Citation : 2022 Latest Caselaw 2105 Ori
Judgement Date : 5 April, 2022
IN THE HIGH COURT OF ORISSA AT CUTTACK
ARBA No.22 Of 2008
(Through hybrid mode)
Dhiren Kumar Singh .... Appellant
Mr. J. K. Mohapatra, Advocate
-versus-
Chief Engineer (Con.II), East .... Respondents
Coast Railway and another
Mr. Debasis Tripathy, CGC
CORAM: JUSTICE ARINDAM SINHA
ORDER
05.04.2022
Order No.
20. 1. Mr. Mohapatra, learned advocate appears on behalf of
appellant and submits, impugned is judgment dated 11th July, 2008, by
which his client's challenge to award dated 7th December, 2006, was
dismissed.
2. He draws attention to the award. It records that seven
extensions were granted for completion of the work. Respondent
agreed that there was delay in handing over the site but disputed claim
for mobilization and idling. Final bill was submitted, settled and paid
on appellant having issued 'no claim' certificate. His client had
pleaded in the tribunal that the 'no claim' certificate was got signed by
// 2 //
duress and coercion. Though the tribunal did not act upon such plea
but still it went wrong in saying that 'no claim' certificate
contemplated under clause 43(2) of General Conditions of Contract
(GCC) was excepted matter under clause 63. He demonstrates from
clause 63 that it does not mention clause 43(2) as a clause providing
for an excepted matter. The other claims for idling and price
adjustment on a work period of 10 months being extended to 38
months were also not considered by the tribunal. In the circumstance,
good grounds to show perversity and patent illegality on face of the
award had been made out in the challenge, erroneously not appreciated
by the Court below.
3. Mr. Tripathy, learned advocate appears on behalf of respondent
and submits, impugned judgment is a good judgment. There should
not be interference in appeal. He submits, when appellant had accepted
payment on final bill with issuance of 'no claim' certificate, no further
claim can survive, as could be made. He relies on paragraph 14 of the
counter.
4. Perused impugned judgment. The Court below found that
clause 43(2) was not covered as excepted matter under clause 63 in
GCC. Said Court however found that nevertheless, thereby clause
// 3 //
43(2) was not rendered redundant. Admitted fact was that appellant
had accepted the final bill after furnishing 'no claim' certificate. It
found that the wrong interpretation cannot be said to be perverse. Such
interpretation cannot go to mean that the arbitral award deals with a
dispute not contemplated by or not falling within terms of the
submission to arbitration or contains decision on a matter beyond the
scope of submission of arbitration.
5. On the other claims, the Court below appreciated reliance by
the tribunal on clause 43(1) and found that decision thereon could not
be interfered with on the challenge.
6. So far as the rejection of claims on mobilization, idling or price
adjustment are concerned, it appears that extensions of time were
granted. The running account bills/statements did not carry any claim
on account of mobilization or idling or price adjustment as
contemporaneously made in a period of work contemplated to be eight
months and extended to 38 months. This coupled with appellant
having furnished 'no claim' certificate persuaded the tribunal to reject
those claims and the Court below declined to interfere. Reasoning in
the award and by the lower Court on those claims do not bring out any
ground under section 34 in Arbitration and Conciliation Act, 1996, for
// 4 //
interference in appeal. That leaves the main point of challenge
regarding the misinterpretation made by the tribunal on clause 43(2)
being an expected matter under clause 63.
7. Reasoning of the Court below on perversity arising from the
misinterpretation, is to be accepted. This because clause 43(2) by itself
puts closure on working of the contract, on the contractor issuing 'no
claim' certificate. This clause was there in GCC, to notice of appellant
at the time of entering into the contract. The clause says as follows.
" 43 (2) Signing of "No-claim" Certificate. The Contractor shall not be entitled to make any claim whatsoever against the Railway under or by virtue of or arising out of this contract, nor shall the Railway entertain or consider any such claim, if made by the Contractor, after he shall have signed a "No Claim" certificate in favour of the Railway, in such form as shall be required by the Railway, after the works are finally measured up. The Contractor shall be debarred from disputing the correctness of the items covered by "No Claim certificate" or demanding a reference to arbitration in respect thereof. "
8. Above reproduced clause says, the contractor shall not be entitled to make any claim after he shall have signed a 'No Claim' certificate in favour of the railways, in such form as shall be required by the railway for the works finally measured up. This, appellant was aware of at the time he entered into the contract, completion of the working of which was delayed beyond extended period. Appellant issued the certificate and accepted the final bill amount, thereafter, to
// 5 //
allege duress and coercion. This clause 43(2) is a standalone clause, which made appellant aware at the time of tender that the contingency of requirement to sign such a certificate was likely to arise. Knowing that, when appellant issued the 'no claim' certificate even though he may have had a claim outstanding, in law he is seen to have waived it.
9. There is no reason to interfere. Impugned judgment is affirmed
in appeal.
10. The appeal is disposed of.
(Arindam Sinha) Judge Prasant
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!