Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Chief Engineer Chennai Zone vs M/S.Amulya Constructions
2021 Latest Caselaw 23620 Mad

Citation : 2021 Latest Caselaw 23620 Mad
Judgement Date : 2 December, 2021

Madras High Court
The Chief Engineer Chennai Zone vs M/S.Amulya Constructions on 2 December, 2021
                                                                          O.P.No.501 of 2017

                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                              DATED : 02.12.2021

                                                    CORAM

                     THE HONOURABLE Mr. JUSTICE SENTHILKUMAR RAMAMOORTHY

                                              O.P.No.501 of 2017

                     Union of India rep by
                     1.The Chief Engineer Chennai Zone,
                     Island Grounds,
                     Chennai - 600 009.               ...Petitioner/Respondent No.1

                     2.The Garrison Engineer (I),
                     Laxmi Tek Camp,
                     Belgaum - 590 009.                  ...Petitioner/Respondent No.2

                                                        -Vs.-

                     M/s.Amulya Constructions
                     rep.by its Partner,
                     No.567, 2nd Cross, 2nd Block,
                     R.T. Nagar,
                     Bangalore - 560 032.                ... Respondent/Claimant



                     Prayer: Original Petition filed under Section 34 of the Arbitration
                     and Conciliation Act, 1996 praying to set aside the Award dated
                     15.12.2016 made in Arbitration C.A.No.CECZ/BEL.24 of 2010-11
                     and to direct the respondent to pay costs.



https://www.mhc.tn.gov.in/judis
                     1/15
                                                                                 O.P.No.501 of 2017

                                  For Petitioners   :     Mr.R.Sankaranarayanan
                                                          Additional Solicitor General
                                                          assisted by
                                                          Mr.Venkataswamy Babu


                                  For Respondent :        Mr.R. Yashod Vardhan
                                                          Senior Counsel
                                                          for M/s.Rajinish Pathiyil


                                                          ORDER

The petitioners assail an arbitral award dated 15.12.2016 (the

Award). In the arbitral proceedings, the petitioners herein were the

respondents and the respondent herein was the claimant.

2. A contract was entered into between the first petitioner

and the respondent on 07.03.2011 for the construction of

residential quarters for the employees of the petitioners (the

Contract). The term of Contract was twenty months for completion

of the two phases thereof. The first petitioner was under an

obligation to provide the site for construction after clearing the

trees standing thereon. On account of the fact that the first

https://www.mhc.tn.gov.in/judis

O.P.No.501 of 2017

petitioner was unable to provide a vacant site to the respondent

until 29.10.2012 (Exhibit C-41) and other reasons such as failure to

provide electricity supply, the respondent issued a notice dated

19.12.2012(Exhibit C-50) informing the petitioners that it had

mobilized its men and material and that the said resources were

idling at site. On such basis, a claim for escalation was made. In

addition, the petitioners were put on notice that the respondent is

entitled to overhead charges and loss of profit. The petitioners were

also informed that the Contract would stand rescinded if such

escalation is not agreed to by the petitioner. Pursuant thereto, it

appears that the petitioners also issued a termination notice dated

23.01.2013. In these facts and circumstances, the respondent

initiated arbitration proceedings. In such arbitration, the

respondent claimed amounts due and payable towards the final bill.

In addition, reimbursement claims were made as well as a claim for

loss of profit. In oral arguments, the petitioners confined the

challenge to the loss of profit claim and the Award in relation

thereto. The claim for loss of profit was for a sum of

https://www.mhc.tn.gov.in/judis

O.P.No.501 of 2017

Rs.2,01,92,002/-. As against the said claim, the Arbitral Tribunal

awarded a sum of Rs.66,71,000/-.

3. The petitioners assail this part of the Award on the

principal ground that a loss of profit claim is a claim for

unliquidated damages. Such claim is required to be proved by

adducing evidence. The petitioners referred to paragraph 105 of

the Award and contended on such basis that it had requested the

Arbitral Tribunal to direct the respondent/Contractor to submit the

audited income tax returns for the previous ten years so as to

ascertain the profit percentage derived by the Contractor from

previous projects executed by it. In spite of such specific request,

it is stated that the Arbitral Tribunal did not direct the respondent

to produce such evidence. The petitioners also referred to

paragraph 110 of the Award and pointed out that there was no basis

at all to the conclusion in the Award that the respondent is entitled

to loss of profit at 5% of the balance value of the Contract.

https://www.mhc.tn.gov.in/judis

O.P.No.501 of 2017

4. In support of this contention, the petitioners relied upon

the following judgments:

(i)Bharat Coking Coal Limited v. L.K. Ahuja [(2014) 5

Supreme Court Cases 109] (Bharat Coking Coal), wherein, at

paragraph 24, the Hon'ble Supreme Court held that a person

claiming loss of profit should establish that he could have utilised

the resources deployed on the contract on some other business

through which he could have earned the profit claimed.

(ii)MSK Projects India (JV) Limited v. State of Rajasthan

and another [(2011) 10 Supreme Court Cases 573](MSK

Projects), wherein, at paragraphs 38 and 39, the Hon'ble Supreme

Court referred to the meaning of the expression “reimbursement”

and, thereafter, at paragraphs 45 to 47, rejected the claim on the

basis that a person cannot be permitted to claim damages in respect

of amounts not spent in terms of the contract.

https://www.mhc.tn.gov.in/judis

O.P.No.501 of 2017

(iii)Oil and Natural Gas Corporation v. Off-Shore

Enterprises Inc. [(2011) 14 Supreme Court Cases 147](Off-shore

Enterprises), wherein, at paragraphs 16 and 20, the Hon'ble

Supreme Court rejected a claim for cost of repair work based on

estimates which were revised upwards from time to time.

(iv)Kailash Nath Associates v. Delhi Development Authority

and another [(2015) 4 Supreme Court Cases 136], wherein the

Hon'ble Supreme Court considered the law on the award of

damages and held that even for a claim for liquidated damages, a

person aggrieved is required to prove actual loss unless actual loss

would be impossible or difficult to prove in view of the nature of

the contract.

5. These contentions were refuted by the respondent. At the

outset, the respondent emphasised that the Arbitral Tribunal

recorded the categorical finding that the petitioners had committed

a fundamental breach of Contract. On such basis, it was contended

https://www.mhc.tn.gov.in/judis

O.P.No.501 of 2017

that the Arbitral Tribunal accepted the plea of the respondent that

its rescission was valid. The respondent referred to paragraph 107

of the Award and pointed out that the Arbitral Tribunal recorded

therein that every business is undertaken with a view to receive

profit. In addition, the respondent pointed out that the Arbitral

Tribunal took note of the fact that Condition 62(G) of the relevant

General Conditions of Contract provided for the Contractor's profit

margin at 15% of the value of the Contract. The respondent also

adverted to the notice dated 19.12.2012 from the respondent to the

petitioners. By referring to paragraphs 12 and III (a) and (b) of

such notice, the respondent contended that it had established that

its men and equipments were mobilized in order to perform the

Contract and that it had incurred substantial losses on such account.

6. In this factual context, the respondent contended that the

award of loss of profit at 5% of the value of the balance work does

not call for interference under Section 34 of the Arbitration and

Conciliation Act, 1996 (the Arbitration Act). The respondent

https://www.mhc.tn.gov.in/judis

O.P.No.501 of 2017

relied upon the judgment of the Hon'ble Supreme Court in

Maharashtra State Electricity Distribution Company Limited v.

Datar Switchgear Limited and others [(2018) 3 Supreme Court

Cases 133]. With specific reference to paragraphs 51 and 67

thereof, the respondent contended that a party which was held to

have been always ready and willing to perform its contractual

obligations but was prevented by the counter party from doing so is

entitled to damages. The respondent also distinguished the

judgments that were relied upon by the petitioners. With reference

to the judgment in Bharat Coking Coal, the respondent submitted

that the conclusion in paragraph 24 thereof turned on the fact that

the prolongation claim and the claim for escalation had been paid

in that case. Therefore, the Hon'ble Supreme Court rejected the

claim of loss of profit at 15%. Similarly, with reference to the

judgment in MSK Projects, the respondent pointed out that the

Hon'ble Supreme Court rejected the claim because the contract had

not been performed by the private appellant therein in respect of

the second phase. As regards the judgment in Off-Shore

https://www.mhc.tn.gov.in/judis

O.P.No.501 of 2017

Enterprises, the respondent pointed out that the claim therein

pertained to repair work. Given the nature of the claim, the actual

expenditure for repair work could and should have been proved

through hard evidence. Therefore, the respondent concluded that

all the above judgments are distinguishable.

7. Upon considering the rival submissions, it should be

noticed at the outset that the Award is challenged only insofar as

the decision on the claim for loss of profit is concerned. A claim

for loss of profit is distinguishable from other types of claim which

are typically made in construction contract disputes by a contractor.

Typically, claims are made for: payment for work done, including

additional work; disruption (otherwise called idling); price

variation (otherwise called escalation); prolongation (otherwise

called extended stay compensation); and loss of profit. Other than

a loss of profit claim, as regards all the other types of claim

outlined above, it is possible for a claimant to prove loss by

adducing evidence of actual loss. A qualification should be made,

https://www.mhc.tn.gov.in/judis

O.P.No.501 of 2017

however, in respect of the portion of the prolongation claim

towards head office overheads because the overall head office

overheads should be apportioned across all the projects of the

contractor and, therefore, various formulae are adopted. A claim

for loss of profit, by contrast, falls into a distinct category. Such

claim is made towards profit which was not earned but which could

possibly have been earned but for the termination or breach by the

employer. Therefore, such claim cannot be proved by showing

actual loss of profit. The merits of this petition should be

considered by bearing the nature of a loss of profit claim in mind.

8. The respondent adverted to the notice dated 19.12.2012

and, in particular, paragraph 12 thereof to defend the Award on this

aspect. In such paragraph, the respondent categorically stated that it

had mobilized its men and material so as to perform the Contract.

Such men and material appear to have been deployed for about 19

months of the contractual term of twenty months. A claim was

made in such communication towards overhead charges and loss of

https://www.mhc.tn.gov.in/judis

O.P.No.501 of 2017

profit. Ideally, in such situation, a claim towards non-utilisation of

men and material on account of prevention by the employer could

have been made as a disruption claim. However, except for

claiming reimbursement for tools and infrastructure, which were

retained by the petitioner-employer, no disruption claim was made.

Equally, no claim for price variation or escalation was made before

the Arbitral Tribunal. The admitted position is that the Contract

was initially rescinded by the respondent herein and, thereafter,

purportedly terminated by the petitioner.

9. The findings of the Arbitral Tribunal on loss of profit

should be considered next against this backdrop. The Arbitral

Tribunal recorded that the respondent/claimant therein was ready

and willing to perform its contractual obligations. The Arbitral

Tribunal also recorded that the petitioners herein did not perform

the prior contractual obligation of, inter alia, providing the vacant

site. Thus, the first condition for any claim for damages, namely,

breach of contract was undoubtedly established. The question of

https://www.mhc.tn.gov.in/judis

O.P.No.501 of 2017

proof of damages remains to be examined. At paragraph 107, the

Arbitral Tribunal recorded that every business is carried on in order

to gain profit there from. Thereafter, significantly, the Arbitral

Tribunal noticed that Condition 62(G) of the General Conditions

of Contract provides for Contractor's profit at 15% of the value of

the Contract. Then, after noticing the judgment of the Hon'ble

Supreme Court in Brij Paul Singh , at paragraph 110, the Arbitral

Tribunal awarded loss of profit at 5% of the balance value of work

by taking into account the level of competition in the market.

10. In a loss of profit claim, the best evidence that the

respondent could have been adduced would have been by

producing its bid document indicating the profit margin which was

assumed therein or by adducing evidence of other similar contracts

awarded to the respondent or any other contractor. Even such

assumption could turn out to be completely off the mark, especially

in a fixed price contract, due to price escalation and its impact on

margins. Even as regards other contracts, no two contracts are

https://www.mhc.tn.gov.in/judis

O.P.No.501 of 2017

identical and actual profit margins tend to vary as many variables

impact such margins. The petitioners contended that the Arbitral

Tribunal should have called for the income tax returns of the

respondent. Such income tax returns would, in all likelihood, have

not indicated project-specific profit margins although an average

profit margin could, arguably, have been computed. As set out at

the inception of the analysis, unlike in the case of other claims, no

proof of actual loss of profit could have been adduced. Another

significant aspect is that the Arbitral Tribunal awarded 5%, which

is lower than the typical 10%-15% profit margin factored in

construction contracts as judicially noticed not only in Brij Paul

Singh but also Government of Andhra Pradesh and others v.

V.Satyam Rao, AIR 1996 AP 288 (DB), and The Superintending

Engineer, T.N.U.D.P., Madras Circle v. A.V.Rangaraju AIR

1994 Mad 217. As correctly pointed out by the respondent,

Bharat Coking Coal is distinguishable. In this context and bearing

in mind that the Arbitral Tribunal took note of Condition 62(G) of

the General Conditions of Contract, I am of the view that the

https://www.mhc.tn.gov.in/judis

O.P.No.501 of 2017

Award cannot be said to be either against public policy or patently

illegal so as to warrant interference under Section 34 of the

Arbitration Act.

11. For reasons set out above, O.P.No.501 of 2017 is

dismissed without any order as to costs.



                                                                            02.12.2021

                     Internet   : Yes/No
                     Index      :Yes/No
                     Speaking / Non-Speaking
                     mps/rrg




https://www.mhc.tn.gov.in/judis

                                                   O.P.No.501 of 2017

                                  SENTHILKUMAR RAMAMOORTHY, J,



                                                           mps/rrg




                                              O.P.No.501 of 2017




                                                      02.12.2021




https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter