Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Directorate General Of Light House ... vs M/S.Vignesh Marine Technical Services ...
2025 Latest Caselaw 6802 Mad

Citation : 2025 Latest Caselaw 6802 Mad
Judgement Date : 9 September, 2025

Madras High Court

The Directorate General Of Light House ... vs M/S.Vignesh Marine Technical Services ... on 9 September, 2025

Author: N. Anand Venkatesh
Bench: N. Anand Venkatesh
                                                                                        Arb.O.P.(Com.Div.) No.542 of 2025

                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                 DATED : 09.09.2025

                                                          CORAM

                            THE HONOURABLE Mr.JUSTICE N. ANAND VENKATESH


                                         Arb.O.P.(Com.Div.) No.542 of 2025
                                                       AND
                                                 A.No.4416 of 2025


                The Directorate General of Light House and Light Ships
                “Deep Bhavan”, AB Sector-24
                Gautam Budh Nagar, Noida 201 301
                Rep. by the Director General                                                    .. Petitioner

                                                               Vs.

                M/s.Vignesh Marine Technical Services Pvt. Ltd.
                Plot No.3, 2nd Street, S1, Seenas Apartments
                J.P.Nagar Extension, Surapet
                Chennai, Tamil Nadu 600 066
                Rep. by its Director Mr.N.Arunagiri                                             .. Respondent

                          Petition filed under Section 34(2)(a)(iv); 32(2)(b)(ii) & (iii) and 34(2A)
                of the Arbitration and Conciliation Act, 1996, read with Rule 3(ii) of the Madras
                High Court (Arbitration) Rules, 2020 and with Section 2(1)(c)(vi) and 10(2) of
                the Commercial Courts Act, 2015, to set aside the arbitral award dated
                02.05.2025 to the extent of directing the petitioner to pay to the respondent, a
                sum of Rs.1,14,68.408/- in respect of work order No.17/1/2004-D&P dated
                01.02.2010, between the petitioner and the claimant in respect of the aforesaid
                work order with cost.


                1/12



https://www.mhc.tn.gov.in/judis               ( Uploaded on: 11/09/2025 01:33:11 pm )
                                                                                        Arb.O.P.(Com.Div.) No.542 of 2025




                                    For petitioner      : Mr.A.R.Sakthivel
                                                          Senior Panel Counsel

                                                         ORDER

This application has been filed under Section 34 of the Arbitration and

Conciliation Act, 1996 (for brevity hereinafter referred to as “the Act”),

challenging the Arbitral Award dated 02.05.2025, passed by the sole Arbitrator

directing the petitioner to pay the respondent a sum of Rs.1,14,68,408/-.

2. Heard the learned Senior Panel Counsel appearing on behalf of the

petitioner and carefully perused the materials available on record and more

particularly, the award passed by the sole Arbitrator dated 02.05.2025.

3. The respondent, in the course of their business, approached the

petitioner regarding the usage of Fiber Glass Reinforce Plastic (FRP) for

construction/erection purposes. On enquiry of the petitioner, for construction of

a light house using FRP components, the respondent submitted a detailed

project design, together with the costing of the same. The petitioner approved

the proposal of the respondent and the petitioner issued a Letter of Intent dated

19.08.2009 to the respondent for erection and fabrication of a light house.

Thereafter, a subsequent Letter of Intent dated 11.12.2009 was issued cancelling

https://www.mhc.tn.gov.in/judis ( Uploaded on: 11/09/2025 01:33:11 pm ) Arb.O.P.(Com.Div.) No.542 of 2025

the previous Letter of Intent dated 19.08.2009. A Work Order dated 01.02.2010

was issued by the petitioner to the respondent for fabrication and erection of 30

meters High FRP Composite Tower as per specification and drawing at Rava

Port, Andhra Pradesh, for a total value of Rs.59,68,126/-. The project was to be

completed by 30.04.2010. The IIT, Madras, was engaged as a Consultant and

Inspection Authority. They studied the entire plan and sketch and suggested

suitable modifications, including the use of alternative raw materials. During

this process, the validity period of the project was extended periodically.

Thereafter, the IIT, Madras consultant preferred stronger resins for the project.

The respondent was bringing in various resins to be used as raw materials.

Ultimately, the final approval was granted by the petitioner for using Vinylester

Resin on 04.02.2013. In the meantime, three years had expired from the date of

the Work Order.

4. The project work was commenced only on 22.02.2013. In the

meantime, there was price escalation of raw materials and the petitioner asked

the respondent to continue the project and ultimately, the respondent completed

the project on 30.04.2014 and the light house was thrown open to the public

from November 2014.

5. The respondent was insisting for price escalation and increase in the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 11/09/2025 01:33:11 pm ) Arb.O.P.(Com.Div.) No.542 of 2025

project value and submitted all the documents in this regard. The IIT, Madras,

after scrutiny of all the documents, arrived at a sum of Rs.98,53,148/- being the

final escalated value of the project as against the original project value of

Rs.59,68,126/-. This was intimated to the respondent and the respondent

accordingly raised a bill for the said amount. Even thereafter, repeated

meetings were held by the Committee and there was absolutely no progress.

Aggrieved by the same, the respondent initiated legal proceedings before the

MSE Council on 19.10.2016. When a reply statement was filed by the

petitioner, the respondent came to know that the Committee had rejected the

claim for price escalation. As per the Reply Statement, the Committee Report

stated that the respondent was entitled to receive only a sum of Rs.7,33,440/-

along with 12.5% VAT amounting to Rs.91,680/- towards additional expenses

and price escalation. The respondent found this amount to be grossly

inadequate, considering the actual cost and expenses incurred duly backed by

original vouchers and bills.

6. The MSE Council, vide order dated 26.09.2018, referred the matter to

the Madras High Court Arbitration Centre, by consent given by both sides

resulting in the constitution of Arbitral Tribunal constituting of a sole Arbitrator

for adjudicating the claim made by the respondent.

7. Thereafter, a Claim Statement was made by the respondent for a sum

https://www.mhc.tn.gov.in/judis ( Uploaded on: 11/09/2025 01:33:11 pm ) Arb.O.P.(Com.Div.) No.542 of 2025

of Rs.2,69,55,938/- along with interest.

8. The petitioner filed a detailed Statement of Defence completely

denying their liability towards both escalation cost as well as additional

expenditure claimed by the respondent.

9. The learned Arbitrator, on considering the Claim Statement and the

Defence taken by the petitioner, framed four issues for consideration. The first

issue is, as to whether the delay in completion of the project was attributable to

the petitioner or to the respondent (claimant). The second issue is, as to whether

the respondent (claimant) is entitled to price escalation associated with the

completion of the project. The third issue is, as to whether the IIT, Madras, had

arrived at Rs.98,53,148/- to be the final escalated value of the project as against

the original project value and the fourth issue is, as to whether the claimant had

incurred additional expenses of Rs.1,14,69,408.55 due to change in the original

project design.

10. First, second and fourth issues were decided in favour of the

respondent (claimant) and third issue was decided against the claimant.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 11/09/2025 01:33:11 pm ) Arb.O.P.(Com.Div.) No.542 of 2025

11. Aggrieved by the Award passed by the sole Arbitrator, the present

petition has been filed under Section 34 of the Act.

12. The main grounds that were raised by the learned Senior Panel

Counsel appearing on behalf of the petitioner is that there is patent illegality on

the face of the award and that the award was contrary to the terms of the

contract and the sole Arbitrator had not properly appreciated the evidence and

as a result, had rendered perverse findings and the award is contrary to Section

34(2)(a)(iv) and Section 34(2A) of the Act.

13. It was submitted that the work order dated 01.02.2010 was a fixed

price contract with no clause permitting escalation. Therefore, there is no

question of awarding escalation cost in favour of the respondent (claimant) and

it goes against the very terms of the contract. It was further contended that the

Work Order was for a fixed period and the delay in completion of the work was

only attributable to the respondent (claimant) and therefore, the claimant was

not entitled for any additional expenditure and the same was not even provided

under the contract and whatever was claimed by the respondent (claimant) was

completely awarded in his favour.

14. When it comes to interfering with an award under Section 34 of the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 11/09/2025 01:33:11 pm ) Arb.O.P.(Com.Div.) No.542 of 2025

Act, it is necessary that the Court must be satisfied that there is a patent

illegality which warrants setting aside a domestic award. The law on this issue

was succinctly captured by the Apex Court in the latest judgment in OPG

Power Generation Private Limited v. Enexio Power Cooling Solutions India

Private Limited and another [2025 (2) SCC 417]. Paragraph No.73 of the said

judgment is extracted hereunder:

“73. In a recent three-Judge Bench decision of this Court in DMRC Ltd. v. Delhi Airport Metro Express (P) Ltd. [(2024)6 SCC 357], the ground of patent illegality/perversity was delineated in the following terms:

39. In essence, the ground of patent illegality is available for setting aside a domestic award, if the decision of the arbitrator is found to be perverse, or so irrational that no reasonable person would have arrived at it; or the construction of the contract is such that no fair or reasonable person would take; or, that the view of the arbitrator is not even a possible view. A finding based on no evidence at all or an award which ignores vital evidence in arriving at its decision would be perverse and liable to be set aside under the head of "patent illegality". An award without reasons would suffer from patent illegality. The arbitrator commits a patent illegality by deciding a matter not within its jurisdiction or violating a fundamental principle of natural justice.”

15. The above judgment had taken into account of the earlier judgments

of the Apex Court and it was held that the Court exercising its jurisdiction under

Section 34 of the Act can interfere with an award only if the decision of the

Arbitrator is found to be perverse or it is so irrational that no reasonable person

https://www.mhc.tn.gov.in/judis ( Uploaded on: 11/09/2025 01:33:11 pm ) Arb.O.P.(Com.Div.) No.542 of 2025

would have arrived at such a conclusion. The Court can also interfere where the

construction of contract is such that no fair or reasonable person would take the

view that the Arbitrator had taken and that is not even a possible view. An

award can also be rendered perverse, where the finding is based on no evidence

at all or the Arbitrator has ignored the vital evidence in arriving at the decision.

