Thursday, 14, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Chairman vs __________
2026 Latest Caselaw 672 Mad

Citation : 2026 Latest Caselaw 672 Mad
Judgement Date : 23 February, 2026

[Cites 4, Cited by 0]

Madras High Court

The Chairman vs __________ on 23 February, 2026

Author: C.V.Karthikeyan
Bench: C.V.Karthikeyan
                                                                                                Arb Appeal No. 14 of 2025


                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                  Reserved on : 20.01.2026              Pronounced on : 23.02.2026


                                                             CORAM

                                  THE HON'BLE MR JUSTICE C.V.KARTHIKEYAN

                                                                AND

                                  THE HON'BLE MR JUSTICE K.KUMARESH BABU

                                                Arb Appeal No. 14 of 2025
                                                                 and
                                                   CMP No.6208 of 2025


                1. The Chairman
                     Puducherry Housing Board, Anna Nagar,
                     Nellithoppe, Puducherry – 605 005.


                2. The Secretary
                     Puducherry Housing Board, Anna Nagar,
                     Nellilthoppe, Puducherry – 605 005.


                3. The Executive Engineer
                     Puducherry Housing Board, Anna Nagar,
                     Nellithoppe, Puducherry – 605 005.


                                                                                           ..Appellants / Petitioners
                                                                  Vs.




                                                                                                            __________
                                                                                                            Page1 of 13
https://www.mhc.tn.gov.in/judis                  ( Uploaded on: 23/02/2026 03:02:30 pm )
                                                                                            Arb Appeal No. 14 of 2025


                1. Mr.Justice K.P.Sivasubramaniam (Deleted)
                     No.47, Pulla Avenue,
                     Shenoy Nagar, Chennai – 600 030.


                2. M/s Sri Pathy Associates Pvt Ltd
                     Rep. by its Chairman/Authorised Signatory,
                     S.Sekar, Civil Engineering Contractors, No.62,
                     Thanga Perumal Koil Street, Erode – 001.


                     R1 name deleted. Cause title amended vide
                     Court order dated 04.08.2025 made in Arb.
                     Appeal        No.14/2025          (CJ        and         SMJ)


                                                                                                ..Respondents /
                                                                                                   Respondents

                                  This Arbitration Appeal filed under Section 13(1A) of the
                Commercial Courts Act, 2015 r/w. Section 37(1) of the Arbitration &
                Conciliation Act, against the order and decreetal order dated 12.08.2024 made
                in Arbitration OP.No. 33/2019 on the file of the Court of the Principal District
                Judge (Commercial Court), Puducherry.


                              For Appellant(s):               Mr. T.M.Naveen
                              For Respondent(s):              Mr.A.Edwin Prabakar
                                                              For Mr. D. Gopal for R2
                                                              R-1 deleted vide order of Court dated 4/8/2025




                                                                                                        __________
                                                                                                        Page2 of 13
https://www.mhc.tn.gov.in/judis                   ( Uploaded on: 23/02/2026 03:02:30 pm )
                                                                                      Arb Appeal No. 14 of 2025


                                                    JUDGMENT

(Judgment of the Court was delivered by C.V.Karthikeyan J.)

This Arbitration Appeal had been filed questioning the order dated

12.08.2024 in Arb.O.P.No.33 of 2019 on the file of the Principal District Court /

Commercial Court at Puducherry.

2.The respondent herein, M/s.Sri Pathy Associates Private Limited at

Erode, had filed a claim petition before the sole arbitrator in accordance with

Agreement No.2/2002-03 entered into between them and the appellants herein

relating to a contract for Construction of Composite Housing Scheme at

Suthanthira Ponvizha Nagar (Rainbow Nagar) Puducherry, which consisted of

49 units of MIG Flats in 7 Blocks and also included both civil and electrical

works. The tender for the same had been issued on 23.01.2002 for a value of

Rs.3,27,15,868/-. The work order was issued on 19.04.2002. The schedule for

completion was 9 months. The work commenced on 29.04.2002. It should have

been completed as per the work order on 28.01.2003. But it was actually

completed on 05.12.2003 with a delay of 10 months and 7 days. It had been

contended that final extension of time had been granted upto 05.12.2003 by

letter dated 23.07.2004 without levy of compensation.

__________ Page3 of 13 https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/02/2026 03:02:30 pm )

3.It had been contended in the claim statement that the tender was based

on pre-qualified bid. The appellants had however reduced the scope of the

tender and also subsequently called for open tender for construction of the

remaining blocks without awarding a preferential order to the respondent. It was

contended in the claim petition that since there was reduction in the construction

of blocks, the expected profit was not achieved and there was a loss about 15%.

4.It was further contended that there was poor soil condition which

prevented further construction after the foundation concrete had been laid. It

was further contended that at every stage of the construction variations were

indicated by the appellants and this also contributed to the delay in completing

the project. The first foundation work was abandoned owing to poor soil

investigation by the appellants. The work recommenced after a period of eight

months when permission was given to commence the work in an alternate site.

Additional expenditure had to be incurred since there was rise in level in the

water table and water had to be drained out continuously.

5.It was further contended that the agreement provided for use of Cold

Twisted bars / M.S. bars alone. The respondent, however, procured TMT steel

manufactured from Vizag Steel Plant which according to them were of superior

quality. It was contended that the rate of TMT bars was generally higher by

Rs.3.50 to Rs.4.00 per Kg than the ordinary Cold Twisted bars / M.S. bars. It __________ Page4 of 13 https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/02/2026 03:02:30 pm )

was contended that therefore the cost enhanced owing to usage of such TMT

bars. It was further contended that the appellants had failed to settle the bills as

and when submitted and this had also slowed down the construction progress.

Further the structural designs were not given immediately after the work order

was given and were furnished after much delay from the date of the work order.

Claiming that there was a clause in the agreement to refer disputes to

arbitration, the claim petition had been filed seeking a total claim of

Rs.71,26,445/-.

6.The sole arbitrator by award dated 09.04.2018 had examined the

dispute relating to the different quality of steel used and had come to a

conclusion that TMT rods were purchased with the knowledge of the appellants

and that there was no specific prohibition by the appellants from usage of such

TMT bars. The claimant was also not informed that the difference in price

would not be paid by the appellants. In view that particular fact, the claim

seeking difference in the rate was adjudicated in favour of the claimant.

7.With respect to the delay in effecting the payments to the claimant, it

had been stated that the delay was also due to the change in the site as a result of

poor soil condition and owing to other factors which were beyond the control of

the respondent. Finally, the arbitrator had granted, a total compensation of

Rs.23,39,961/- which was rounded to Rs.23,40,000/- and also granted interest at __________ Page5 of 13 https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/02/2026 03:02:30 pm )

9% per annum for the period during the pendency of the arbitration proceedings

and 18% per annum for the post award period.

8.The appellants challenged this award by filing Arb.O.P.No.33 of 2019

before the Principal District Court (Commercial Court) at Puducherry. By an

order dated 12.08.2024 the said petition was dismissed, necessitating filing of

the present Arbitration Appeal.

9.Heard arguments advanced by Mr.T.M.Naveen, learned counsel for the

appellants and Mr.A.Edwin Prabakar for Mr.D.Gopal learned counsel for the

respondent.

10.Even though in the appeal, the appellants had impleaded the arbitrator

as the 1st respondent, subsequently by order dated 04.08.2025 the 1 st respondent

had been deleted, which only left the claimant as the sole respondent in the

appeal.

11.It is the contention of Mr.T.M.Naveen, learned counsel for the

appellants that in the agreement / work order entered into between the

appellants and the respondent, it had been specifically provided that MS Tor

Steel bars alone should be used for structural steel sections and further that the

appellants would be supplying the materials in accordance with the quantity __________ Page6 of 13 https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/02/2026 03:02:30 pm )

required. It had also been provided that the respondent herein should keep in

touch with the day to day position regarding the supply of materials and to

adjust the progress of the work, so that the labour may not remain idle or they

may not raise other claims due to delay in obtaining the materials. It had also

been contended that in the agreement, it had been provided that after the final

bill had been submitted no further claim would be entertained.

12.It had been contended by the learned counsel for the appellants that the

respondent herein had proceeded to utilize TMT bars, the cost of which were

more and also independently procured the steel from Vizag Steel Plant. The

learned counsel disputed the contention that the Cold Twisted bars / MS bars

were not available in the market necessitating purchase of TMT bars by the

respondent from Vizag Steel Plant. He also disputed the contention of the

respondent that permission had been granted to use TMT bars and that there

was an understanding that the enhanced rate would be paid to the respondent.

The learned counsel further contended that after the submission of the final bill,

a further claim was made by the respondent towards the difference in the rates

of the MS bars and TMT bars. It is contended that this claim should not have

been adjudicated and granted by the arbitrator and that this point was also not

considered in the petition filed under Section 34 of the Arbitration and

Conciliation Act. The learned counsel therefore contended that this Court

should reject the claim towards the difference in rate between MS bar and TMT __________ Page7 of 13 https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/02/2026 03:02:30 pm )

bar. It had been contended that the award of the arbitrator and the further order

passed in the petition filed under Section 34 of the Arbitration and Conciliation

Act should be interfered with to that extent.

13.The learned counsel for the respondent, however, contended that

though the site had been initially handed over for putting up of construction of

MIG Flats in 7 Blocks, the appellants had failed to conduct soil test before

deciding the location where the MIG Flats were to be put up. When the

foundation was laid the soil was not fit enough to put up construction in that

place. Thereafter, with further delay of about six to eight months an alternate

site had been allotted to the respondent. The works had commenced. The

learned counsel contended that the steel portion was the critical element in the

construction. The respondent had used TMT bars purchased from Vizag Steel

Plant. The bills thereof had been submitted to the appellants herein. The learned

counsel contended that the quality of the TMT bars were of superior quality

than the MS bars suggested by the appellants. He contended that there was no

delay in presenting the bills. The actual cost had been submitted by the

respondent. The learned counsel contended that both the learned arbitrator and

the Court examining the petition under Section 34 of the Act had correctly

adjudicated all issues and therefore, urged that this Court should dismiss the

appeal.

__________ Page8 of 13 https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/02/2026 03:02:30 pm )

14.We have carefully considered the arguments advanced and perused the

material records.

15.The appellants herein / Puducherry Housing Board had invited tenders

for Construction of Composite Housing Scheme at Suthanthira Ponvizha Nagar

(Rainbow Nagar) Puducherry – MIG Flats 49 units (M8 – 7 Blocks) including

civil and electrical works. The total estimated cost was Rs.2,06,51,434/-. There

is not dispute over the fact that the respondent herein, Sri Pathy Associates

Private Limited, had participated in the tender and was declared as the

successful bidder. Thereafter, issues were raised relating to the site over which

the flats had to be constructed. The soil was unfit for putting up construction

and an alternate site had been located and handed over to the respondent who

had to commence work afresh.

16.But however, the central point raised in this appeal is about the

difference in rate claimed by the respondent in purchase of TMT steel bars vis-

a-vis MS bars as recommended and suggested by the appellants herein. No

ground had been raised that TMT bars utilized by the respondent are of

substandard quality. On the other hand, it the consistent stand of the respondent

that they are of superior quality. Naturally, in any construction, the steel bars

provide the core strength in the construction and in the longevity of the

construction. By usage of higher quality of steel bars the appellants should not __________ Page9 of 13 https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/02/2026 03:02:30 pm )

have entertained any grievance except for the fact that probably the cost was

higher.

17.It is the specific case of the respondent that MS bars, which should not

have been supplied by appellants, had not been supplied in time and when

required and was also not available in the open market. The respondent had

therefore purchased TMT bars from Vizag Still Plant. It is also the specific case

of the respondent that this fact had been informed to the officials of the

appellants and objections were not raised for the usage of TMT bars. There was

also no indication that the bills raised would be rejected or not processed. These

facts had been established both by the Arbitrator and by the Court examining

the petition under section 34 of the Act. The scope of an appeal under Section

36 of the Act on that ground is extremely narrow.

18.This Court cannot revisit the facts already established. This Court can

never step into the shoes of the arbitrator to determine or grant an alternate

finding. Even if two particular views could be drawn it would not mean that the

view drawn by the arbitrator has to be necessarily set aside, unless perversity is

established. The appellants had not stated that the award of the arbitrator suffers

from perversity. The only ground of appeal is that, the respondent could not

have laid a claim for the difference in price between the TMT bars purchased by

them and the MS bars suggested by the appellants. However, as a fact, TMT __________ Page10 of 13 https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/02/2026 03:02:30 pm )

bars had been used. Bills in that regard had been produced and submitted. This

fact cannot be denied or disputed by the appellants. Naturally, when such TMT

bars had been purchased and had been used in the construction, the respondent

is entitled to be paid for the value of such TMT bars. There is no

correspondence produced or evidence adduced that the appellants had protested

at the usage of TMT bars. It must therefore be held that they had acquiescenced

to the usage of the TMT bars in the construction. Having given their consent,

either directly or indirectly, they cannot now turn around and question the bills

which had been submitted for consideration and the claim for the difference in

price.

19.We hold that both the learned arbitrator and the Court in the petition

under Section 34 of the Act had correctly adjudicated the said claim as

admissible.

20.The appellants had also raised an issue of a further bill being presented

after the final bill. But however, even though, there is a specific clause that no

further bills should be raised after the final bill had been presented, the bill so

presented is strictly not an additional claim but an explanation to the final bill

regarding the TMT bars which had been purchased. Both the issues are

interlinked. The claim had been made only for the difference in rate between the

cost of the TMT bars purchased and the cost of the MS bars as suggested by the __________ Page11 of 13 https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/02/2026 03:02:30 pm )

appellants. We find no infirmity in the bills presented. We also find no infirmity

or perversity in the award of the learned Arbitrator or in the order passed in the

petition filed under Section 34 of the Act.

21.In view of these reasons, we find no ground to allow the appeal.

Accordingly, the Arbitration Appeal stands dismissed with costs. Consequently,

connected Civil Miscellaneous Petition is closed.

(C.V.K.,J.) (K.B.,J.) 23-02-2026 smv Index: Yes/No Speaking/Non-speaking order Neutral Citation: Yes/No

__________ Page12 of 13 https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/02/2026 03:02:30 pm )

C.V.KARTHIKEYAN, J.

AND K.KUMARESH BABU, J.

smv

Pre-delivery Judgment made in

23-02-2026

__________ Page13 of 13 https://www.mhc.tn.gov.in/judis ( Uploaded on: 23/02/2026 03:02:30 pm )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter