar omission in case of transportation higher charges bill.

There is observation in the view that there had been no statutory rise in

wage rates under provisions of Minimum Wages Act. So also there had

not been statutory rise in rates of materials or transportation charges

during the period of execution. He submits, this view is the correct

view and reiterates, the majority view prevailing was misconduct on

part of the Tribunal.

4. Mr. Sanganeria, learned advocate appears on behalf of the

contractor and relies on two judgments of the Supreme Court. They are

// 4 //

firstly, Tarapore & Co. v. State of M.P., reported in 1994 (1)

Arbitration Law Reporter 341 (SC), paragraphs 26 and 27. Secondly,

on K. N. Sathyapalan (Dead) by Lrs. vs. State of Kerala, reported in

2006 (4) Arbitration Law Reporter 275 (SC), paragraphs 36 and 37.

5. The award is based on reasons given both by majority as well

as minority views. By impugned judgment the majority view was

upheld. It is to be seen whether, State's contention on the majority view

versus the minority view can lead to conclusion of misconduct on

former view being effective view of the Tribunal.

6. It will appear from above extract of majority view that basis of

awarding the escalation was coming into effect of 1972 scheduled

rates. By the view, value of work executed on or after 10th November,

1972, from 2nd R/A bill dated 22nd November, 1972 up to final bill

dated 23rd July, 1976, was awarded at Rs.4,96,404/-. The basis of the

award was that the claim of statutory rise of 20% excess appeared, to

the two members, to be reasonable in view of the compulsive rising

prices and as had been held in State of Orissa vs. Birat Chandra

Dagara, reported in AIR 1977 Orissa 142.

// 5 //

7. The minority view expressed, inter alia, that escalation is

essentially a claim for reimbursement on price rise. In Tarapore and

Company (supra) the Supreme Court said by relied upon paragraphs

26 and 27, that it has to be seen whether there was an implied contract

to reimburse the increased wages as per the rates fixed under the

Minimum Wages Act, being statutory obligation and the terms of

contract being silent about payment of minimum wages. Facts in that

case were that wages were being increased from time to time, as would

appear from the decisions of the Wage Committee referred therein and

if appellant (before the Supreme Court) was being required to pay

wages as per those decisions, the Court read meeting of minds in so far

as claim of escalated payment on account of increase of fair wages is

concerned. The Court said, it has to be assumed that when appellant

was required to pay fair wages at increased rates, the authorities did

visualize that appellant would not do so by cutting down his profit.

Thus, the minority view on escalation being reimbursement and

necessity of proof of having incurred higher expenditure, finds support

from said judgment.

8. In K. N. Sathyapalan (supra) the Supreme Court found, it was

quite apparent appellant (before the Supreme Court) was prevented by

// 6 //

unforeseen circumstances from completing work within stipulated

period of eleven months and that such delay could have been prevented

had the State Government sought to maintain law and order to not

allow the problem created at work site. It was further clear that rubble

and metal, which should have been available at the departmental quarry

had to be obtained from quarries situated at double the distance and

even more, resulting in doubling of transportation charges. Even space

for dumping excess earth was not provide by the employer, which

compelled dumping at a place far away from work site entailing extra

cost for the same. Those facts were there in that case and the Supreme

Court held, in the circumstances, the arbitrator appeared to have acted

within his jurisdiction in allowing some of the claims on account of

escalation of costs, which were referable to the execution of the work

during the extended period.

9. On pain of repetition, majority view in the impugned award

does not refer to substantiation of any fact requiring reimbursement on

account of escalation. Court finds, the Tribunal misconducted itself in

awarding escalation without obtaining satisfaction for basis of the

award, the law being settled that escalation is a claim for

reimbursement on higher costs incurred. There does not appear to be

// 7 //

any dispute that materials were supplied by the department at agreed

scheduled rates and there was no evidence, documentary or otherwise

regarding incurring of higher costs on account of wages or

transportation.

10. Award on claim no.30 is set aside in appeal. The decree be

drawn-up accordingly.

11. The appeal is disposed of.

(Arindam Sinha) Judge Prasant

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter