Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Icici Prudential Life Insurance ... vs Mrs.P.Usha
2021 Latest Caselaw 24641 Mad

Citation : 2021 Latest Caselaw 24641 Mad
Judgement Date : 15 December, 2021

Madras High Court
Icici Prudential Life Insurance ... vs Mrs.P.Usha on 15 December, 2021
                                                                                   O.P.No.171 of 2014


                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                            DATE D       :   15.12.2021

                                                  CORAM:

                         The Hon'ble Mr. Justice SENTHILKUMAR RAMAMOORTHY

                                               O.P.No.171 of 2014


                ICICI Prudential Life Insurance Co. Ltd.
                Regd. Office at
                ICICI Prulife Tower,
                1089, Appa Saheb, Marathe Marg,
                Prabhadevi, Mumbai – 400 025,
                Rep. by its Manager-Legal
                Ms.Shital Patwa                                           ... Petitioner

                                                    Vs

                1.Mrs.P.Usha

                2.Dr.A.M.Swaminathan I.A.S.(Retd)
                  Sole Arbitrator,
                  Nani Palkhivala Arbitration Centre,
                  22, Karpagambal Nagar,
                  Mylapore, Chennai.                                      ... Respondents



                PRAYER : This Petition has been filed under Section 34 of the Arbitration

                and Conciliation Act 1996 praying to set aside the Award dated 18.11.2013

                passed in Arbitration Case No.14 of 2013.



                _____________
https://www.mhc.tn.gov.in/judis
                Page No.1 of 23
                                                                                      O.P.No.171 of 2014


                                           For Petitioner   : Mr.J.Sivanandaraaj
                                                              for Ms.Ridhima Sharma

                                          For Respondents : Mr.V.Anand for R-1


                                                    ORDER

The Petitioner herein was the respondent before the Arbitral

Tribunal. The Arbitral Award dated 18.11.2013(the Award) is assailed by

this petition.

2. A Lease Agreement dated 17.04.2008 (the Lease Agreement)

was entered into between the Petitioner, as lessee, and the first Respondent,

as lessor. The period of lease was for an aggregate term of nine years with

provision for escalation after three and six years. Consequently, the

aggregate lease period was scheduled to expire on 16.04.2017. Although

the lease was for an aggregate period of 9 years, the Lease Agreement was

neither adequately stamped nor registered. The Lease Agreement provided

for termination by the lessee by giving three months advance written notice

to the lessor. The Lease Agreement stipulated that the lessee would deposit

a sum of Rs.18,00,000/- as security deposit, which was repayable by the

lessor on the date of termination of lease and at the time of handing over

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

vacant possession of the relevant premises. A monthly lease rental of

Rs.3,00,000/- was payable by the lessee, inclusive of municipal taxes but

exclusive of service tax and any future taxes imposed by the Government.

On the same date, a separate Agreement for Provision of Amenities and

Services(the Amenities Agreement) was entered into between the parties.

The Amenities Agreement dealt with the provision of the amenities listed in

Annexure -1 thereto by the lessor to the lessee. These amenities included

electricity connection for a total power load of 100 KVA, a diesel generator

set with 100% back up, electrical fittings, fixtures, furniture, AC Units,

LAN, UPS, etc. In connection with the Amenities Agreement, an interest

free refundable security deposit of Rs.27 lakhs was paid by the lessee to the

lessor. This Agreement was co-terminus with the Lease Agreement. While

the Lease Agreement provided for dispute resolution by a sole arbitrator, the

Amenities Agreement contained a separate arbitration clause, which

provided for dispute resolution by a sole arbitrator, if mutually agreed upon,

or, in the alternative, a panel of three arbitrators with the venue of

arbitration being Mumbai.

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

3. By a communication dated 20.05.2009, the Petitioner issued a

notice of termination of the Lease Agreement by relying upon Clause 24

thereof. By such communication, the first Respondent was called upon to

refund the security deposit of Rs.45 lakhs + electricity deposit, if any. This

Rs.45 lakh claim appears to be both under the Lease Agreement and the

Amenities Agreement (Rs.18 lakhs + Rs.27 lakhs = Rs.45 Lakhs). A

subsequent communication dated 26.08.2009 was also issued stating that the

Petitioner is ready to hand over possession on 27.08.2009 and that the rent

for June to August 2009, the amenities charges for June to August 2009 and

the maintenance for June to August 2009 along with the electricity charges

and diesel charges would be handed over at the time of handing over

possession. Further communications dated 28.06.2009 and 30.08.2009 were

also issued in this connection.

4. By a reply dated 02.09.2009(wrongly mentioned as

02.09.2008), the first Respondent informed the Petitioner that she had not

received the rent, service tax, maintenance charges, electricity charges and

diesel charges for the months of June to September 2009. In addition, it was

stated therein that the first Respondent would refund the interest free

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

security deposit after deducting the pending amounts and interest thereon

once the keys are hand over. By a further communication dated 16.09.2009,

the Petitioner called upon the first Respondent to take possession by

refunding the security deposit with interest thereon at 30% per annum.

5. In the above facts and circumstances, a dispute arose between

the parties. The Petitioner herein filed an application under Section 9 of the

Arbitration and Conciliation Act, 1996 (the Arbitration Act) seeking security

for a sum of Rs.45 lakhs and also requesting that a court receiver be

appointed to take possession of the premises. Eventually, in appellate

proceedings arising out of the order passed in the application under Section

9, a Division Bench of this Court, by order dated 09.07.2012 in

O.S.A.No.247 of 2012, directed the parties to resolve the dispute through

arbitration conducted by the Nani Palkhivala Foundation. The Arbitral

Tribunal was constituted pursuant to such order. The first Respondent

herein submitted a statement of claim in April 2013. In such statement of

claim, the first Respondent claimed a sum of Rs.4,25,86,200/-; future rents

till the date of handing over of possession by the Petitioner; 30% interest on

rental dues; Rs.50 lakhs towards damages to amenities; and surrender of

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

possession. The Petitioner herein submitted a counter statement with a

counter claim. In such counter statement-cum- counter claim, the Petitioner

sought to recover the sum of Rs.45 lakhs with interest thereon at 30% per

annum from 30.08.2009. The Arbitral Tribunal framed ten issues based on

the pleadings. Both parties adduced documentary evidence: the first

Respondent/claimant exhibited 11 documents as Exhibits C1 to C11; and the

Petitioner/respondent exhibited 15 documents as Exhibits R1 to R15.

Neither party adduced oral evidence. Eventually, the arbitral proceedings

were disposed of by the Award.

6. The Petitioner assailed the Award on multiple grounds. The

Petitioner contended that the Award is contrary to public policy and is

patently illegal by referring to the documentary evidence on record. By

drawing reference to the Lease Agreement, the Petitioner contended that the

Lease Agreement provided for a security deposit of Rs.18 lakhs. Such

security deposit was liable to be refunded by the lessor upon expiration or

termination of the Lease Agreement. The Petitioner relied upon Clause 24 of

the Lease Agreement which enables the lessee / Petitioner to terminate the

Lease Agreement without assigning any reason by providing three months'

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

advance written notice. The Petitioner also relied upon Clause 30 of the

Lease Agreement which stipulates that the first Respondent / lessor shall

refund the security deposit on the date of handing over of keys / vacant

possession of the demised premises. In case the security deposit is not

refunded as per the Lease Agreement, it was contended that interest at 30%

per annum is payable from the date the security deposit became refundable.

7. The Petitioner also relied upon the communications dated

20.05.2009, 26.08.2009, 30.08.2009 and 31.08.2009 so as to emphasize that

it had called upon the first Respondent to take vacant possession.

According to the Petitioner, the rental dues, amenities charges, maintenance,

electricity charges and diesel charges were offered to be paid at the time of

handing over possession, but the first Respondent refused to take

possession. Indeed, the Petitioner contended that it was constrained to file

applications under Section 9 of the Arbitration Act both to ask for security

for the sum of Rs.45 lakhs and also for the appointment of a receiver to take

possession of the premises.

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

8. The Petitioner also referred to the Award. After pointing out

that the Arbitral Tribunal framed 10 issues, the Petitioner contended that the

Arbitral Tribunal committed a patent illegality by refusing to rely upon the

Lease Agreement even for collateral purposes. As regards the Amenities

Agreement, the Petitioner contended that the said Agreement was duly

stamped and that it did not require registration. With regard to the

inadequacy of stamp duty on the Lease Agreement, the Petitioner contended

that such defect was curable. In addition, it was contended that the Arbitral

Tribunal was duty bound to impound the document and send it to the

Collector for levying the deficit stamp duty with penalty. Once the

deficiency was remedied, the document should have been take into

consideration to adjudicate the dispute. After pointing out that the Lease

Agreement was marked as Exhibit C3 and the Amenities Agreement as

Exhibit C2, the Petitioner contended that once a document is received in

evidence and exhibited, it cannot be disregarded because it is inadequately

stamped as per Section 36 of the Indian Stamp Act, 1899 (the Stamp Act).

9. More importantly, as indicated above, the Petitioner contended

that the Amenities Agreement did not require compulsory registration as per

Section 17 of the Indian Registration Act, 1908 (the Registration Act).

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

However, the Arbitral Tribunal erroneously concluded that the Amenities

Agreement was inadequately stamped and that it required compulsory

registration. On such basis, it was contended that the Arbitral Tribunal

disregarded both the Lease Agreement and the Amenities Agreement. As a

corollary, the Arbitral Tribunal failed to take into account the clauses of the

Lease Agreement and the Amenities Agreement as regards refund of the

security deposit along with interest thereon.

10. The Petitioner further contended that the Arbitral Tribunal

gravely erred in concluding that its authority was derived entirely from the

order of the Division Bench of this Court by which the dispute was referred

to the Nani Palkhivala Foundation. The Petitioner also contended that the

Award is liable to be interfered with because the Arbitral Tribunal exceeded

its jurisdiction and held that the first Respondent is entitled to set-off the

rental dues and amenities charges, even in the post-termination period, until

the date of handing over of keys and possession by the Petitioner.

11. In support of these contentions, the Petitioner referred to and

relied upon the following judgments in course of oral submissions:

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

(i) Silicon Graphics Systems India Private Limited v. NIDAS

Estates Private Limited and Ors. 182(2011) DLT 753, wherein, at paragraph

18, the Delhi High Court held that the licensor was required to refund the

security deposit at the time of vacant possession being handed over and that

if the licensor refuses to do so, the licensee is entitled to retain physical

possession.

(ii) ICRA Limited v. Associated Journals Limited and Ors. (2008)

ILR 1 Delhi 684, wherein, at paragraph 21, the Delhi High Court concluded

that once the lessee offers to hand over possession and the lessor refuses to

take possession, the lessee would be entitled to remain in possession.

(iii) N.N.Global Mercantile Private Limited and others v. INDO

Unique Flame Limited and others (2021) 4 SCC 379, wherein, at paragraph

36.1, the Hon'ble Supreme Court held that the Arbitral Tribunal is obligated

by Section 33 of the Stamp Act to impound an insufficiently stamped

instrument and direct the parties to pay the requisite stamp duty and penalty,

if any, and obtain an endorsement from the Collector concerned.

12. These contentions were refuted by the first Respondent. The

first Respondent submitted that a sum of Rs.39,51,000/- was due and

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

payable by the Petitioner towards rental arrears, amenities charges,

maintenance charges, electricity charges, diesel charges, etc. as of August

2009. Indeed, the first Respondent asserted that the Petitioner also admitted

in contemporaneous correspondence that there were dues towards rent,

amenities, maintenance, etc. By referring to the communication dated

26.08.2009 from the Petitioner, the first Respondent pointed out that the

payments specified therein were not made by the Petitioner. The first

Respondent further submitted that the Lease Agreement was for an

aggregate period of nine years. Therefore, the Lease Agreement was

required to be adequately stamped and registered. Since it was admittedly

not adequately stamped or registered, no rights were created in favour of

the parties by such Lease Agreement. As regards the Amenities Agreement,

the first Respondent contended that the said Agreement was supplementary

to the Lease Agreement. Therefore, it did not have an existence

independent of the Lease Agreement. Since the Lease Agreement was void,

the Amenities Agreement, which was supplementary thereto and co-

terminus therewith, was also void.

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

13. The first Respondent clarified that physical possession of the

property was taken by her only on or about 26.07.2017 pursuant to orders

passed by this Court. At such time, by way of security towards the refund

claim, the first Respondent made a deposit of a sum of Rs.12 lakhs. The

first Respondent contended that the Award is certainly not in violation of

public policy and cannot be termed as patently legal or as shocking the

conscience of the Court. As regards the conclusion of the Arbitral Tribunal

that it derived authority from the order of the Court, the first Respondent

pointed out that the parties had agreed, under the Lease Agreement, to

arbitration by a sole arbitrator to be mutually agreed upon by the parties and

under the Amenities Agreement to arbitration in Mumbai by a panel of three

arbitrators, whereas the Court referred the dispute to the Nani Palkhivala

Foundation. In effect, it was contended that the reference of the dispute for

arbitration was not as per the relevant clause of the Lease Agreement but on

the basis of the order of this Court.

14. Upon considering the rival submissions, several questions

arise for consideration. The first question is whether the Arbitral Tribunal

was justified in disregarding the Lease Agreement. This question was

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

considered and dealt with under Issues 1 and 2 by the Arbitral Tribunal.

Upon examining the Lease Agreement, there is no doubt that the term of

lease is an aggregate period of nine years. Therefore, as per Section 107 of

the Transfer of Property Act, 1882, read with Section 17 of the Registration

Act, the document required compulsory registration. The said document

bears stamp duty of only Rs.300/-, which is not adequate for a nine year

lease under the Stamp Act. Therefore, the stamp duty is also inadequate.

Consequently, the Arbitral Tribunal was justified in concluding that no

rights in respect of the immovable property can be founded on the Lease

Agreement. Learned counsel for the Petitioner contended that the Lease

Agreement could be relied upon for collateral purposes as per the proviso to

Section 49 of the Registration Act. However, from the pleadings and the

Award, it does not appear that such contention was raised before the Arbitral

Tribunal. In any event, the handing over of vacant possession is not

collateral to a lease. Consequently, the refund of security deposit, which is

to be effected simultaneously with the handing over of vacant possession,

cannot be looked at in isolation and construed as collateral. The contention

of the Petitioner that the Lease Agreement was exhibited in evidence and,

therefore, cannot be eschewed may be a valid contention from the

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

perspective of the Stamp Act, but does not cure the defect of non-

registration under the Registration Act or avert the consequences thereof.

15. The next aspect to be considered is the conclusion of the

Arbitral Tribunal on the Amenities Agreement. The subject matter of the

Amenities Agreement is the provision of the amenities listed in Annexure-1

thereto. As indicated earlier, these amenities included, inter alia, electricity

connection, diesel generator, electricity fittings, fixtures, furniture, AC

Units, router. The Amenities Agreement was clearly not a document by

which interest in immovable property was created, declared, transferred,

limited or extinguished. It also does not fall within the scope of any of the

clauses in sub-section (1) of Section 17 of the Registration Act. Therefore,

an agreement of this nature did not require compulsory registration under

Section 17 of the Registration Act. The said Agreement bears the stamp

duty of Rs.300/-, which is adequate because an agreement of this nature

would fall within the residuary entry in Article 5 of Schedule I of the Stamp

Act. On this issue, the Arbitral Tribunal committed an error by treating it in

the same manner as the Lease Agreement. Hence, the material clauses of the

Amenities Agreement should be examined so as to determine if the non-

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

consideration of the same vitiates the Award. Clause 1 of the Amenities

Agreement provided for payment of a sum of Rs.4,50,000 per month as

charges for the provision of amenities and services and Clause 2 stipulated

that such charges shall be paid on or before the 7th of each month. Clause 4

of the Amenities Agreement deals with the security deposit and is, therefore,

of significance. The said Clause is as under:

''4. An interest free refundable Security deposit amounting to Rs.27,00,000/- (Rupees Twenty Seven Lakhs only) shall be payable to the Lessor upon the signing of the agreement. The security deposit will be held by the Lessor during the said leave and licence agreement and this amenities agreement and shall be returned upon the expiration or earlier termination of the agreement after the deduction of any reasonable dues or damages if any arising out of and in pursuance of the Leave and Licence agreement.

The Lessor shall refund security deposit on the date of handing over of keys/Vacant possession of the demised premises by the lessee either by Demand Draft/ Current Dated cheque. In case if the lessee gives written communication before 5 days of handing over of the keys / Vacant possession, then the lessor shall issue a Post dated cheque(PDC) with respect to

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

last date of termination of the lease agreement.

Furthermore, the Lessor shall pay an interest @ 30% per annum on the security deposit for such period the security deposit is not refunded to the Lessee in case of such termination.'' (emphasis added).

16. On perusal of Clause 4, it is evident that a security deposit of

Rs.27 lakhs was specified as payable by the Petitioner. The said clause

further specified that the security deposit should be refunded upon the

expiry or termination of the Agreement, after deducting reasonable dues or

damages arising out of the Lease Agreement, on the date of handing over

the keys / vacant possession of the demised premises by the lessee. In

addition, it provided for the payment of interest at 30% per annum on the

security deposit if the same is not refunded.

17. The question whether the Award is liable to be interfered with

on account of non-consideration of the Amenities Agreement is examined

next. As indicated above, as a consequence of disregarding the Amenities

Agreement, the Arbitral Tribunal did not take into account the clauses

thereof, including Clause 4. On this issue, it should be noticed that even de

hors the Lease Agreement and the Amenities Agreement, the amounts

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

payable monthly towards rent and amenities charges, and the amounts

deposited by way of security deposit are not in dispute. For instance, the

communication dated 16.09.2009 from the Petitioner sets out these amounts

with no room for ambiguity. Besides, the communication dated 26.08.2009

from the Petitioner clearly indicates that there are dues towards rent,

amenities, maintenance, etc. from June 2009 onwards. In this factual

context, the Arbitral Tribunal examined whether possession was handed

over by the Petitioner especially while dealing with Issues 5 and 6 by

looking at the correspondence between the parties. Upon considering such

evidence, the Arbitral Tribunal recorded, in relevant part, as under while

dealing with Issue 5:

“ ....Copies of the correspondence filed as Exhibits show the Respondent using the terms like “ready to hand over”, “called upon to take over”, etc. Even in his final written submission the Respondent submitted that they “only held de jure possession, they are not enjoying the benefits of the premises”, etc. When it comes to immovable property like a locked office premises, when the key to the premises is still held by the tenant, it cannot be said that proper possession has been handed over to the landlord. Issue 5 is answered accordingly.”

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

In this manner, the Arbitral Tribunal proceeded to enter a finding that the

Petitioner had not handed over possession and therefore continued to be

under an obligation to pay rent and amenities charges. These conclusions

were based on a reasonable appraisal of the documentary evidence on

record. Therefore, such conclusion does not warrant interference under

Section 34 of the Arbitration Act. Clause 4 of the Amenities Agreement

would have enured to the benefit of the Petitioner only if the Arbitral

Tribunal had concluded that the Petitioner had handed over or at least taken

all possible steps to hand over possession to the first Respondent. However,

the Arbitral Tribunal concluded that the Petitioner did not hand over

possession either by delivering physical possession or by handing over the

keys because of pending issues such as rental arrears, maintenance and

amenities charges arrears, etc. Consequently, the error committed by the

Arbitral Tribunal in not taking into account the Amenities Agreement does

not vitiate the Award. In other words, it cannot be construed as an illegality

which goes to the root of the case.

18. The Petitioner contended that the Arbitral Tribunal erred in

concluding that it derived authority and jurisdiction from the judgment of

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

the Division Bench and not from the arbitration clause in the Lease

Agreement and Amenities Agreement. There is merit in this contention

inasmuch as the arbitration agreement is required to be treated as

independent of other clauses in an agreement as per Section 16(1)(a) of the

Arbitration Act and, as per clause (b) of the above Section, even if it is

concluded that the contract is invalid, it does not lead to the inference that

the arbitration clause is invalid. Nonetheless, the error on this count is a

non-sequitur because the Award cannot be interfered with merely because

the Arbitral Tribunal was under the misconception that it derived authority

only from the judgment of the Division Bench of this Court.

19. Another contention was raised that the Arbitral Tribunal

exceeded the scope of authority in directing payment of rent and amenities

charges in the post-termination period. This contention should be tested by

examining the arbitration clause in the Lease Agreement and Amenities

Agreement. Both Clause 45 of the Lease Agreement and Clause 10 of the

Amenities Agreement, which are the arbitration clauses, are wide and use

the expression “any dispute”. In addition, both use the expression

“howsoever arising”. In such context, it certainly cannot be concluded that

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

the direction to pay rent and amenities charges in the post-termination

period is beyond the scope of reference or beyond jurisdiction.

20. This arbitration and even the Section 34 petition were prior to

Act 3 of 2016. Therefore, the law that applied prior to 23.10.2015 should be

applied. Under the then prevailing legal regime, an arbitral award could be

interfered with if it conflicts with public policy, including on account of

being patently illegal. While the Petitioner contended that the Award is

liable to be interfered with by citing Delhi Development Authority v. R.S.

Sharma and Company, New Delhi (2008) 13 SCC 80 and Associate Builders

v. Delhi Development Authority (2015) 3 SCC 49, the said judgments

instruct that an award is patently illegal if it is so unfair and unreasonable

that it shocks the conscience of the Court. The Award in the case at hand

may contain errors in certain respects, but when viewed dholistically does

not qualify as being patently illegal or as shocking the judicial conscience.

Therefore, the Petitioner's challenge fails.

21. By the operative part of the Award, the Arbitral Tribunal

concluded that the first Respondent is entitled to set-off amounts due and

payable towards rent and amenities charges, at Rs.7,50,000/- per month,

from the security deposit of Rs.45 lakhs until the date of handing over of

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

possession by the Petitioner to the first Respondent. Since the Award was

pronounced on 18.11.2013, it proceeded on the assumption that after

setting-off such amounts, a portion of the security deposit would be

refundable to the Petitioner. Accordingly, the balance of the security deposit

was directed to be paid by the first Respondent to the Petitioner herein.

However, the Petitioner challenged the Award before this Court, and did not

hand over physical possession until about 26.07.2017. As a corollary, the

rent and amenities charges would, in all likelihood, have exceeded the

security deposit, if computed at Rs.7,50,000 per month up to the date of

hand over, as indicated in the Award. This may result in a dispute which the

Award did not envisage or deal with. The Award also enables the parties to

institute separate proceedings as regards damages to the leased premises.

22. For reasons set out above, the Award, including the operative

part thereof, does not call for interference. Consequently, the first

Respondent is entitled to file an appropriate application for payment out of

the amounts deposited by the first Respondent as a condition for taking

possession. However, open issues such as claims or disputes in relation to

amounts due and payable by the Petitioner to the first Respondent towards

rental dues, amenities charges, maintenance charges,etc. after setting-off the

_____________ https://www.mhc.tn.gov.in/judis

O.P.No.171 of 2014

entire security deposit or claims for damages may be dealt with by the

parties in accordance with law. O.P.No.171 of 2014 is disposed of on the

above terms without any order as to costs.



                                                                            15.12.2021

                Index    :Yes
                Internet :Yes
                rrg




                _____________
https://www.mhc.tn.gov.in/judis

                                                         O.P.No.171 of 2014


                                   SENTHILKUMAR RAMAMOORTHY J.

                                                                     rrg




                                                 O.P.No.171 of 2014




                                                        15.12.2021



                _____________
https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter