Citation : 2023 Latest Caselaw 149 Mani
Judgement Date : 6 April, 2023
SHAMURAILATPAM Digitally signed by
SHAMURAILATPAM SUSHIL SHARMA
SUSHIL SHARMA Date: 2023.04.06 13:42:01 +05'30'
Page |1
IN THE HIGH COURT OF MANIPUR
AT IMPHAL
PIL No. 34 of 2022
Shri Potsangbam Jaminikanta Singh, aged about 42
years, S/o (late) P. Iboyaima Singh, by profession
Advocate, resident of Haobam Marak Nangom Leikai,
P.O. Imphal, P.S. Singjamei, Imphal West District,
Manpur-795001.
... Petitioner
-Versus-
1. The State of Manipur through the Chief Secretary,
Govt. of Manipur, Manipur Secretariat, Imphal West
- 795001.
2. The Principal Secretary/Commissioner/Secretary,
(Works), Govt. of Manipur, Manipur Secretariat,
Imphal West - 795001.
3. The Chief Engineer (Works), Govt. of Manipur,
Khoyathong, Imphal West, Manipur - 795001.
4. M/S Sri Avantika Contractor (I) Ltd. 610, Nilgiri Block,
Aditya Enclave, Ameerpet, Hyderabad - 38.
... Respondents
BEFORE HON'BLE THE ACTING CHIEF JUSTICE M.V. MURALIDARAN HON'BLE MR. JUSTICE A. GUNESHWAR SHARMA
For the Petitioner :: Mr. Th. Khagemba, Advocate
For the Respondents :: Mr. Lenin Hijam, AG Mr. Tayenjam Momo, Advocate
Date of Hearing and
PIL No. 34 of 2022 Page |2
reserving Judgment & Order :: 29.03.2023
Date of Judgment & Order :: 04.04.2023
JUDGMENT AND ORDER (CAV) (M.V. Muralidaran, Acting CJ)
This public interest litigation has been filed by the
petitioner, who is a practising lawyer, seeking issuance of a writ
of mandamus directing the respondents to complete the
balance/remaining work for construction of Capital Complex
(Civil Secretariat Component) at Mantripukhri, Imphal, so that the
existing Manipur Secretariat may be shifted to the new building
and there is no traffic congestion.
2. The case of the petitioner is that in October, 2010,
the work for construction of Civil Secretariat was awarded to
M/s.Simplex Projects Limited and since M/s.Simplex Projects
Limited was not able to complete the construction work within the
stipulated time, the contract was terminated vide letter dated
2.11.2019. Thereafter, on 28.12.2019, the Public Works
Department issued a fresh Notice Inviting Tender (NIT) for the
Civil Secretariat work, which was also challenged by M/s.Simplex
Projects Limited and finally, this Court, vide judgment and order
dated 13.1.2021 in W.A.No.39 of 2020, directed the parties to
have a final joint measurement and after completion of the joint
PIL No. 34 of 2022 Page |3
measurement, liberty was given to the State to proceed with the
construction of the Civil Secretariat Complex by following the
required formalities and procedures as provided by law.
3. Further case of the petitioner is that as per the joint
measurement, the balance work estimation was determined and
NIT for the work "Construction of Capital Complex" at
Mantripukhri was invited on 19.2.2021 till 15.3.2021 in two-bid
system comprising of technical and financial bid. The fourth
respondent M/s.Sri Avantika Contractor (I) Limited emerged as
successful bidder and was awarded the work on 27.5.2021 within
a condition to complete the work within 12 months and the
contract agreement was also executed between the fourth
respondent and the State. The execution of the work was also
started by the said firm. However, the said balance work could
not be completed by the said firm within the stipulated period and
M/s.Sri Avantika Contractor (I) Limited requested for extension of
time and the deadline for completion of the said balance of work
was extended upto 30.9.2022. However, the work yet to be
completed without assigning any reason. The non-completion of
the said work till date is causing inconvenience to the general
public passing through the eastern side of the present Manipur
PIL No. 34 of 2022 Page |4
Secretariat. Hence, the petitioner has filed the present public
interest litigation.
4. The respondents 2 and 3 filed affidavit stating that
the present public interest litigation suffers from technical
defects, as no representation was made to the authorities
concerned for remedial actions before filing this petition by the
petitioner as per the High Court of Manipur Rules, 2019. Hence,
the motive of this petition is ill-conceive and liable to be
dismissed.
5. The fourth respondent filed affidavit stating that the
fourth respondent was aware of the issue of congestion faced in
the Highway adjacent to the existing Secretariat. Even though,
the traffic congestion may be attributed on various factors, the
fourth respondent believes that if the subject project is
completed, the traffic will be decongested from the Highway
adjacent to the existing Secretariat. It is stated that while the
fourth respondent had initiated works at the site, a number of
impediments, including restrictions due to Covid-19 pandemic,
curfews enforced by the Government, impeded the pace of the
project. Some part of the work was being done by certain
unauthorized contractors at the site and the fourth respondent
always kept the Public Works Department abreast of the situation
PIL No. 34 of 2022 Page |5
and sought appropriate measures to mitigate these impediments.
In the month of August, 2021, the fourth respondent procured all
requisite materials for the project as per the specifications and in
the process, certain deviations and extra items were noticed due
to change in the site conditions and they were also duly notified
to the PWD. Some of the deviations/extra items were approved
by the PWD only after a year. Despite the impediments, the
fourth Respondent was entrusted to work on the prestigious
project and also offered to conduct extra landscaping and
horticultural works at the site. The fourth respondent,
accordingly, carried out extra items.
6. It is stated that immense pressure was put on the
fourth respondent to complete the works earlier than the
stipulated time period, however, on the contrary the PWD would
never clear the payments to the fourth respondent on time nor
approve deviations, rate analysis etc. in a timely manner. After
the newly elected State Government came in, there was an
added pressure on the fourth respondent to finish the project
prior in time for inauguration. However, even then, the PWD did
not take commensurate steps to facilitate such faster rate of work
by the fourth respondent. Clause 7 of the General Conditions of
the contract applicable in the present case stipulates that
PIL No. 34 of 2022 Page |6
payments shall be made within 45 days of presentation of the bill,
failing which simple interest at the rate of 5% shall accrue on
such bills.
7. It is further stated in the affidavit that the fourth
respondent is diligently carrying on the works at the site and
about 95% of the works at the site are complete. Despite
completion of 95% work, out of the total bill of Rs.100.78 crore
submitted by the fourth respondent, the PWD has only paid a
sum of Rs.69.11 crore and currently, there is an outstanding of
Rs.31.67 crore due to the fourth respondent by the PWD. The
approval on a large number of deviation items sought by the
fourth respondent has not been considered by the PWD and
remains actionable at their end. Hence, there is a delay in
completing the subject project and the fourth respondent is no
way related to the said delay.
8. The learned counsel for the petitioner submitted
that the non-completion of the Civil Secretariat caused
inconvenience/grievances to the general public passing through
the eastern side of the present Manipur Secretariat, as both
halves of the National Highway in front of the Secretariat are
occupied by the parked vehicles of the officers/employees and
securities of VIPs, which has caused traffic congestion. Thus, a
PIL No. 34 of 2022 Page |7
prayer is made to direct the respondents to complete the balance
work within the time frame so that the present Manipur
Secretariat may be shifted to the new building at Mantripukhri.
9. The learned Additional Advocate General
appearing for the official respondents submitted that there is
technical defect in the public interest litigation, as there is no
representation made to the authorities concerned for remedial
actions before filing the public interest litigation. He would submit
that the vehicles parked on the National Highway-102 in front of
the Manipur Secretariat are managed by the Imphal Municipality
and action is being taken against the illegally parked vehicles on
the NH-102 under Sections 24 and 27 of the National Highways
(Land and Traffic) Act, 2002. Thus, a prayer has been made to
dismiss the present public interest litigation.
10. The learned counsel appearing for the fourth
respondent submitted that the fourth respondent is a contractor
entrusted with completion of the subject project and is aware of
the issue of congestion faced in the Highway adjacent to the
existing Secretariat. Even though, the traffic congestion
attributed on various factors, it verily believes that if the Civil
Secretariat work is completed, the traffic will be decongested
from the Highway adjacent to the existing Secretariat.
PIL No. 34 of 2022 Page |8
11. The learned counsel for the fourth respondent
would submit that it mobilized its team to the site by June, 2021.
However, it faced several difficulties upon visiting the site,
including security issues as number of unauthorized personnel
were gaining access to the site, handover of the drawings,
materials, etc. for commencement of the work. It had kept the
Public Works Department informed about all these impediments.
However, the Public Works Department has always reacted with
indifference or lethargy. After the initiation of works at the site, a
number of impediments, including restrictions due to Covid-19
pandemic, impeded the pace of the project. Further, the works
related to the CCTV surveillance was arbitrarily descoped,
causing opportunity loss and loss of profit to the fourth
respondent as the work amounting to Rs.42.43 crore was
descoped from the agreement.
12. The learned counsel for the fourth respondent next
submitted that the fourth respondent is diligently carrying on the
works at the site and about 95% of the works are completed and
out of the total bill of Rs.100.78 crore submitted by the fourth
respondent, the PWD has only settled Rs.69.11 crore and
currently, there is an outstanding of Rs.31.67 crore due to it by
the PWD. According to the fourth respondent, lack of timely
PIL No. 34 of 2022 Page |9
payments has seriously impeded its speed and affected the
timely delivery of the project and it will be in a position to ensure
completion of its contractual obligation within a period of three
months, only if the payments due to it are made within the time
and the rate of the deviations and extra items are approved by
the Department.
13. In reply, the learned Additional Advocate General,
by producing the present status of payment of bills settled to the
fourth respondent for the work "Construction of Capital Complex
(Civil Secretariat Component)", submitted that the fourth
respondent has submitted excessive bills beyond the value of the
work, which is payable as per agreement. The Executive
Engineer of Public Works Department returned the bills to make
corrections vide letters dated 27.1.2023 and 25.3.2023. The
probable liability amount of the fourth respondent may be
Rs.18.90 crore approximately.
14. The learned Additional Advocate General again by
referring to the present status of payment of bills submitted that
there is more to recover than to pay to the fourth respondent.
Therefore, the completion of the subject project is not related on
the payment to the fourth respondent.
PIL No. 34 of 2022 P a g e | 10
15. We have considered the rival submissions and also
perused materials available on record.
16. The grievance of the petitioner is that due to parking
of vehicles along both sides of the National Highway in front of
the Secretariat, there is traffic congestion, which is mainly for the
reason of non-completion of the construction work of Civil
Secretariat Component. Therefore, a direction may be issued to
the official respondents to complete the balance work of Capital
Complex (Civil Secretariat Component) at Mantripukhri, Imphal
within a time frame.
17. The official respondents contended that no
representation was submitted by the petitioner to the authorities
for remedial action before filing the public interest litigation and
on that sole ground, the present public interest litigation is liable
to be dismissed. Coming to the traffic congestion alleged by the
petitioner, it is the say of the official respondents that the vehicles
parked on the National Highway-102 in front of the Manipur
Secretariat are managed by the Imphal Municipality and action is
being taken against the vehicles parked illegally.
18. The non-submission of the representation to the
respondent authorities for remedial measures before filing the
PIL No. 34 of 2022 P a g e | 11
public interest litigation would not in any way technically affect
the present petition for the simple reason that the cause brought
to the notice of this Court by the petitioner by way of this public
interest litigation assumes larger public interest. There is no
quarrel that if anyone wants to take up the matter that demands
Government action, he has to first raise that issue with the
authorities, bring it to their knowledge and ask them how are they
going to solve it, for which he has to send a representation in the
first place to authorities. But in the case on hand, the situation is
traffic congestion within the heart of Imphal City, particularly,
eastern side of the present Manipur Secretariat along the
National Highway, which has been witnessed by the Government
officials, including the police personnel day in and day out. The
work contractor, namely the fourth respondent, also stated that if
the subject project is completed, the traffic will be decongested
form the Highway adjacent to the existing Secretariat. When
such being the statement of the fourth respondent and the traffic
congestion alleged by the petitioner in the present public interest
litigation is not vague, the non-submission of representation by
the petitioner to the respondent authorities for remedial
measures before filing the public interest litigation is not affected
the case of the petitioner.
PIL No. 34 of 2022 P a g e | 12
19. The Court has to be satisfied about (a) the
credentials of the applicant; (b) the prima facie correctness or
nature of information given by him; and (c) the information being
not vague and indefinite. The information should show gravity
and seriousness involved. The Court has to strike balance
between two conflicting interests - (i) nobody should be allowed
to indulge in wild and reckless allegations besmirching the
character of others; and (ii) avoidance of public mischief and to
avoid mischievous petitions seeking to assail, for oblique
motives, justifiable executive actions. In such case, however, the
Court cannot afford to be liberal. It has to be extremely careful to
see that under the guise of redressing a public grievance, it does
not encroach upon the sphere reserved by the Constitution to the
Executive and the Legislature. The Court has to act ruthlessly
while dealing with imposters and busy bodies or meddlesome
interlopers impersonating as public spirited holy men. They
masquerade as crusaders of justice. They pretend to act in the
name of Pro Bono Publico, though they have no interest of the
public or even of their own to protect.
20. Public interest litigation was intended to mean
nothing more than what words themselves said, namely "litigation
in the interest of the public".
PIL No. 34 of 2022 P a g e | 13
21. It is settled law that a writ petitioner who comes to
the Court for relief in public interest must come not only with clean
hands like any other writ petitioner but also with a clean heart,
clean mind and clean objective.
22. In the instant case, the petitioner has approached
this Court with clean hands and for larger public interest. Since
we are satisfied with the credentials of the petitioner, prima facie
correctness of the information given by him and also the
information given by the petitioner being not vague, the present
public interest litigation at the hands of the petitioner is a bona
fide one.
23. It is the admitted case of both sides that the delay
in completion of the Civil Secretariat work has caused traffic
congestion on the Highway adjacent to the existing Secretariat
as both halves of the National Highway in front of the Secretariat
are occupied by the parked vehicles of the officers/employees
and securities of VIPs. The said traffic congestion has led to
inconvenience to the public passing through the eastern side of
the present Secretariat.
24. Though the Civil Secretariat work was started in the
year 2010 and even after about 13 years, the same has not been
PIL No. 34 of 2022 P a g e | 14
completed and there appears to be a blame by the fourth
respondent contractor on the respondent officials qua lack of
timely payment and delay by the Public Works Department in
approving the rates of the deviations and extra items. Though
the learned Additional Advocate General submitted that there is
more to recover than to pay to the fourth respondent and the
completion of the project is not related with the payment to the
fourth respondent, nothing has been produced to prove the
same, except the status of payment of bills, which is a self-styled
note prepared and signed by the Executive Engineer, Building
Division No.I, PWD, Manipur. On the basis of such self-styled
undated note, it cannot be contended that excess payments were
made to the fourth respondent. The State Government has to be
a role model in settling the contractor for the work done by them
and because of non-payment, the work cannot be delayed, as
the contractor has to pay salaries to its employees for their hard
work done and settle the material cost to the traders.
25. Considering the facts and circumstances of the
case and the larger public interest involved, the PIL No.34 of
2022 is disposed of with the following directions:
(i) The respondent State is directed to
decongest the traffic on the National
PIL No. 34 of 2022 P a g e | 15
Highway in front of the Old Manipur
Secretariat by making arrangements for
proper park of vehicles on both sides.
Further, the respondent State is directed
to strictly enforce the traffic rules to
ensure illegal parked vehicles are
booked.
(ii) The respondent State and the fourth
respondent are directed to comply with
their contractual obligations qua the
completion of construction of Civil
Secretariat work.
(iii) The respondent State is directed to pay
the Outstanding dues as per the RA Bills
raised by the respondent No. 4 and also
approve the rates of deviations and extra
items regarding the Civil Secretariat work
at earliest.
(iv) The respondent State and the fourth
respondent are directed to co-operate
and work in concert with each other to
ensure that the Civil Secretariat work is to
be completed within a period of three
PIL No. 34 of 2022 P a g e | 16
months from the date of receipt of a copy
of this order.
(v) There will be no order as to costs.
JUDGE ACTING CHIEF JUSTICE
FR/NFR
Sushil
PIL No. 34 of 2022
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!