Citation : 2022 Latest Caselaw 12541 MP
Judgement Date : 20 September, 2022
1
IN THE HIGH COURT OF MADHYA PRADESH
AT JABALPUR
BEFORE
HON'BLE SHRI JUSTICE RAVI MALIMATH,
CHIEF JUSTICE
&
HON'BLE SHRI JUSTICE VISHAL MISHRA
ON THE 20th OF SEPTEMBER, 2022
WRIT PETITION No. 15248 of 2021
BETWEEN:-
VAISHNO ASSOCIATES THROUGH ITS PARTNER
OM NARAYAN SINGH, S/O SHRI RAJENDRA SINGH,
AGED ABOUT 36 YEARS, R/O INFRONT OF
VAISHALI ENCLAVE, SHAKTI NAGAR UMARI,
DISTRICT SATNA (MADHYA PRADESH)
.....PETITIONER
(BY SHRI ALOK KUMAR GUPTA - ADVOCATE)
AND
1. M.P. RURAL ROAD DEVELOPMENT
AUTHORITY THROUGH CHIEF EXECUTIVE
OFFICER BLCOK-2, 5TH FLOOR, PARYAVAS
BHAWAN, ARERA HILLS, BHOPAL (MADHYA
PRADESH)
2. CHIEF GENERAL MANAGER (T AND e-G) MP
RURAL DEVELOPMENT AUTHORITY, BLOCK-
2, 5TH FLOOR, PARYAVAS BHAWAN, ARERA
HILLS, BHOPAL (MADHYA PRADESH)
3. GENERAL MANAGER, M.P. RURAL
DEVELOPMENT AUTHORITY, PIU, SATNA,
DISTRICT SATNA (MADHYA PRADESH)
.....RESPONDENTS
(SHRI RAHUL DESHMUKH - ADVOCATE FOR RESPONDENT NO.3)
-----------------------------------------------------------------------------------------------------------------
2
This petition coming on for admission this day, Hon'ble Shri Justice
Vishal Mishra passed the following:
ORDER
Aggrieved by the order dated 30.07.2021 passed by the respondents rejecting the bid of the petitioner, the instant writ petition is filed.
2. It is his case that petitioner being a registered partnership firm incorporated under the Indian Partnership Act and registered contractor with M.P. PWD. Notice Inviting Tender (NIT) was issued by the respondents on 18.05.2021 for work of construction/up-gradation of rural roads under the Pradhan Mantri Gram Sadak Yojana (PMGSY) including maintenance of five years after construction, in various districts of Madhya Pradesh. Petitioner's fulfilling the qualifying criteria, applied for the same. In terms of Clause 4.6 of Section 2, "Instructions to Bidders" (ITB), according to which the bidder should meet the minimum qualification criteria, only if their available bid capacity for the construction work is equal to or more than the bid value excluding maintenance duly calculated as per the formula. Petitioner submitted tenders for six packages, which were opened on 06.07.2021 and on further dates. Four tenders were opened by the respondents. The petitioner informs the respondents on 09.07.2021 regarding non inclusion of the bid capacity and the work undertaken by the petitioner due to mistake and the same was unintentional. Therefore, requested the respondents to take into account the bid capacity of the petitioner, which is more than the required bid capacity. Vide e-mail dated 12.07.2021 and 16.07.2021, he was informed that the bid for package reference no.MP 34715 and MP 34725 were opened and admitted. Thereafter, he has received a letter on 30.07.2021 rejecting the bid of the petitioner during technical evaluation for the reason "Non-responsive".
3. It is his case that despite intimation being sent to the respondents regarding revised bid capacity of the petitioner vide letter dated 09.07.2021, the
same was not taken note of and bid was rejected on technical grounds. It is his case that the information regarding the bid capacity was already furnished prior to finalization of the bid. Therefore, the authorities were under an obligation to consider the same. Therefore, the petition has been filed. By way of an amendment in the writ petition with further relief to quash the Notice Inviting Tender dated 11.08.2021 with respect to package MP 44707.
4. Per contra, learned counsel appearing for the respondents by filing reply has denied all the averments and has contended that in terms of Section 3 of PMGSY, which talks about qualification, information and clause 1.3.3. of Section 3 regarding information required to be submitted by the bidder on Bid Capacity (works for which bids have been submitted and works which are yet to be completed) as on the date of applying for NIT. Clause 8 of the NIT deals with the disqualification which says that even if the bidder qualified the criteria but has mislead or given a false representation in forms, statements, affidavits and attachments submitted in the proof of the qualification requirements, he is always subjected to disqualification. The security of bidder will also to be forfeited. It is submitted that the cogent reading of clause 15, clause 1.3.3. of Section 3 and 8 makes it clear that the bidder while submitting the bid has to submit the details of the existing commitment and ongoing works, failing which or suppressing the same, he is always liable for disqualification. Merely, putting up information on subsequent dates does not fulfill the requirements of the NIT. The authorities have refused to accept the bid of the petitioner owing to the suppression made by him with respect to existing commitment and ongoing work. He has prayed for dismissal of the writ petition.
5. Heard the learned counsel for the parties and perused the record.
6. Admittedly, in pursuance to the advertisement inviting tender, the petitioner participated in the same for six packages. It is not disputed that in terms of contract, he was required to submit the bid capacity and details
regarding ongoing work undertaken by him. The aforesaid information was not submitted by the petitioner at the time of applying the bid. Clause 1.3.3. is relevant, which reads as under:-
"Clause 1.3.3. - The bidder has to submit the information on Bid Capacity (works for which bids have been submitted and works which are yet to be completed) as on the date of the bid."
7. The aforesaid information was not submitted by the petitioner at the relevant time. Subsequently, the same was placed before the authorities. But the fact remains that it was required to be submitted at the time of submission of the bid documents. Section 8 deals with disqualification, which reads as under:-
"Section 8 - Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have made misleading or false representation in the forms, statements, affidavits and attachments submitted in proof of the qualification requirements. In addition to disqualification Bid Security of bidder will also be forfeited."
8. From the aforesaid, it is clear that in case of any suppression of material information the candidate is always liable for disqualification. It is not in dispute that the information as required in terms of Clause 1.3.3. was not furnished by the petitioner.
9. Being a matter relating to the contract, the terms and conditions in the NIT are required to be fulfilled at the time of furnishing of bid documents. The assessment is to be made by considering these documents, which is being done by the committee of expert. Such decision taken by the committee of expert cannot be interfered while exercising jurisdiction under article 226 of the Constitution of India, which amounts to virtually exercising power of a judicial review. The aforesaid aspect was considered in the case of Sunflag Iron and Steel Co. Ltd. vs. State of M.P. (2019) 1 MPLJ 689.
10. The Hon'ble Supreme Court in the case of Master Marine Service (P) Ltd. Vs. Metcalfe & Hodgkinson (P) Ltd. (2005) 6 SCC 138 has held that while exercising the power of judicial review in respect of contracts, the Court should concern itself primarily with the question, as to whether there has been any infirmity in the decision making process. By way of a judicial review, Court cannot examine details of the terms of contract, which have been entered into by the public body of the State.
11. In view of the aforesaid judgments, it is only required to see that whether the process adopted by the authorities is just and proper while dealing with the case of the petitioner. It is not disputed that at the time of submitting the bid documents, necessary information as required in terms of Clause 1.3.3. of the NIT was not furnished by the petitioner. Hence, no illegality is committed by the technical experts in rejecting the bid of the petitioner. Furnishing of information subsequently is of no help to the petitioner. In such circumstances, no relief can be extended to the petitioner.
12. This writ petition sans merit and is accordingly dismissed. No order as to costs.
(RAVI MALIMATH) (VISHAL MISHRA)
CHIEF JUSTICE JUDGE
Irf.
Digitally signed by MOHD
IRFAN SIDDIQUI
Date: 2022.09.24 11:22:57
+05'30'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!