Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Anant Mandgi vs Union Of India
2026 Latest Caselaw 802 Mad

Citation : 2026 Latest Caselaw 802 Mad
Judgement Date : 26 February, 2026

[Cites 22, Cited by 0]

Madras High Court

Anant Mandgi vs Union Of India on 26 February, 2026

Author: Krishnan Ramasamy
Bench: Krishnan Ramasamy
                                                                                         W.P.Nos.29753 & 29755 of 2019



                                   IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                         Reserved on                               26.11.2025
                                        Pronounced on                              26.02.2026


                                                                CORAM

                                  THE HON'BLE Mr. JUSTICE KRISHNAN RAMASAMY

                                            W.P.Nos.29753 & 29755 of 2019
                                     & W.M.P.Nos.29654, 29885, 29886, 29883 of 2019,
                                                 7600 & 7592 of 2025

                        Anant Mandgi
                                                                                ... Petitioner in both petitions
                                                                  Vs.

                        1.Union of India,
                        Ministry of Road Transport and Highways,
                        Rep by its Secretary,
                        No.1, Parliament Street,
                        New Delhi 110 001.

                        2.The Competent Authority,
                        Special District Revenue Officer (Land Acquisition),
                        National Highways-948A,
                        STRR(I/C), Hosur, Krishnagiri.

                        3.National Highways Authority,
                        Rep by its Regional Project Director,
                        Project Implementation Unit-Bengaluru (Expressway),
                        No.718 11th Cross, 20th Main,
                        Padmanabha Nagar, Bengaluru-580 070
                                                               ... Respondents in both petitions


                        1/42




https://www.mhc.tn.gov.in/judis                ( Uploaded on: 02/03/2026 04:03:51 pm )
                                                                                           W.P.Nos.29753 & 29755 of 2019




                        Common Prayer:
                                  Writ Petition filed under Article 226 of the Constitution of India
                        praying to issue a Writ of Certiorari,
                                  Calling for the records of the 2nd respondent dated 25.6.2019
                        bearing Reference No.26/2018/L3 and quash the same and thereby
                        forbear the respondents from further proceeding with the acquisition in
                        respect of the petitioner land situated in at Bairamangalam Village,
                        Denkanikottai Taluk, Krishnagiri District bearing Survey Nos.612/B,
                        612/C1, 824/B4, 824/B5 and 824/C
                                  To call for the records the Notification dated 8.3.2019 bearing
                        Reference S.O.1333 (E) passed by the 1st respondent under Section 3D
                        of the National Highways Act, 1956 and quash the same



                                        For Petitioner
                                        in both petitions      : Mr.S.R.Raghunathan,
                                                                 Asst. by Mr.Manjunath Karthikeyan,
                                                                 Ms.Pavithra Sundararajan,
                                                                 Ms.Archita Aneesh

                                        For Respondents
                                        in both petitions : Mr.R.Rajesh Vivekananthan,
                                                            Deputy Solicitor General of India
                                                            for R1 & 2
                                                            Ms.S.R.Sumathy for R3




                        2/42




https://www.mhc.tn.gov.in/judis                  ( Uploaded on: 02/03/2026 04:03:51 pm )
                                                                                           W.P.Nos.29753 & 29755 of 2019

                                                      COMMON ORDER

These writ petitions have been filed challenging the impugned

Notification dated 08.03.2019 issued by the 1st respondent and the

impugned order dated 25.06.2019 passed by the 2nd respondent.

2.Brief facts of the case:

2.1 In the case on hand, initially, a notification dated 12.07.2018

came to be issued by the 1st respondent for acquisition of subject lands, to

an extent of 25941 Hectares, which spread across 25 villages, for public

purpose, i.e., formation of the National Highway “NH 948A”. Out of the

said total extent, the petitioner's land is about 0.8195 Hectares.

Subsequently, the petitioner sent a letter dated 25.07.2018 to the 2 nd

respondent, whereby he requested for personal hearing and also

explained that there were no concrete alignment of proposed ring road

and the remaining portion of the land will become redundant after the

acquisition. Upon receipt of the said letter, the Surveyors had visited the

subject land.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

2.2 Thereafter, another letter dated 20.08.2018 was communicated

by the petitioner to the respondents 2 & 3, wherein it was stated that the

vacant lands towards edge of property could be used instead of

petitioner's land for the purpose of forming the proposed road. On

15.10.2018, the 2nd respondent issued notice to call upon the petitioner

for enquiry, which was scheduled to be held on 25.10.2018. Purusant to

the said notice, the petitioner had filed his objection dated 22.10.2018

before the 2nd & 3rd respondents and thereafter, attended the enquiry on

25.10.2018. However, according to the petitioner, the 2nd respondent had

rejected the petitioner's objection vide order dated 12.12.2018, without

any proper consideration. Against the said order, a writ petition in

WP.No.8186 of 2019 was filed by the petitioner, wherein, this Court, vide

order dated 20.03.2019, had stayed the operation of the proceedings of

Notification issued by the respondents. Thereafter, the said writ petition

was disposed of by this Court vide order dated 18.06.2019 with a

direction to conduct joint spot inspection and complete the proceedings.

2.3 During the pendency of the above writ petition, the 1 st

respondent issued the impugned Notification dated 08.03.2019 by

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

declaring that the subject land should be acquired. Aggrieved over the

said notice, one of the present writ petitions, i.e., WP.No.29755 of 2019

came to be filed by the petitioner.

2.4 Pursuant to the order passed in WP.No.8186 of 2019, the said

joint spot inspection was conducted on 22.06.2019. The petitioner's wife

and son had attended the joint spot inspection and filed the additional

objections before the 2nd respondent. However, the 2nd respondent had

rejected the additional objections vide impugned order dated 25.06.2019,

against which, the writ petition in WP.No.29753 of 2019 came to be filed

by the petitioner.

3. Petitioner's submission:

3.1 The learned counsel for the petitioner raised two grounds

against the respondents. The 1st ground is pertaining to non-obtaining of

Environment clearance prior to declaration under Section 3D of the

National Highways Act, 1956 (hereinafter called as "the Act"). The 2 nd

ground is pertaining to non-consideration of petitioner's objections.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

3.2 As far as the 1st ground is concerned, he would submit that in

the Clause 7(f) of Schedule to the Environment Impact Assessment

Notification dated 14.09.2016, it has been clearly stated that it is

mandatory to obtain environment clearance for all projects and activities

mentioned under Category A in the nature of expansion of National

Highways greater than 100 km. In such case, the declaration under

Section 3D of the Act, can be made only after obtaining the

environment/forest clearance. To substantiate his submission, he referred

to the judgement rendered by the Hon'ble Apex Court in Project Director

vs. P.V.Krishnamurthy reported in (2021) 3 SCC 572 (hereinafter

referred as “PV Krishnamurthy's case”).

3.3 Further, he would contend that in this case, the environment

clearance was not at all obtained by the respondents prior to the

Declaration made under Section 3D of the Act. The said aspect was also

admitted by the respondents vide the impugned order dated 25.06.2019,

wherein it has been clearly stated as follows:

"..........the process of Environment Clearance is in advance stage and final EIA report as part of the same will be submitted to MOEF&CC with incorporation of public hearing proceedings."

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

3.4 Hence, by referring the above, he would submit that no

environment clearance was obtained by the respondents prior to the

Declaration and thus, the respondents have erroneously implemented the

entire project, which is not sustainable in law.

3.5 As far as the 2nd ground is concerned, he would submit that in

this case, the petitioner made severe objections to the proposed

acquisition and the same were submitted before the respondents. In spite

of the same, while passing the impugned order dated 25.06.2019, the

respondents had wrongly recorded that the petitioners are not having any

objections to the present alignment. When such being the case, it is clear

that the respondents had not at all considered the petitioner's objection in

a proper manner at the time of passing the impugned order, which is a

clear violation of principles of natural justice. Therefore, he requested

this Court to set aside the impugned 3D(1) Notification dated 08.03.2019

issued by the 1st respondent and the impugned order dated 25.06.2019

passed by the 2nd respondent.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

4. The respondent's reply:

4.1 Per contra, the learned counsel appearing for the respondents

would submit that the National Highways Authority of India (NHAI),

being a Statutory Authority, had proposed to acquire the lands comprising

25 villages at Krishnagiri District, which includes the subject land. In this

regard, a Notification under Section 3A(1) of the Act was published on

29.06.2018. Thereafter, a notice dated 15.10.2018 was issued, calling

upon the petitioner to attend the enquiry on 25.10.2018. Hence, he would

submit that the petitioner was provided with ample opportunities to make

objections regarding the acquisition of lands. In spite of the same, the

petitioner has made willful attempts to postpone the enquiry. Under these

circumstances, after due inspection, the order dated 07.12.2018 came to

be passed by the respondents. Subsequently, the Central Government

made a Declaration under Section 3D(1) of the Act vide Notification

dated 11.03.2019.

4.2 As far as the order dated 18.06.2019 passed by this Court in

W.P.No.8186 of 2019 is concerned, he would submit that pursuant to the

said order, a complete enquiry was conducted by the respondents and

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

after due consideration, a detailed speaking order came to be passed on

25.06.2019.

4.3 Further, he would submit that the petitioner's suggestion, with

regard to the utilisation of Government Poromboke Lands for the purpose

of forming Highway roads, was also examined by the Competent

Authority. However, during inspection, it was observed that any change

in alignment will affect the Geometry and it will have more social

impact, for which, NHAI will be constrained to acquire more patta lands.

Hence, the said suggestion was dropped by the Authority. Therefore, he

would submit that all the objections and suggestions made by the

petitioners were duly considered by the respondents at the time of

passing the impugned order.

4.4 He would also submit that the subject lands are inevitably

required for the purpose of forming National Highway. In such case, the

interest of general public will prevail over the interest of individual land

owner. That apart, as per the Doctrine of Eminent Domain, it is well

settled that when the Central Government acquires a private land for

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

bonafide public purpose, the Article 14 and 21 of the Constitution of

India will not be available against the said acquisition. When such being

the case, he would submit that there is no violation of fundamental rights

of the petitioner.

4.5 He would further contend that the petitioner's land is inevitably

required for formation of National Highway NH 948A. The total length

of the road is 35.766 km, out of which, the road passing through the

petitioner's land is only to the extent of 200 meter. Even the physical

construction of the road has been completed in 28.05 km, for which a

sum of Rs.709 Crore has been incurred till date. Due to the stay granted

in these petitions, the respondents are not in a position to complete the

remaining 0.2 km of road. When such being the case, if the proceedings,

pertaining to land acquisition, is quashed at this stage, it will lead to a

great Revenue loss to the Central Government. Hence, he prays for

dismissal of these petitions.

5. I have given due consideration to the submissions made by the

learned counsel for the petitioner and the learned Additional Solicitor

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

General appearing for the respondents and also perused the entire

materials available on record.

6. In the case on hand, two writ petitions were filed challenging the

issuance of notification dated 08.03.2019 and the passing of impugned

order dated 25.06.2019.

7. According to the petitioner, Section 3D(1) notification was

issued on 08.03.2019, which is consequent to the issuance of Section

3A(1) notice dated 12.07.2018. However, the respondents had failed to

obtain environment clearance prior to the issuance of aforesaid Section

3D(1) notification and the same is contrary to the law laid down by the

Hon'ble Apex Court in PV Krishnamurthy's case. Further, contention of

the petitioner was that the impugned order dated 25.06.2019 was passed

without considering the petitioner's objection, which is not only violation

of principles of natural justice but also in contrary to the order dated

18.06.2019 passed by this Court in WP.No.8186 of 2019.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

8. Now, the issues that arise for consideration in these writ

petitions are as follows:

i) Whether the order dated 25.06.2019 was passed by the 2nd respondent, after due consideration of the petitioner's submission/objection, as per the order of this Court dated 18.06.2019 in WP.No.8186 of 2019 ?

ii) Whether Section 3D(1) notification dated 08.03.2019, issued by the 1st respondent, without obtaining Environment Clearance, is against the law laid down by the Hon'ble Apex Court in PV Krishnamurthy's case ?

9. Issue No.1: Whether the order dated 25.06.2019 was passed by the 2nd respondent, after due consideration of the petitioner's submission/objection, as per the order of this Court dated 18.06.2019 in WP.No.8186 of 2019 ?

9.1 Initially, on 12.07.2018, a notification under Section 3A(1) was

issued by the 1st respondent for acquisition of land for public purpose,

which includes the petitioner's land. On 25.07.2018, a request was made

by the petitioner to the 2nd respondent for personal hearing opportunity.

Thereafter, on 11.08.2018, a surveyor, engaged by the respondent, had

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

visited the petitioner's land and conducted survey therein. On 18.10.2018,

another survey was conducted by Thasildhar and Revenue Inspector. On

15.10.2018, the 2nd respondent issued notice to the petitioner calling upon

him for enquiry, which was scheduled on 25.10.2018. In the meantime,

on 22.10.2018, the petitioner placed additional objection on record before

the file of respondents 2 and 3. On 25.10.2018, the petitioner attended the

enquiry before the 2nd respondent. However, the 2nd respondent had

postponed the enquiry without fixing any specific date of hearing. Under

these circumstances, all of a sudden, the order dated 12.12.2018 was

passed without hearing the petitioner's submission.

9.2 Aggrieved over the said order, the petitioner filed a writ

petition in WP.NO.8186 of 2019, wherein this Court vide order dated

18.06.2019, directed the respondent to conduct joint spot inspection on

22.06.2019 and thereafter complete the enquiry proceedings within a

period of 3 days. Subsequently, on 22.06.2019, the petitioners attended

the joint spot inspection and placed their objections on record. As

directed by this Court vide order dated 18.06.2019, subsequent to the

joint spot inspection, the 2nd respondent, after considering the said

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

objection and other representations filed by the petitioner, passed the

impugned order dated 25.06.2019.

9.3 Now, the grievance of the petitioner is with regard to the non-

consideration of objections filed by the petitioner at the time of passing

the impugned order dated 25.06.2019.

9.4 A perusal of the impugned order would show that the 2 nd

respondent had given sufficient opportunities to the petitioner to

participate in the proceedings and also duly conducted the joint spot

inspection, in which the petitioner had also participated. Thereafter, the

2nd respondent had passed a detailed order after duly considering the

petitioner's submission/objections. In such case, this Court does not find

any fault on the part of the respondent in passing the impugned order

dated 25.06.2019.

9.5 Further, this Court only finds fault on the petitioner, who failed

to avail the opportunities, which were provided to him by the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

respondents. As stated above, the respondents had duly complied with the

direction issued by this Court vide order dated 18.06.2019 passed in

WP.No.8186 of 2019. In such view of the matter, the writ petition in

WP.No.29753 of 2019, which is filed against the impugned order dated

25.06.2019, is liable to be dismissed. Accordingly, the 1 st issue is

answered.

10. Issue No.2: Whether Section 3D(1) notification dated 08.03.2019 issued by the respondents, without obtaining Environment Clearance is against the law laid down by the Hon'ble Apex Court in PV Krishnamurthy's case ?

10.1 As far as the 2nd issue is concerned, according to the

petitioner, in this case, Section 3D(1) notification was issued without

obtaining Environment Clearance, which is against the law laid down by

the Hon'ble Apex Court in PV Krishnamurthy case.

10.2 To answer this issue, it would be apposite to peruse the

judgement of the Hon'ble Supreme Court of India, rendered in PV

Krishnamurthy case, wherein, it had elaborately discussed on the aspect

of requirement of obtaining Environmental Clearance. In the said

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

judgement, it has been clearly stated that Environmental Clearance is

required to be obtained before the commencement of construction work

or preparation of land by project management for the purpose of

development, which would happen subsequent to the entrustment of

lands to NHAI. The relevant portion of the order reads as follows:

“79. Reverting to the notification issued by the MoEF dated 14.9.2006, even this notification does not constrict the power of Central Government to issue notification under Section 2(2) or Section 3A of the 1956 Act. There is nothing to suggest that before expressing intention to acquire any land for the purpose of the 1956 Act, prior environmental/forest clearance is required. The environmental/forest clearance, however, is, required to be obtained by the executing agency in terms of this notification “before commencing the actual work or executing the proposed work/project”. That would happen only after the land is vested in the NHAI or the NHAI was to be entrusted with the development work of concerned national highway by the Central Government in exercise of powers under Section 5 of the 1956 Act read with Section 11 of the 1988 Act. The land would vest in the Central Government under the 1956 Act only after publication of declaration of acquisition under Section 3D. And until then, the question of Central Government vesting it in favour of NHAI under Section 11 of the 1988 Act would not arise. However, until the vesting of the land, the Central Government and its authorised officer can undertake surveys of the notified lands by entering upon it in terms of Section 3B of the Act. Pertinently, the activities predicated in Section 3B are of exploration for verifying the feasibility and viability of land for construction of a national highway. These are onetime activities and not in

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

the nature of exploitation of the land for continuous commercial/industrial activities as such. There is remote possibility of irretrievable wide spread environmental impact due to carrying out activities referred to in Section 3B for assessing the worthiness of the land for using it as a national highway. Thus, the question of applying notification of 2006 at this stage does not arise, much less obligate the Central Government to follow directives thereunder.

80 to 85. ..............

86.Suffice it to observe that the subject notification of 2006 and Office Memorandum dated 7.10.2014 ordain that such permission is required to be obtained (only) before commencement of the work of the new project or activities or on the expansion or improvisation of the project or activities based on their potential environment impact.

87 to 92 ...........

93. For the purpose of considering the question posed before us, suffice it to observe that the prior environmental clearance in terms of 2006 notification issued under Section 3 of the Environment (Protection) Act, 1986 Act read with Rule 5 of the Environment (Protection) Rules, 1986, is required to be taken before commencement of the “actual construction or building work” of the national highway by the executing agency (NHAI). That will happen only after the acquisition proceedings are taken to its logical end until the land finally vests in the NHAI or is entrusted to it by the Central Government for building/management of the national highway.

94 to 96. ..........

97.Considering the provisions of the 1956 Act and the 1988 Act, NHAI can take over the work of development and maintenance of the concerned national

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

highway only if the notified land is vested in it or when the same is entrusted to it by the Central Government. ..................” (*** Emphasis supplied)

10.3 In all the above paragraphs, the Hon'ble Apex Court had dealt

with 2006 Notification, 1956 Act, 1998 Act and Environmental

Protection Act, 1984, and categorically held that the Environmental/

Forest Clearance is required to be obtained before commencing actual

work or executing of proposed work/project. Further, it has been held that

the said aspect would arise only subsequent to the entrustment of lands

with NHAI. Prior to entrustment of lands to NHAI, the lands are required

to be vested with the Central Government and that would happen by

issuance of Section 3D Notification. Merely, the issuance of Section 3D

Notification would not be considered as commencement of actual work

or execution of proposed work/project. Such commencement/execution

will happen only after the entrustment of lands by the Government to

NHAI.

10.4 In terms of the 1956 Act, once the land is vested with the

Government by virtue of issuance of Section 3D Notification, thereafter,

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

they have to take possession in terms of Section 3E of the 1956 Act. Such

possession can be taken only after the determination of compensation for

the land by the Competent Authority in terms of Section 3G of the 1956

Act and depositing the same in terms of Section 3H(1) of the 1956 Act.

Therefore, it is not that the physical possession of the land can be taken

by the Government immediately upon issuance of Section 3D

Notification. As stated above, such taking over of physical possession

will happen only after quantification of the compensation amount and

deposit of the same in accordance with the provisions of Section 3G and

3H of the 1956 Act. Hence, at any cost, one cannot construed that

immediately upon issuance of Section 3D Notification, the Government

can commence the construction work or execute the proposed

work/project automatically.

10.5 Therefore, the Hon'ble Apex Court was conscious of the fact

that the commencement of actual work or execution of proposed

work/project would happen in terms of 2006 Notification, only after

entrustment of land with NHAI. Thus, merely by virtue of issuance of

Section 3D Notification, the land will not be entrusted to NHAI but it

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

will only be vested with the Government. Merely, vesting of land with

the Government would not amount to automatic commencement of

construction work or execution of proposed work/project.

10.6 Therefore, the Hon'ble Apex Court, held in clear terms that

the commencement of actual work or execution of proposed work/project

will not happen, or cannot construed to be happened, immediately upon

issuance of Section 3D Notification. By virtue of Section 3D notification,

only the land is going to be vested with the Government. Except vesting

of land, nothing is going to happen with regard to commencement of any

construction works or development activities, which are all subsequent

events. As per the provisions of 2006 Notification, the bar is only for

commencement of construction work or execution of proposed

project/works, prior to the obtaining of Environmental Clearance and the

same would happen once the land is entrusted to NHAI. Therefore, a

mere issuance of Section 3D Notification itself cannot not be considered

or construed as commencement of construction work.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

10.7 Now, it would be apposite to extract the Office Memorandum

of the Ministry of Environment, Forests and Climate Change dated

07.10.2014 (2014 OM), which reads as follows:

Office Memorandum Subject: Status of land acquisition w.r.t. project site while considering the case for environment clearance under EIA Notification, 2006-regarding It has been brought to the notice of this Ministry that in the absence of a guidelines, different EACS/SEACs adopt different criteria about the extent to which the land w.r.t. the project site should be acquired before the consideration of the case for environment clearance (EC). Some of the Ministries in the Government of India and some industrial associations have represented that full acquisition or land for the project site should not he insisted upon before consideration of the case for EC and instead Initiarn of land acquisition process should be sufficient for the consideration of such cases. The argument being that land acquisition process can go on in parallel and that consideration of EC need not await full far acquisition.

2. The matter has been examined in the Ministry.

The EC granted for a project or activity under the EIA Notification: 2006, as amended, is site specific. While full acquisition of land may not be a pre-requisite for the consideration of the case for EC, there should be some credible document to show the status of land acquisition w.r.t project site when the case is brought before the concerned EAC/SEAC for appraisal. It has been accordingly decided that the following documents relating to acquisition of the project site may be

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

considered as adequate by EACS/SEACs at the time of appraisal of the case for EC.

(i) In case the land w.r.t. the project site is proposed to be acquired through Government intervention, a copy of preliminary notification issued by the concerned State Government regarding acquisition of land as per the provisions of Land Acquisition, Rehabilitation and Resettlement, Act, 2013.

(ii) In case the land is being acquired through private Showing the intent of the land owners to sell the land negotiations with the land owners, credible documer the proposed project.

3. It may, however, be noted that the EC granted for a project on the basis of aforesaid documents shall become invalid in case the actual land for the project site turns out to be different from the lang considered at the time of appraisal of project and mentioned in the EC.

4. This issues with the approval of the competent authority.”

10.8 Subsequent to the issuance of 2006 Notification, different

Environmental Authorities adopted different criteria with regard to which

extent of project site should be acquired before consideration of the case

for Environmental Clearance. The said aspect was brought to the

knowledge of Ministry of Environment, Forests and Climate Change and

hence, the aforesaid 2014 OM came to be issued.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

10.9 As discussed in paragraph Nos.1 & 2 of 2014 OM, after

examining all the aspects, the Authorities have categorically arrived at a

conclusion that while full acquisition of land may not be a pre-requisite

for the consideration of the case for EC, there should be some credible

document to show the status of land acquisition with respect to project

site when the case is brought before the concerned EAC/SEAC for

appraisal. Therefore, insisting of the acquisition of land in full extent by

the concerned Authorities has been relaxed by virtue of the aforesaid OM

to the extent to show some documents relating to acquisition of project

site. Thus, the acquisition of land in full extent at the time of preliminary

notice was relaxed to the aforesaid extent.

10.10 Further, at paragraph Nos.3 & 4 of 2014 OM, it was

concluded that the Environmental Clearance, granted based on the

aforesaid documents, would become invalid in case the actual land for

the project site turns out to be different from the land considered at the

time of appraisal of project and mentioned in the EC. When such being

the case, if the Environmental Clearance is granted after entrustment of

lands to NHAI, the question of carrying out the construction work and

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

commencement of project in any land, different from the actual project

site submitted before the Environmental Authorities for which the EC

was granted, would not arise and otherwise, entire exercise for getting

EC will become wasteful exercise and the respondent is required to

follow the entire exercise of land acquisition from the beginning.

10.11 At this juncture, it would be apposite to extract paragraph

No.95 of the PV Krishnamurthy case, wherein the Hon'ble Apex Court

had dealt with the aforesaid 2014 OM and it has been held as follows:

“95. Applying the tenet underlying this notification, it is amply clear that before the process of acquisition of land is ripe for declaration under Section 3D of the 1956 Act, it would be open to the executing agency (NHAI) to make an application to the competent authority for environmental clearance. That process can be commenced parallelly or alongside the acquisition process after a preliminary notification under Section 3A of the 1956 Act, for acquisition is issued. ”

10.12 In terms of the above paragraph No.95, the Hon'ble Apex

Court has held that NHAI shall make applications for Environmental

Clearance even before the issuance of Section 3D Notification. Further, it

was held that the process of obtaining Environmental Clearance can be

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

commenced parallelly or alongside the acquisition process after a

preliminary Notification, under Section 3A of the 1956 Act, for

acquisition.

10.13 Further, at paragraph Nos.100 & 102, in the case of PV

Krishnamurthy, the Hon'ble Apex Court had dealt with the aspect of

reverting back of the subject lands to the respective land owners and the

relevant portion reads as follows:

100. Reverting to the dictum of this Court in Karnataka Industrial Areas Development Board (supra), it must be understood to mean that the declaration under Section 3D regarding acquisition of notified land, be made only after environmental/forest clearance qua the specific land is granted. To put it differently, the necessity of prior environmental/forest clearance would arise only if finally, the land in question (site specific) is to be notified under Section 3D, as being acquired for the purposes of building, maintenance, management or operation of the national highway or part thereof. Such interpretation would further the cause and objective of environment and forest laws, as also not impede the timeline specified for building, maintenance, management or operation of the national highway or part thereof, which undeniably is a public purpose and of national importance. This would also assuage the concerns of the land owners that even if eventually no environment permission or forest clearance is accorded, the land cannot be reverted to the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

original owner as it had de jure vested in the Central Government upon issue of notification under Section 3D of the 1956 Act and no power is bestowed on the Central Government under this Act to withdraw from acquisition.

101. ........

102.The argument of the writ petitioners that the expression “shall” occurring in Section 3D(1) be interpreted as “may”, though attractive on the first blush, deserves to be rejected. If that interpretation is accepted, it would render the efficacy of Section 3D(3) of lapsing of the acquisition process otiose. It is a mandatory provision. Instead, we have acceded to the alternative argument to give expansive meaning to the proviso in Section 3D(3) of the 1956 Act by interpretative process, including by invoking plenary powers of this Court under Article 142 of the Constitution to hold that the dictum of this Court in Karnataka Industrial Areas Development Board (supra) be regarded as stay granted by the Court to all notifications issued under Section 3A of the 1956 Act until the grant or nongrant of permissions by the competent authorities under the environmental and forest laws, as the case may be, including until the stated permissions attain finality. In other words, time spent by the executing agency/Central Government in pursuing application before the concerned authorities for grant of permission/clearance under the stated laws need to be excluded because of stay by the Court of actions (limited to issue of notification under Section 3D), consequent to notification under Section 3A. Thus, the acquisition process set in motion upon issue of Section 3A notification can go on in parallel until the stage of publication of notification under Section 3D, which can be issued after grant of clearances/permissions by the competent authority under the environment/forest laws and attaining finality thereof. (*** Emphasis supplied)

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

10.14 In the above paragraphs, it has been stated that “after the

issuance of Section 3D Notification, even if no environment clearance is

accorded, the land cannot be reverted to the original owner since no

power is bestowed on the Central Government under the National

Highways Act to withdraw from acquisition”, which means, in terms of

the National Highways Act, if no clearance is obtained or even if any

conclusion arrived at to the extent that the subject lands will not be used

for the purpose of that Act, no provision is available for reverting back of

the land to the respective land owners. May be, by keeping the said

aspect in mind, the Hon'ble Apex Court has held at paragraph Nos.100 &

102 that Environmental Clearance has to be obtained prior to the issuance

of Section 3D Notification, in order to protect the interest of land owners.

10.15 As far as the observation made, at paragraph No.102 of PV

Krishnamurthy case, with regard to the receipt of Environmental

Clearance is concerned, it is not in consonance with the paragraph

Nos.79, 86, 93 & 97 of the very same judgement, 2006 Notification and

2014 OM, wherein it has been categorically held that the Environmental

Clearance is required to be obtained only prior to the commencement of

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

actual construction work or execution of proposed work, which would

occur only after the entrustment of land to NHAI and even after

entrustment, NHAI cannot commence the construction work or proposed

work until the receipt of Environmental Clearance. Therefore, this Court

is inclined to go with the findings of the Hon'ble Apex Court at paragraph

Nos.79, 86, 93 & 97, which is in consonance with 2006 Notification and

2014 OM.

10.16 As stated above, at paragraph No.79 of PV Krishnamurthy

case, the Hon'ble Apex Court held that the Environmental Clearance is

required to be obtained not prior to the issuance of Section 3D

Notification but before the commencement of any construction work at

the project site. Such commencement would occur only after the

entrustment of subject lands to NHAI. At the time of issuance of Section

3D Notification, the lands will only be vested with Government.

Therefore, it is crystal clear that Environmental clearances is not required

to be obtained before issuance of Section 3D Notification but prior to the

commencement of construction work by NHAI.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

10.17 To substantiate the above aspect, it would be apposite to,

once again, extract the relevant portion of paragraph No.79 of PV

Krishnamurthy case, wherein the procedures for land acquisition was

elaborately explained and it was categorically held that the

clearance/permission has to be obtained prior to the commencement of

construction work or implementation of the project, which would happen

only after the land is vested in the NHAI or the NHAI was to be entrusted

with the development work of concerned National Highway by the

Central Government. The relevant portion reads as follows:

“79. ...................The environmental/forest clearance, however, is, required to be obtained by the executing agency in terms of this notification “before commencing the actual work or executing the proposed work/project”. That would happen only after the land is vested in the NHAI or the NHAI was to be entrusted with the development work of concerned national highway by the Central Government in exercise of powers under Section 5 of the 1956 Act read with Section 11 of the 1988 Act. The land would vest in the Central Government under the 1956 Act only after publication of declaration of acquisition under Section 3D. And until then, the question of Central Government vesting it in favour of NHAI under Section 11 of the 1988 Act would not arise. However, until the vesting of the land, the Central Government and its authorised officer can undertake surveys of the notified lands by entering upon it

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

in terms of Section 3B of the Act. Pertinently, the activities predicated in Section 3B are of exploration for verifying the feasibility and viability of land for construction of a national highway. ................”

10.18 In the above paragraph, the Hon'ble Apex Court had clearly

explained the procedures involved in acquisition of land. Initially,

Section 3D Notification has to be issued, by virtue of which, the subject

lands have to be vested with Government. Thereafter, the said lands will

be entrusted to the concerned executing agency, after which, the NHAI

would commence the actual work or execution of proposed work/project.

Therefore, as per the ruling at paragraph No.79 of the PV

Krishnamurthy case, upon the issuance of Section 3D Notification, only

the lands will be vested with the Government and it will not amount to

entrustment of lands with NHAI. Only subsequent to the entrustment, the

NHAI would commence the construction of building and other

developmental activities, that too, after the receipt of Environmental

Clearance.

10.19 At this juncture, it would also pertinent to note that the issue

before the Hon'ble Apex Court was as to whether the Environmental

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

Clearance is required to be obtained prior to Section 3A Notification or

not. The said judgements was passed only on the aspect as to whether the

Environmental Clearance is required to be obtained before issuance of

Section 3A Notification or not. Ultimately, the Hon'ble Apex Court had

concluded that before issuance of Section 3A Notification, there is no

requirement for obtaining the Environmental Clearance and the same

shall be obtained prior to the commencement of construction work.

10.20 Therefore, at no stretch of imagination, one could construed

that immediately upon issuance of Section 3D notification, the

construction works or preparation of lands would commence. In terms of

the order passed by Hon'ble Apex Court at paragraph No.79 of PV

Krishnamurthy case, unless and otherwise the land is entrusted with

NHAI by the Central Government, the question of developmental

activities, as mentioned in 2006 Notification, would not arise and even

NHAI cannot commence the project prior to the obtaining of

Environmental Clearance.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

10.21 When such being the case, the view took by the Hon'ble

Apex Court by way of restrictions at paragraph No.102 of the PV

Krishnamurthy case, to the extent that Environmental Clearance is

required to be obtained prior to the issuance of Section 3D Notification,

is only to safeguard the interest of the land owners since there was no

provision for withdrawal of acquisition and reverting back the lands to

the original owners in terms of National Highways Act. Even if the

protection is not available for reverting the land back to the land owners,

and if the purpose, for which the lands were acquired, was not achieved,

certainly, the respective land owners are entitled to make an application

for returning the land, in which case, the respondent-Department is

bound to return the same.

10.22 Therefore, I am of the considered view that except securing

the land, all the other construction activities would happen only when the

property is entrusted by the Government with the NHAI. At the stage of

issuance of Section 3D Notification, only the property will be vested with

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

Government and the entrustment of the said property with the NHAI will

be subsequent event. Only after such entrustment, the commencement of

construction work or preparation of land for project/work would arise.

10.23 In view of the above, this Court has no hesitation to hold that

immediately upon issuance of Section 3D Notification, no

commencement of construction work or preparation of land by project

management would occur as held by the Hon'ble Apex Court in PV

Krishnamurthy case. Thus, there is no bar either under the Statute or by

the Apex Court Ruling in PV Krishnamurthy for obtaining

Environmental Clearance up to the stage of entrustment of land to NHAI

by the Government, but before the commencement of construction work

or preparation of land, the NHAI must obtain Environmental Clearance

Certificate.

10.24 When such being the case, there is no bar for the

respondents in issuing Section 3D Notification, prior to the receipt of

Environmental Clearance, since the such issuance of Section 3D

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

Notification would not amount to the commencement of construction

work or preparation of land by the project management. The said aspect

would happen only after the entrustment of land by the Government to

the NHAI. Even after such entrustment, the NHAI has to wait until the

approval of Environmental Clearance for commencement of construction

work or preparation of land in the project site. Accordingly, the 2 nd issue

is answered.

11. Other case laws referred by the petitioners:

11.1 Further, a reference was made to the judgment in

C.Kenchappa case, wherein at paragraph No.100, it has been stated as

follows:

“100. The importance and awareness of environment and ecology is becoming so vital and important that we, in our judgment, want the appellant to insist on the conditions emanating from the principle of `Sustainable Development'.

(1) We direct that, in future, before acquisition of lands for development, the consequence and adverse impact of development on environment must be properly comprehended and the lands be acquired for development that they do not gravely impair the ecology and environment.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

(2) We also direct the appellant to incorporate the condition of allotment to obtain clearance from the Karnataka State Pollution Control Board before the land is allotted for development. The said directory condition of allotment of lands be converted into a mandatory condition for all the projects to be sanctioned in future.”

11.2 A reading of above paragraph would makes it clear that a

direction was issued by the Hon'ble Apex Court to the extent that the

consequence and adverse impact of development on environment must be

properly comprehended and the lands acquired for development that they

do not gravely impair the ecology and environment.

11.3 Keeping the above order in mind, the Notification 2006 was

issued by stating that before starting the acquisition process, the

respondent had to conduct a thorough Environment Impact Study.

Accordingly, a study was conducted and after satisfaction of the

respondents only, they have proceeded to acquire land and set up the

project. Therefore, the direction issued by the Hon'ble Apex Court, vide

C.Kenjappa case, has been duly followed by the respondents in this case.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

11.4 Yet another reference was made to the order passed by the

Hon'ble Division Bench of this Court in M.Velu case and the relevant

portion of the said order reads as follows:

“45. Since the land acquisition proceeding is only in the preliminary stage now, we are of the view that before issuing the notification under Section 3(1) of the Act the authorities have to approach the statutory authority constituted under the environment (Protection) Act for environmental clearance. The report of the statutory authority must also be considered by the Government while dealing with the objections submitted by the land owners and the other interested persons, including the petitioner and the fifth respondent in pursuance of the notice issued under Section 3(2) of the Industrial Purposes Act.

DIRECTIONS:-

46. Therefore keeping in view the direction given by the Supreme Court in the Karnataka Industrial Areas Development Board case, (cited supra) we are inclined to issue the following directions:-

(1) The petitioner is granted liberty to make a comprehensive representation within fifteen days from the date of receipt of a copy of this order before the statutory authority constituted to hear objections relating to the land acquisition in question in pursuance to the notice issued under Section 3(2) of the Tamil Nadu Acquisition of Land for Industrial Purposes Act, 1997. Similar liberty is granted to the fifth respondent also.

(2) The statutory authority exercising powers under the Industrial Purposes Act, simultaneous with the process of hearing the objections from the land owners, petitioner, fifth respondent and other interested persons should

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

approach the State Level Environmental Impact Assessment Authority for prior environmental clearance before proceeding further in the matter of issuance of notice under Section 3(1) of the Act.

(3) In case the State Environmental Impact Assessment Authority gives clearance for the project in question, it would be open to the Government to proceed further with the acquisition of property.

(4) As undertaken by SIPCOT in their counter affidavit dated 6 February, 2007, appropriate provisions should be incorporated in the Lease Agreements mandating preservation of ecology and to maintain the ponds and other natural streams by the concerned industrial units.

11.5 As far as the Paragraph No.45 is concerned, in above case, it

was recorded that no Environmental Assessment Study was made after

obtaining acquisition order. However, in this case, as contended by the

respondents, a thorough Environmental Impact Assessment Study was

conducted and after that only the land acquisition process was initiated.

Therefore, the question of obtaining acquisition order/initiating the

acquisition process without conducting Environment Impact Assessment

Study would not arise in this case.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

11.6 As far as the directions issued at Paragraph Nos.46(2) & 46(3)

are concerned, in above case, the Hon'ble Division Bench had no

occasion to consider the 2006 Notification. As discussed above, in terms

of the said 2006 Notification, the question of obtaining Environmental

Clearance would arise only before the commencement of any

construction work or preparation of land by the project management,

which would occur subsequent to the entrustment of land by the

Government to NHAI as held by the Hon'ble Apex Court in the case of

PV Krishnamurthy case at paragraph Nos.79, 86, 93 & 97. Therefore,

the said directions will not apply to the present case at the stage of

issuance of Section 3D Notification.

12. Findings:

12.1 In the present cases, the procedures mentioned in 2006

Notification, 2014 OM and the law laid down by the Hon'ble Apex Court

in PV Krishnamurthy case and C.Kenchappa case, have been duly

adopted by the respondents. Therefore, I am of the considered view that

Section 3D Notification was issued duly in accordance with 2006

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

Notification, 2014 OM and in compliance with paragraph Nos.79, 86, 93

& 97 of the order passed by the Hon'ble Apex Court in PV

Krishnamurthy case.

12.2 As discussed above, in these cases, merely by vesting of land

to Government would not amount to commencement of any construction

work or preparation of land by the Project Management. Admittedly, the

construction or other development works would commence only after

obtaining the Environmental Clearance. Until then, the acquisition

process shall go on parallelly as held by the Hon'ble Apex Court at

paragraph Nos.93 & 95 of PV Krishnamurthy case.

12.3 As held by the Hon'ble Apex Court at paragraph No.79 of PV

Krishnamurthy case, the lands can be entrusted to the NHAI. However,

the NHAI has to wait for the purpose of commencement of construction

work until the receipt of Environmental clearance. Therefore, as stated

above, all the acquisition process, including the entrustment of land to

NHAI, shall go on, but the commencement of construction work and

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

other developmental activities shall be deferred until the receipt of

Environmental Clearance.

12.4 As far as the petitioner's land is concerned, it is inevitably

required for formation of National Highway “NH948A”. It was also

pointed out by the respondents that the total length of the road is 35.766

km, out of which, the road passing through the petitioner's land is only to

the extent of 200 meter. Even the physical construction of the road has

been completed in 28.05 km, for which a sum of Rs.709 Crore has been

incurred till date. Now, only 0.2 km could not be completed because of

the interim stay order granted by this court in the present cases. As

rightly contended by the respondent, since the public money to the tune

of Rs.709 Crore was already spent on this project, if the proceedings,

pertaining to land acquisition, is quashed at this stage, it will certainly

lead to a great loss to the Central Government.

12.5 Further, the present petitions are not filed with regard to the

public interest but it is only about the private interest of the petitioners.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

Normally, the public interest will prevail over the private interest. That

apart, as stated above the Environmental Clearance was duly obtained by

the respondents and now, only the formation/construction of 0.2 km of

road is yet to be completed. In such view of the matter, now, it is not

proper to entertain these petitions by considering the petitioner's private

interest.

13. Result:

For all the reasons stated above, this Court is not inclined to

entertain these cases. Therefore, these writ petitions are dismissed as

devoid of merits. The interim stay/injunction orders, if any, granted in

these writ petitions stand vacated. No cost. Consequently, the connected

miscellaneous petitions are also closed.

26.02.2026 Speaking/Non-speaking order Index: Yes / No Neutral Citation: Yes / No nsa

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm ) W.P.Nos.29753 & 29755 of 2019

KRISHNAN RAMASAMY.J.,

nsa

W.P.Nos.29753 & 29755 of 2019

26.02.2026

https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/03/2026 04:03:51 pm )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter