Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Odisha Mining Corporation Ltd vs Sri D.K. Nayak
2022 Latest Caselaw 3627 Ori

Citation : 2022 Latest Caselaw 3627 Ori
Judgement Date : 1 August, 2022

Orissa High Court
Odisha Mining Corporation Ltd vs Sri D.K. Nayak on 1 August, 2022
                 IN THE HIGH COURT OF ORISSA AT CUTTACK

                              ARBA No.31 of 2018
                             (Through hybrid mode)

            Odisha Mining Corporation Ltd.          ....           Appellant

                                                   Mr. A.R. Dash, Advocate
                                                  Mr. A. Mahanta, Advocate

                                       -versus-

            Sri D.K. Nayak                          ....         Respondent
                                                  Mr. U.K. Samal, Advocate


                     CORAM: JUSTICE ARINDAM SINHA
                                      ORDER

01.08.2022 Order No.

8. 1. Mr. Mahanta, learned advocate led by Mr. A.R. Dash,

learned advocate appears on behalf of appellant. Mr. Mahanta

submits, impugned is judgment dated 15th December, 2017

made by the Court below upholding award dated 18th July,

2016 in favour of respondent contractor. He refers to agreement

dated 3rd June, 2011 between his client and respondent, clause-

52 and several sub-clauses thereunder. Nature and scope of

work provided, he submits, was for the agency to transport 3

lakh cubic meter of low grade dump located near Jagar Quarry

and feed to the installed screen and crusher plant having

average hauling distance of 1.5 kms., to produce fines. The

// 2 //

spurious materials were to be segregated. The fines were to be

shifted to Central Stock Yard, while the spurious materials to

the designated dump. In breach of this condition, being an

essential condition, respondent set up the screening and crusher

plant at zero distance from Jagar Quarry. By reason of this

breach, running bills of respondent were held up on settlement.

Mr. Mahanta relies on section 54 in Contract Act, 1872 to

submit respondent not having fulfilled its obligation under the

contract, was not entitled to payment. Respondent thereafter

shifted screening operation as required but soon after

abandoned the work. In the circumstances, claims of

respondent in the reference, should not have been allowed. The

award was in violation of mandatory provisions in sub-section

(3) of section 28, Arbitration and Conciliation Act, 1996 in not

taking into account terms of the contract applicable to the

transaction. On query from Court Mr. Mahanta submits, there is

no provision in the agreement requiring his client to identify the

spot, where the screen and crusher plant was to be set up.

2. Drawing attention to clause 71 of the contract Mr.

Mahanta submits, inter alia, termination of contract was

provided, thereby. The contractor abruptly abandoned the work.

// 3 //

3. Mr. Samal, learned advocate appears on behalf of

respondent contractor. He submits, screen and crusher plant

was set up at the place indicated by appellant through its

Manager (Mining) as per clause-13 of the agreement. This is

because forest clearance by appellant had not been had on any

site in its leasehold to, be used to set up the plant. Later, on

requirement upon clearance had, the plant was shifted. His

client then was told to stop production by letter dated 17th

December, 2011, of the Regional Manager, tendered as Ext.22

in the reference.

4. Court had made query of appellant regarding whether it

was relying on the average hauling distance requirement under

nature and scope of work, provided for in clause-52 as an

essential term. Nothing could be demonstrated for finding that

it was. Clause 52.2(a) simply talks about average distance as

shown in anneuxre-1 to the agreement. Annexure-1 gives

information sheet of Gandhamardan Iron Ore Mines. Relevant

information regarding average hauling distances are extracted

and reproduced below.

"INFORMATION SHEET OF GANDHAMARDAN IRON ORE MINES

1. Weighted average distances:

a)      Low grade dump to screen & crusher plant- 1.5 KM
b)      Screen & crusher plant to stock yard via W/B-1.0 KM


                                 // 4 //




c)      Screen & crusher plant to OB dump-               1.5 KM
d)      Dump No.II to Dump No.I-                         1.0 KM"

5. On further query from Court, necessity on average

hauling distance could not be demonstrated on behalf of

appellant, considering also that admittedly the screen and

crusher plant was set up at zero distance of the acquiring site,

the fines segregated from spurious materials and hauled to

Central Stock Yard by respondent. In the circumstances, the

indication by information of hauling distances cannot be found

to be an essential term of the contract, to hold breach thereof by

respondent. It also appears that initially the screen and crusher

plant was set up at a place indicated by appellant itself.

6. The other contention is regarding abandonment of work

to be seen as wrongful termination of the contract by

respondent. On perusal of clause 71 providing for, inter alia,

termination it is found that in event of completion or

termination, respondent was obliged to do certain things like

clearing out the site. On default, the clause provided for

appellant to have done so at expense of the contractor. On

query from Court response was, no counter claim was filed in

the reference by appellant.

// 5 //

7. Perused impugned judgment. There is no reason to

interfere. It is confirmed.

8. The appeal is disposed of.

(Arindam Sinha) Judge

Sks

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter