Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mascom Steel (India) Pvt. Ltd vs The Assistant Engineer
2025 Latest Caselaw 7281 Ker

Citation : 2025 Latest Caselaw 7281 Ker
Judgement Date : 27 June, 2025

Kerala High Court

Mascom Steel (India) Pvt. Ltd vs The Assistant Engineer on 27 June, 2025

Author: A.K.Jayasankaran Nambiar
Bench: A.K.Jayasankaran Nambiar
                                                          2025:KER:46266

              IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                PRESENT

        THE HONOURABLE DR. JUSTICE A.K.JAYASANKARAN NAMBIAR

                                   &

                THE HONOURABLE MR. JUSTICE P.M.MANOJ

        FRIDAY, THE 27TH DAY OF JUNE 2025/6TH ASHADHA, 1947

                           W.A.NO.833 OF 2024
    AGAINST THE JUDGMENT DATED 20.05.2024 IN W.P(C).NO.29139 OF 2023
                         OF HIGH COURT OF KERALA

APPELLANT(S)/PETITIONER:

           MASCOM STEEL (INDIA) PVT. LTD,
           ERUMATHALA P.O., V-713, NEAR IDA, ALUVA,
           ERNAKULAM DISTRICT, KERALA, REPRESENTED
           BY ITS MANAGING DIRECTOR SRI.GEORGE ANTONY,
           PIN - 683112

           BY ADV.SRI.N.JAMES KOSHY
           BY ADV.SRI.ALEX ABRAHAM


RESPONDENT(S)/RESPONDENT:

    1      THE ASSISTANT ENGINEER,
           KERALA STATE ELECTRICITY BOARD LTD.,
           EDATHALA SECTION, ALUVA, ERNAKULAM DISTRICT,
           PIN - 683563

    2      THE DEPUTY CHIEF ENGINEER,
           KERALA STATE ELECTRICITY BOARD LTD., PERUMBAVOOR,
           ERNAKULAM DISTRICT, PIN - 683542

    3      THE SPECIAL OFFICER (REVENUE),
           KERALA STATE ELECTRICITY BOARD LTD.,
           VYDYUTHI BHAVANAM, PATTOM PLACE P.O.,
           THIRUVANANTHAPURAM, PIN - 695004

    4      KERALA STATE ELECTRICITY BOARD LTD,
           VYDYUTHI BHAVANAM, PATTOM PLACE P.O.,
           THIRUVANANTHAPURAM, REPRESENTED BY ITS CHAIRMAN
           AND MANAGING DIRECTOR, PIN - 695004
 W.A.No.833/2024                       :: 2 ::



                                                            2025:KER:46266

   5              THE CHIEF ELECTRICAL INSPECTOR,
                  GOVERNMENT OF KERALA, OFFICE OF THE CHIEF ELECTRICAL
                  INSPECTOR, HOUSING BOARD BUILDING, SANTHI NAGAR,
                  THIRUVANANTHAPURAM, PIN - 695001

   6              THE ASSISTANT EXECUTIVE ENGINEER,
                  KERALA STATE ELECTRICITY BOARD LTD., ELECTRICAL
                  SUB DIVISION, KIZHAKKAMBALAM, ERNAKULAM DISTRICT,
                  PIN - 683562

                  BY SRI.B. PREMOD, STANDING COUNSEL


       THIS WRIT APPEAL HAVING BEEN FINALLY HEARD ON
 26.06.2025, THE COURT ON 27.06.2025 DELIVERED THE FOLLOWING:
 W.A.No.833/2024                           :: 3 ::



                                                                   2025:KER:46266




                                   JUDGMENT

Dr. A.K. Jayasankaran Nambiar, J.

The writ petitioner in W.P(C).No.29139 of 2023 is the appellant

before us aggrieved by the judgment dated 20.05.2024 of a learned

Single Judge dismissing its writ petition.

2. The brief facts necessary for a disposal of this writ appeal

are as follows:

The appellant is a private limited company having its registered

office at Erumathala P.O., Aluva, Ernakulam District. It is engaged in the

manufacture of steel bars of different sizes. In connection with its

manufacturing activities, it is also registered as a consumer of electricity

with the Kerala State Electricity Board Limited [KSEBL] which is the

licensee under the Electricity Act in the area where the appellant

functions. While the energy requirements of the appellant company were

of limited nature upto 2017, in that year, the appellant decided to

upgrade its manufacturing activities, and towards that end applied for an

enhancement of its contracted load from 1000 KVA to 2500 KVA with

immediate effect. The application dated 06.01.2018 filed by the

appellant, which is produced as Annexure R1(a) by the respondent Board, W.A.No.833/2024 :: 4 ::

2025:KER:46266

reveals that the engineers of the electrical section of the licensee had,

while recommending the case of the appellant for sanction, also indicated

that in as much as some of the work in connection with the 66 KV lines

would be 'time consuming', the consumer could be 'provided the load

temporarily' by using the existing 11 KV line. The administrative

sanction for the work was accorded by Ext.P5 communication dated

12.04.2018, and the appellant was asked to remit Rs.21,02,500/- towards

costs for the works to be undertaken. The appellant accordingly remitted

the said amount and thereafter, the work on upgradation of the

transformer and installation of other equipment in the premises of the

appellant was approved by the Electrical Inspectorate which issued

Ext.P9 letter dated 22.05.2018 sanctioning the energisation of the

transformer, and connected electrical equipment's in the premises. The

annexure to Ext.P9 letter suggests that the connected load that was

approved by the electrical inspectorate was 2500 KVA. These facts are

also borne out by Ext.P10 communication dated 23.05.2018 of the Asst.

Engineer, KSEBL to the Asst. Executive Engineer wherein he seeks a

direction from the latter for permitting the appellant to connect the load

to the 'newly installed 2500 KVA transformer through the existing

metering system'. It is therefore clear that by June 2018, the appellant

had applied for and obtained the necessary sanction for the use of a

connected load upto 2500 KVA through an upgraded transformer that

was equipped to handle the said load.

3. When the appellant thereafter raised a complaint with the W.A.No.833/2024 :: 5 ::

2025:KER:46266

Minister for Electricity as regards the delay in execution of the remaining

works for which payment had been made, the KSEBL vide Ext.P13 letter

dated 01.11.2018 informed the appellant that an NOC from the

Panchayath was required in order to grant additional power supply since

the Panchayat had informed them that it had taken a decision to refuse a

licence to the appellant. The appellant therefore challenged the decision

taken by the Panchayat before the Tribunal for Local Self Government

Institutions, and by its order dated 29.11.2018 the tribunal found the

decision of the Panchayat to be legally unsustainable. Immediately

thereafter, the KSEBL vide its letter dated 07.12.2018 [Ext.P17]

approached the Additional District Magistrate to seek permission to draw

dedicated AB Cables through an alternate path, than the one originally

proposed, taking note of disputes that had been raised by some persons

in the locality. In the said letter, the KSEBL also acknowledges that it had

received a payment of Rs.21,02,500/- from the appellant for drawing the

dedicated ABC feeder. The ADM granted permission to KSEBL vide

Ext.P18 order dated 15.01.2019. The appellant thereafter paid the

energisation charges for the enhanced load and its unit was energised

with the enhanced contract demand on 09.04.2019.

4. It is the case of the appellant that, while the excess

contracted load to the unit had been duly sanctioned, and the unit with

the enhanced load and upgraded transformer, was energised on

09.04.2019, the only work that remained to be completed was the

drawing of the dedicated ABC feeder. Pending this, however, for over 48 W.A.No.833/2024 :: 6 ::

2025:KER:46266

months from 09.05.2019 to 17.05.2023, the appellant was served with

bills for energy charges that clearly showed that whenever the appellant

exceeded the contract demand [that was still shown as 1000 KVA], it was

billed for the maximum demand, over and above the contracted demand,

at 1.5 times the normal rate. Some of the sample bills raised on the

appellant during the aforesaid period were produced as Exts.P20 to P31

in the writ petition. While so, the Anti Power Theft Squad of KSEBL

visited the premises of the appellant on 15.07.2023 and found that the

connected load in the appellant's premises was 3570.200 KW while its

originally sanctioned contract demand and connected load were 1000

KVA and 792.15 KW respectively. A provisional assessment order was

therefore issued to the appellant proposing to treat 2778 KW [3570 -

792] as Unauthorised Connected Load and demand a differential amount

to the tune of Rs.4,18,21,242/- from it towards energy charges. Although

the appellant preferred its objections to the said proposal, the same was

confirmed by Ext.P36 final order dated 09.08.2023. It was the said final

order that was impugned by the appellant in the writ petition

aforementioned.

5. The learned Single Judge who considered the writ petition

found that the issue raised by the appellant in the writ petition required

an adjudication on facts and hence the appellant had to be relegated to

the statutory remedy of filing an appeal against Ext.P36 order before the

appellate authority. The writ petition was accordingly dismissed without

interfering with the impugned order.

 W.A.No.833/2024                           :: 7 ::



                                                                   2025:KER:46266




6. In the appeal before us, it is the submission of Sri.James

Koshy, the learned counsel for the appellant, that the learned Single

Judge ought not to have relegated the appellant to its alternate remedy

under the statute because pursuing that alternate remedy was not

efficacious for the appellant. This was because it had to remit 50% of the

confirmed demand, amounting to approximately Rs.2 Crore, as a

precondition for maintaining the appeal before the appellate authority. It

is his further submission, on merits, that the finding of the assessing

officer, based on the mahasar drawn up by the APTS, that there was an

excess connected load of 2778 KW in the premises, ignores the fact that

the authorised connected load of the appellant was 2500 KW, and not 792

KW as alleged. Pointing to Regulation 101 of the Supply Code, he

contends that since the KSEBL knew from 2019 onwards that the

maximum demand availed by the appellant was in excess of its contracted

load, as they had billed the excess load at 1.5 times the normal rate, it

was obliged in terms of the Regulation to issue a notice of thirty days to

the appellant requiring it to submit within the notice period, an

application for enhancement of the contract demand. KSEBL apparently

did not resort to the said procedure because it was aware that the

appellant had been sanctioned an additional contract load of 1500 KVA

over and above the originally sanctioned 1000 KVA. That being the case,

the KSEBL could not have found that there was an unauthorised

connected load of 2778 KW at the appellant's premises on the date of

inspection.

 W.A.No.833/2024                          :: 8 ::



                                                                  2025:KER:46266




7. Per contra, it is the submission of Sri.Premod, the learned

Standing Counsel for the KSEBL that the impugned judgment of the

learned Single Judge does not require to be interfered with. He points

out that the appellant has an effective alternate remedy under the

Statute and in so far as an adjudication on facts is warranted, the writ

court rightly chose not to interfere with the final order passed against the

appellant in the writ proceedings. Alternatively, he contends that the

additional contract demand of 1500KVA was never sanctioned to the

appellant, nor did the appellant apply for a regularisation of the

additional connected load at any point in time before the visit of the APTS

to its premises. As the entire work with regard to the sanction of

additional contract demand to the appellant was not completed, the

appellant could not have obtained a service connection in respect of the

enhanced contract demand.

8. We have considered the rival submissions and perused the

pleadings and the relevant statutory provisions. At the very outset, we

might observe that we find ourselves in disagreement with the approach

of the learned single judge in dismissing the writ petition solely on the

ground of existence of a statutory alternate remedy. While it is trite that

the exercise of power under Article 226 of the Constitution is entirely

discretionary, and that this court would not ordinarily entertain a writ

petition in circumstances where an effective adjudication on facts is

better undertaken before the statutory authorities entrusted with W.A.No.833/2024 :: 9 ::

2025:KER:46266

adjudicatory functions, the writ court must take note of the economic

hurdles placed in the way of the litigant while pursuing the statutory

alternate remedy. In the instant case, the learned single judge ought to

have considered, at least prima facie, the justification offered by the

KSEBL for the exorbitant demand made on the appellant. This was

required since the statutory provision for appeal is hedged in with a

condition that requires an appellant to remit 50% of the demand

confirmed against it as a condition for availing the appellate remedy. In

the event of a wholly unjustifiable and exorbitant demand being made

against a consumer, the statutory appellate remedy would be nothing but

a teasing illusion since not many consumers would be in a position to pay

the mandatory pre-deposit for maintaining an appeal. It is for this reason

that we have chosen to consider the merits of the appellant's case in this

writ appeal.

9. From the facts available before us, we find that there was

an application preferred by the appellant for enhancement of the contract

demand to 2500 KVA as early as on 06.01.2018 and that was acted upon

by the KSEBL to sanction the additional load and upgrade the

transformer for the purpose. The energisation of the unit with the

additional contract load also took place on 09.04.2019. Thus, a part of the

work of upgradation of the system, to facilitate the additional contract

load, was completed in 2019 itself and all that remained was for the

dedicated ABC feeder to be drawn and the formal application and

agreement for the additional service connection to be processed and W.A.No.833/2024 :: 10 ::

2025:KER:46266

sanctioned by the KSEBL. The endorsements made by the engineers of

KSEBL on Ext.R1(a) application dated 06.01.2018 clearly indicate that it

was understood by all concerned that the drawing of additional lines for

supplying the electricity at a higher load would take time and hence the

appellant could be permitted to avail the additional load 'temporarily' by

connecting the additional load to the 'newly installed 2500 KVA

transformer through the existing metering system'. Thereafter, for almost

48 months the KSEBL raised bills on the appellant clearly noticing a

maximum demand in excess of the original contracted load, and charging

it at 1.5 times the normal rate for such excess demand. It is significant

that at that stage, the KSEBL did not require the appellant to make an

application for an enhancement of the contract demand as mandated in

Regulation 101 of the Electricity Supply Code, presumably because it

already knew of the sanction of the additional load to the appellant by

then. KSEBL had also collected the charges [approximately Rs.22 Lakhs]

for carrying out the necessary works for the enhancement of the contract

load.

10. Against the backdrop of the above facts, we find it difficult

to accept the finding of the assessing officer in Ext.P36 order that on the

date of the inspection by the APTS, there was an unauthorised connected

load, to the extent of 2778 KW [3570 KW - 792 KW], at the appellant's

premises. In our view, the contracted load of the appellant had to be

taken as 2500 KVA and in that view of the matter, the 'unauthorised'

connected load could only have been 1070 KW [3570 KW - 2500 KW].

 W.A.No.833/2024                          :: 11 ::



                                                                2025:KER:46266

Since the contracted load had been enhanced to 2500 KVA in the

meanwhile, and the transformer had been upgraded to support that

higher load, increasing the connected load upto the limit of the enhanced

contracted load would not have caused any technical issues for the

licensee [KSEBL] so as to invoke the penal provisions under the

Electricity Act against the appellant. It follows that it is only in respect of

the above 1070 KW that the appellant can be seen as having resorted to

an 'unauthorised use of electricity', within the meaning of that phrase

under Explanation (b)(ii) to Section 126 of the Electricity Act.

11. We accordingly allow this appeal, by setting aside the

impugned judgment of the learned single judge and allowing the writ

petition by quashing Ext.P36 final order impugned therein. We remand

the matter to the assessing authority to recompute the demand against

the appellant herein after hearing it and by treating only 1070 KW as the

unauthorised connected load, and by computing the differential energy

charges payable by the appellant for a period of 12 months prior to the

date of inspection, on that basis. A fresh final order as above shall be

passed by the assessing officer within a period of one month from the

date of receipt of a copy of this judgment, and served on the appellant

shortly thereafter.

Taking note of the submission of the learned counsel for the

appellant that electricity supply to the premises has been disconnected

and if the connection is not restored, it will seriously prejudice the W.A.No.833/2024 :: 12 ::

2025:KER:46266

interests of the appellant as well as the workers in its unit who depend on

the functioning of the unit for their livelihood, we direct that on the

appellant paying the re-determined energy charges, on being intimated of

the same by the KSEBL, the respondents shall forthwith restore

electricity connection to the appellant's premises. The right of the

appellant to challenge the fresh final order on merits before the statutory

appellate authority, on all other issues, is also left open.

The Writ Appeal is allowed as above.

Sd/-

DR. A.K.JAYASANKARAN NAMBIAR JUDGE

Sd/-

                                                         P.M.MANOJ
                                                            JUDGE
prp/
   W.A.No.833/2024              :: 13 ::



                                                    2025:KER:46266







PETITIONER'S ANNEXURES: NIL.

RESPONDENT'S ANNEXURES:

ANNEXURE R1(a)       The true copy of the Power Allocation
                     Application   submitted   by   the   appellant
                     consumer on 05.01.2018 along with a covering
                     letter dated 03.01.2018
ANNEXURE R1(b)       The true copy of the letter addressed to the

Assistant Executive Engineer dated 06.03.2018 ANNEXURE R1(d) The true copy of the sanction for energisation issued to the consumer by the Chief Electrical Inspector on 22.05.2018 ANNEXURE R1 (f) The true copy of the letter dated 08.08.2019 issued by the Assistant Executive Engineer Kizhakkambalam ANNEXURE R1(g) The true copy of the communication issued by the Deputy Chief Engineer on 22.08.2023 ANNEXURE R1(e) True copy of the energisation approval issued by the Electrical Inspector on 08.04.2019 ANNEXURE R1(h) The true copy of the application submitted seeking enhancement of contract load on 08.09.2023 ANNEXURE R1(j) The true copy of the communication issued by the Deputy Chief Engineer on 28.12.2023 ANNEXURE R1(k) The true copy of the communication issued on 30.01.2024 ANNEXURE R1(c) The true copy of the power allocation sanction issued on 12.04.2018 ANNEXURE R1(i) The true copy of the communication issued on 30.09.2023 by the Deputy Chief Engineer ANNEXURE R1(l) The true copy of the communication issued by the Assistant Engineer, Electrical Section, Edathala DTD. 12.03.2024

//TRUE COPY//

P.S. TO JUDGE

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter