Citation : 2025 Latest Caselaw 11676 MP
Judgement Date : 27 November, 2025
NEUTRAL CITATION NO. 2025:MPHC-JBP:61419
1 WP-36016-2025
IN THE HIGH COURT OF MADHYA PRADESH
AT JABALPUR
BEFORE
HON'BLE SHRI JUSTICE SANJEEV SACHDEVA,
CHIEF JUSTICE
&
HON'BLE SHRI JUSTICE VINAY SARAF
ON THE 27th OF NOVEMBER, 2025
WRIT PETITION No. 36016 of 2025
M/S ANUSHKA POWER INC
Versus
THE STATE OF MADHYA PRADESH AND OTHERS
Appearance:
Shri Eijaz Nazar Siddiqui - Advocate for Petitioner.
Shri H.S. Ruprah - Additional Advocate General and Shri Dr. S.S.
Chauhan - Government Advocate with Shri Akash Malpani - Advocate for
Respondents/State.
ORDER
Per: Hon'ble Shri Justice Sanjeev Sachdeva, Chief Justice
1. Petitioner is aggrieved by action of the respondent, whereby by order dated 11.08.2025 the representation of the petitioner challenging the
order of termination dated 27.06.2025 has been dismissed.
2. The petitioner, being a consortium partner of respondent No. 5, was awarded the contract vide agreement dated 06.05.2025. However, the said contract has subsequently been terminated by the impugned order dated 27.06.2025.
3. Learned Additional Advocate General appearing on behalf of State
NEUTRAL CITATION NO. 2025:MPHC-JBP:61419
2 WP-36016-2025 submits that a contract was awarded pursuant to NIT dated 28.01.2025, which provides for settlement of disputes through the mode of arbitration. He further submits that the contract itself stipulates that the agreement is terminable. Reference is drawn to Clause 4.3.
4. Clause 4.3 reads as under :
4.3. TERMINATION 4.3.1. TERMINATION BY DEFAULT
The competent authority may, without prejudice to any other remedy for breach of contract, by a written notice of default of at least 30 days sent to the Service Provider, terminate the contract in whole or in part: -
I. If the Service Provider fails to deliver any or all quantities of the service within the time period specified in the contract, or any extension thereof granted by the Department; or
II. If the Service Provider fails to perform any other obligation under the contract within the specified period of delivery of service or any extension granted thereof; or
III. If the Service Provider, in the judgment of the Department, is found to be engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the contract.
IV. If the Service Provider commits breach of any condition of the contract.
4.3.2. TERMIINATION OF INSOLVENCY
The Department may at any time terminate the Contract by giving a written notice of at least 30 days to the Service Provider, if the Service Provider become bankrupt or otherwise insolvent or unable to perform due to any major change in the management of the bidder, bidder's bankers refusing to release funds.
Impact Of Termination On Ground Of Default Or Insolvency
If the Department terminates the contract in whole or in part, PBG may be forfeited and payment for goods already supplied / work already done shall not be made. Termination will be without compensation to the Service Provider. Such termination will not prejudice or affect any further right of action or remedy that has accrued or will accrue thereafter to MP Police.
NEUTRAL CITATION NO. 2025:MPHC-JBP:61419
3 WP-36016-2025
4.3.3. TERMINATION OF CONVENIENCE
M.P. Police by written notice of not less than 90 days sent to the successful bidder may terminate the Contract, if whole or in part, at any time for its convenience. The notice of termination shall specify that termination is for its convenience. In case of termination for convenience, M.P Police would pay to the bidder cost of goods and services provided till the date of the termination. The PBG in such a case would be refunded to the successful bidder.
4.3.3.A . Further the M.P Police shall also have the unfettered right to repudiate and rescind the Contract by providing 30 days written notice, if there is any breach of the Contract by the Successful Bidder including but not limited to the occurrence of any of the following events or contingencies:
I. Performance Bank Guarantee not submitted within the stipulated as mentioned in the RFP.
II. Performance Bank guarantee not renewed as mentioned in the RFP.
III. Quality of service is found to be grossly substandard or not as per specifications/agreements or Bidder failing to replace such defective or deficient goods and services even after giving sufficient notice of the same.
IV. inordinate delay in completion of tasks beyond given time limits.
V. Failure to provide warranty, maintenance or handholding support.
In such a situation same consequence may follow as mentioned at Clause 4.3.2A above. And It may lead to blacklisting of successful bidder
5. Clause 4.3. provides for termination of contract under different circumstances inter alia termination by default, termination for insolvency and termination of convenience. Clearly the parties have agreed that the contract is terminable. It is settled position of law that there can be no specific performance of a contract which is terminable in nature. Clause 4.3 clearly shows that the contract is terminable accordingly, there can be no direction for specific performance of the contract and as such petitioner cannot seek setting aside of the termination and right to continue performing
the contract. In case, the petitioner is aggrieved by the termination on the
NEUTRAL CITATION NO. 2025:MPHC-JBP:61419
4 WP-36016-2025 ground that same is unlawful or wrongful, it is open to the petitioner to avail of such remedy as may be permissible in law.
6. Reference may be had to the judgment of Indian Oil Corporation Ltd. Vs. Bhagwan Balasai Enterprises (1991) 1 SCC 533, wherein the Supreme Court has held that in respect of a contract which is in nature determinable, no specific performance is permissible and the only remedy lies to seek appropriate damages.
7. Since it is a case of the respondent that there is an arbitration clause in the NIT, it is open to the petitioner to invoke the Alternative Dispute Resolution Mechanism for redressal of his grievance quo wrongful termination of contract.
8. In view of the above, petition is disposed of.
9. It is clarified that this Court has neither considered nor commented on the merits of the contention of either parties. All rights and contentions of the parties are reserved.
(SANJEEV SACHDEVA) (VINAY SARAF)
CHIEF JUSTICE JUDGE
Shub
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!