The Arbitrator can also be said to have committed a patent illegality by deciding

a matter not within its jurisdiction or by violating the fundamental principles of

natural justice.

16. In the case in hand, the entire dispute revolves around the Award

made under two heads viz., the escalation cost and the additional expenditure

incurred by the claimant. The main ground that was raised on the side of the

petitioner is that the Work Order neither provided for payment of escalation cost

or for additional expenditure. Therefore, the award of compensation under

these two heads is beyond the terms of the contract and consequently, the award

suffers from patent illegality.

17. This Court carefully went through the finding rendered by the learned

Arbitrator for the issues No.1 and 2. Issue No.1 pertains to the delay in

completion of the project and to whom such delay was attributable. The learned

https://www.mhc.tn.gov.in/judis ( Uploaded on: 11/09/2025 01:33:11 pm ) Arb.O.P.(Com.Div.) No.542 of 2025

Arbitrator has dealt with the entire claim and the defence taken and also the

evidence on record and has come to a conclusion that the entire delay had taken

place due to factors outside the control of both the parties. Having rendered

such a finding, the learned Arbitrator went into the issue of price escalation.

The learned Arbitrator, in fact, dealt with the defence taken by the petitioner and

came to a conclusion that even if the agreement does not provide for

compensation under the head of price escalation, it can be given, where the

agreement does not specifically bar the payment of compensation under this

head. Having come to such a conclusion, the learned Arbitrator rendered a

finding that the delay in the completion of the project which resulted in the

increase in terms of cost and time was not attributable to the respondent

(claimant) and in the absence of any clause in the Work Order barring a claim

under price escalation, it was held that the respondent (claimant) is entitled to

price escalation associated with completion of the project. This Court does not

find any ground to interfere with the finding of the learned Arbitrator, since it

does not suffer from any infirmity. Probably, with the same materials, an

alternative interpretation can be given, but, that is not a ground for interfering

with the finding of the learned Arbitrator on this issue.

18. Insofar as the fixation of the value for the escalation cost, the learned

https://www.mhc.tn.gov.in/judis ( Uploaded on: 11/09/2025 01:33:11 pm ) Arb.O.P.(Com.Div.) No.542 of 2025

Arbitrator has rightly relied upon the value fixed by the IIT, Madras at

Rs.98,53,148/- and the claim made by the respondent (claimant) under this head

was rejected. Therefore, the escalation cost fixed by the Arbitrator does not

require any interference by this Court.

19. The last issue with regard to the additional expenses that was incurred

by the respondent (claimant), the learned Senior Panel Counsel appearing on

behalf of the petitioner submitted that the petitioner had taken a very specific

stand that the Work Order was for a fixed cost and there was no scope for any

additional cost payable to the respondent (claimant) and this stand was

completely disregarded by the learned Arbitrator.

20. On carefully going through the findings rendered by the learned

Arbitrator for issue No.4, which deals with the additional expenditure claimed

by the respondent (claimant), it is seen that the learned Arbitrator has relied

upon various exhibits in order to support the total cost incurred by the

respondent (claimant) as additional expenditure. Even though the petitioner has

independently denied the claim made by the respondent (claimant) for price

escalation and the additional expenditure, the fact remains that the defence is

more or less common. The learned Arbitrator has held that the delay is not

https://www.mhc.tn.gov.in/judis ( Uploaded on: 11/09/2025 01:33:11 pm ) Arb.O.P.(Com.Div.) No.542 of 2025

attributable to the respondent (claimant) and hence, the escalation cost was

granted and it was fixed based on the report of the IIT, Madras. If that is the

reason given for awarding escalation cost, there is absolutely no reason as to

why the respondent (claimant) must be denied the claim made for additional

expenditure. The reasoning given by the learned Arbitrator which is summed

up at paragraph 56 of the Award, does not suffer from patent illegality.

21. In the light of the above discussion, this Court does not find any

ground to interfere with the Award passed by the learned sole Arbitrator, since

the facts of this case and the grounds raised on the side of the petitioner does not

fall within any of the eight pigeon holes available under Section 34 of the Act.

Accordingly, this petition stands dismissed. No costs. Connected application

stands closed.

09.09.2025 gya

Index : Yes/No Neutral Citation : Yes/No

https://www.mhc.tn.gov.in/judis ( Uploaded on: 11/09/2025 01:33:11 pm ) Arb.O.P.(Com.Div.) No.542 of 2025

N. ANAND VENKATESH, J.

gya

Arb.O.P.(Com.Div.) No.542 of 2025

09.09.2025

https://www.mhc.tn.gov.in/judis ( Uploaded on: 11/09/2025 01:33:11 pm )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter