Friday, 17, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Olam Exports (India) Ltd vs Suma Mammen
2025 Latest Caselaw 785 Ker

Citation : 2025 Latest Caselaw 785 Ker
Judgement Date : 9 July, 2025

Kerala High Court

M/S.Olam Exports (India) Ltd vs Suma Mammen on 9 July, 2025

RFA 677/2008 & Cross Objection 21/2023



                                         1

                                                                2025:KER:50337

                  IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                         PRESENT

                THE HONOURABLE MR. JUSTICE C.PRATHEEP KUMAR

        WEDNESDAY, THE 9TH DAY OF JULY 2025 / 18TH ASHADHA, 1947

                                RFA NO. 677 OF 2008

            OS NO.364 OF 2002 OF ADDITIONAL SUBORDINATE COURT,KOLLAM


APPELLANT/DEFENDANT
           M/S.OLAM EXPORTS (INDIA) LTD.
           REGISTERED OFFICE AT BISHOP JEROM,, NAZAR NEW BLOCK,
           IVTH FLOOR,, KOLLAM 691001, REPRESENTED BY ITS DIRECTOR,
           MR. SANCHETI.

              BY ADVS.
              SRI.E.K.NANDAKUMAR (SR.)
              SHRI.ANIL D. NAIR (SR.)
              SHRI.BENNY P. THOMAS (SR.)
              SHRI.K.JOHN MATHAI
              SHRI.CHETHAN KRISHNA R.

RESPONDENTS/ADDL.PLAINTIFFS 2, 3 AND 4
     1     SUMA MAMMEN, W/O K.C.MAMMEN,, KANDATHIL HOUSE,, KARSHAKA
           ROAD, KOCHI 682016.
     2     K.M.JOSEPH, S/O K.C.MAMMEN, KANDATHIL HOUSE,, KARSHAKA
           ROAD, KOCHI 682016.
     3     RAVI PHILIP MAMMEN
           S/O K.C.MAMMEN, KANDATHIL HOUSE,, KARSHAKA ROAD,, KOCHI
           682016.
           BY ADVS.
           SRI.ENOCH DAVID SIMON JOEL
           SRI.S.SREEDEV
           SRI.RONY JOSE
           SMT.SUZANNE KURIAN
           SHRI.CIMIL CHERIAN KOTTALIL
           SHRI.LEO LUKOSE


       THIS    REGULAR     FIRST     APPEAL   HAVING   BEEN   FINALLY   HEARD   ON
25.6.2025, ALONG WITH CO.21/2023, THE COURT ON 9.7.2025 DELIVERED
THE FOLLOWING:
 RFA 677/2008 & Cross Objection 21/2023



                                         2

                                                         2025:KER:50337

                  IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                         PRESENT

                THE HONOURABLE MR. JUSTICE C.PRATHEEP KUMAR

          WEDNESDAY, THE 9TH DAY OF JULY 2025 / 18TH ASHADHA, 1947

                                  CO NO. 21 OF 2023

                     RFA NO.677 OF 2008 OF HIGH COURT OF KERALA


CROSS OBJECTORS/RESPONDENTS
     1     SUMA MAMMEN, AGED 66 YEARS
           W/O. K C MAMMEN, KANDATHIL HOUSE, KARSHAKA ROAD, KOCHI
           682 016.

      2       K M JOSEPH
              AGED 43 YEARS
              S/O. K C MAMMEN, KANDATHIL HOUSE, KARSHAKA ROAD, KOCHI
              682 016. REPRESENTED BY HIS MOTHER AND POWER OF ATTORNEY
              HOLDER MRS. SUMA MAMMEN.
      3       RAVI PHILIP MAMMEN
              AGED 39 YEARS
              S/O. K C MAMMEN, KANDATHIL HOUSE, KARSHAKA ROAD, KOCHI
              682 016. REPRESENTED BY HIS MOTHER AND POWER OF ATTORNEY
              HOLDER MRS. SUMA MAMMEN.
              BY ADVS.
              SRI.ENOCH DAVID SIMON JOEL
              SRI.S.SREEDEV
              SRI.RONY JOSE
              SHRI.LEO LUKOSE
              SHRI.CIMIL CHERIAN KOTTALIL


RESPONDENTS/APPELLANTS

              M/S OLAM EXPORTS (INDIA) LTD., REGISTERED OFFICE AT
              BISHOP JEROM, NAZAR NEW BLOCK, IVTH FLOOR, KOLLAM 691
              001., REPRESENTED BY ITS DIRECTOR Mr.SANCHETI

              SRI.CHETHAN KRISHNA R.

       THIS CROSS OBJECTION/CROSS APPEAL HAVING BEEN FINALLY HEARD ON
25.6.2025, ALONG WITH RFA.677/2008, THE COURT ON 9.7.2025 DELIVERED
THE FOLLOWING:
 RFA 677/2008 & Cross Objection 21/2023



                                          3

                                                                      2025:KER:50337

                                         JUDGMENT

Dated : 9th July, 2025

This appeal has been preferred by the defendant in O.S.364/2002 on the file of

the Subordinate Judge's Court, Kollam. The plaintiff is the cross-objector. (For the

purpose of convenience, the parties are referred to as per their rank before the trial).

2. The plaintiff filed the suit for realisation of money due as per an

agreement by which he had undertaken the work of furnishing and interior decoration

of the office of the defendant at Kollam. As per the work order dated 26.8.1998, the

plaintiff had undertaken the furnishing and interior work of the defendant's office for

a total sum of Rs.45,45,931.60. The plaintiff completed the work on 16.2.1999 and

inauguration of the office of the defendant was held on 17.2.1999. During the course

of the work, the plaintiff received a sum of Rs.9,00,000/- on September 1998,

Rs.14,00,000/- during November 1998 and another Rs.10,00,000/- during February

1999. The plaintiff thus received a total sum of Rs.33,00,000/-. The defendant

entrusted the work to the plaintiff through the defendant's consultant M/s. Kumar

Group Total Designers, Kochi. Accordingly the plaintiff had presented final bill for

Rs.48,18,540.90 before M/s.Kumar Group after the completion of the work. From the

said bill amount, 10% was discounted as agreed in the contract. Though the final bill

was submitted before the defendant, the balance amount was not paid to the plaintiff.

As per the terms of the contract, the final bill was liable to be settled within three

months after certification of the bill by M/s.Kumar Group Total Designers. In addition RFA 677/2008 & Cross Objection 21/2023

2025:KER:50337

to the same, the plaintiff has deposited earnest money of Rs.25,000/- also with the

defendant. Therefore, the plaintiff filed the suit demanding balance amount as well as

interest at the rate of 18% amounting to Rs.15,82,823.90.

3. The defendant filed written statement admitting the entrustment of the

work with the plaintiff. According to the defendant, as per the terms of the contract,

the plaintiff had to complete the work within a period of 60 days from the date of

issuance of the work order. As per the contract, in case of delay in executing the work

the defendant is entitled to realize pre-liquidated damages at the rate of 1% of the

tendered cost of the work per week subject to a maximum of 10% of the total contract

value. Time was essence of the contract entered into with the plaintiff. Though the

period stipulated in the contract was only 60 days, the plaintiff took about six months

to complete the work. Because of the delay in completing the work, the defendants

sustained huge loss to the tune of Rs.11,44,000/- The claim of final bill was raised

without any basis. Therefore, according to the defendant, the plaintiff is not entitled to

realise the amount claimed in the plaint.

4. In the light of the above pleadings, the trial court has framed four issues.

The evidence in the case consists of the oral testimony of PW1 and Exts.A1 to A13 on

the side of the plaintiff and on the side of the defendant DW1 was examined and

Exts.B1 to B8 were marked. After evaluating the evidence on record, the trial court

decreed the suit and permitted the plaintiff to realise a sum of Rs.15,82,823/- along

with interest at the rate of 12% per annum from the date of suit till the date of RFA 677/2008 & Cross Objection 21/2023

2025:KER:50337

judgment and at the rate of 6% per annum thereafter till realisation. Being aggrieved

by the above judgment and decree of the trial court the defendant preferred this

appeal. Now the points that arise for consideration are the following :

i) Whether the suit is barred by limitation ?

ii) Whether the impugned judgment and decree of the trial court calls for

any interference in the light of the grounds raised in the appeal ?

5. Heard Sri.Chethan Krishna R., the learned counsel for the

appellant/defendant and Sri.S.Sreedev, the learned counsel for the

respondents/plaintiffs.

6. Point No.(i) :- The defendant entrusted the interior and decoration work

of its office with the plaintiff through their consultant M/s.Kumar Group Total

Designers. Ext.A1 is the letter dated 10.8.1998 sent by the plaintiff to M/s.Kumar

Group for work and also for furnishing demand draft for Rs.25000/- being earnest

money deposit. Ext.A2 is the work order issued by the defendant to the plaintiff dated

26.8.1998. The total tendered amount was shown as Rs.45,44,931.60. Ext.A2 also

states that the said amount is subject to deducting the discounts offered during

negotiations. Clause 2.1 and 2.2 of Ext.A2 states that, tender in original and tendered

drawings and covering letter enclosing the tender sent, are part of Ext.A2 contract.

Clause 2.4 of Ext.A2 states that the entire work shall be carried out under the

supervision of the defendant's architects/interior design personnel who should be

consulted for commencement of work and for other technical clarifications required RFA 677/2008 & Cross Objection 21/2023

2025:KER:50337

regarding the work. Clause 3 of Ext.A2 states that this work order shall be treated as

commencement of the order for the execution of work and that the work shall be

completed within 60 days from the date of the order. Clause 4 states that, M/s.Kumar

Group Total designer, Architects shall be the consultants of the defendant for

Architectural/Design details as well as the site construction management. All the

technical correspondence on the project shall emanate from the consultant. It further

states that the contractors shall make replies to the consultants under advice to the

defendant. It further states that all policy decisions involving financial implications

shall be finalized by the defendant.

7. Though as per Ext.A2 the work is to be completed within a period of 60

days, the work could not be started in time and could not also be completed within the

above 60 days as stipulated. From the evidence available on record it is revealed that

there was default on the part of both the parties in the delayed commencement and

completion of the work. According to the learned counsel for the appellants, more

default was on the part of the plaintiffs and thereby it was the plaintiff who committed

breach of contract and as such in the light of the stipulations in Ext.A2, the plaintiff is

liable to pay penalty at the rate of 1% of the contract amount per week upto a

maximum of 10%. However in this case, no set-off or counter-claim is raised by the

defendants and as such, I do not find any merits in the argument advanced by the

learned counsel regarding realisation of any penalty from the plaintiff.

8. Ext.A3 is the letter dated 1.9.1998 issued by the plaintiff demanding a RFA 677/2008 & Cross Objection 21/2023

2025:KER:50337

sum of Rs.9,00,000/- and accordingly in September 1998, the defendant paid a sum of

Rs.9,00,000/-. Ext.A4 is the letter dated 14.11.1998 issued by the plaintiff demanding

a further sum of Rs.14,00,000/- and accordingly in November 1998, a sum of

Rs.14,00,000/- was disbursed to the plaintiff. Ext.A6 is the letter dated 16.1.1999

issued by the plaintiff demanding a further sum of Rs.10,00,000/- and accordingly, the

same was released by the defendant in February, 1999. Admittedly, no further amount

was paid by the defendant to the plaintiff. Ext.A8 is the final bill dated 26.10.1999

issued by the plaintiff to the defendant through M/s.Kumar Group.

9. As per the plaint, the completion of the work was on 16.2.1999 and

inauguration of the office of the defendant was held on 17.2.1999. Therefore relying

upon the terms in Ext.B8 tender, the learned counsel for the appellant would argue

that the plaintiff had to submit the final bill and file the suit within a period of three

years from the date of completion of the work on 16.2.1999. It was in the above

context that the learned counsel argued that the suit is barred by limitation. On the

other hand, relying upon Ext.B8 tender, the learned counsel for the

respondents/plaintiffs would argue that as per Clause10 of Annexure-I of Ext.B8

tender, the period of honouring bills is seven days from the date of certification of the

bill by the Architect. Therefore, it was argued that though the bill was presented

before the Architect M/s.Kumar Group, the final bill was certified by the Architect

only belatedly and that is why the suit happened to be filed in the year 2002.

Therefore, it was argued that the suit is filed within the period of limitation. RFA 677/2008 & Cross Objection 21/2023

2025:KER:50337

10. Relying upon the decisions of the Hon'ble Supreme Court in State of

Gujarat v. Kothari and Associates, 2016 (14) SCC 761, the learned counsel for the

appellants would argue that even though the prayer for limitation was not raised, it is

the duty of the Court to satisfy itself that the Suit is not barred by limitation. In

support of the above argument, he has relied upon the decision of Himachal Pradesh

Hugh Court in State of H.P. And Ors. v. Baldev and Ors., MANU/HP/0950/2015

also.

11. It is true that, even though the prayer for limitation was not raised, it is

the duty of the Court to satisfy itself that the Suit is not barred by limitation. As per

Ext.B8 tender, the liability of the defendant to honour the bill arose only within seven

days from the date of certification of the bill by the Architect. Though the virtual

completion of the construction was on 16.2.1999 and the inauguration was held on

17.2.1999, even thereafter some works were pending and it was completed only

subsequent to the inauguration. In Ext.A7 letter issued by the plaintiff on 11.9.1998, it

was informed to M/s.Kumar Group that though the plaintiff had deputed people on

8.9.1998 along with the representative of the consultant to do the necessary work, the

work could not be completed as about half the floor was waterlogged. Several other

matters to be done by the defendant was also narrated in the said letter and the said

letter reveals that, only if the above requirements were met, they could proceed with

the construction.

12. It is true that, as per Ext.B2 letter dated 3.3.1999 the defendant had RFA 677/2008 & Cross Objection 21/2023

2025:KER:50337

given an ultimatum to the plaintiff to complete the work by 7.3.1999. Exts.B2, B3, B4

and B5 are the correspondence between the plaintiff and defendant as well as

M/s.Kumar Group and from the above documents also it is revealed that the

construction of the work was not complete even by 3.3.1999. Ext.B4 is another letter

issued by the defendant to M/s.Kumar Group on 4.3.1999 in reply to Ext.B3 letter.

Ext.B6 is the final bill dated 26.10.1999 duly verified and recommended for payment

by M/s Kumar Group and given to the defendant. Ext.B7 is the letter dated 1.11.1999

issued by the defendant to M/s.Kumar Group objecting to Ext.B6 final bill. One of the

reasons stated in Ext.B7 is that M/s Kumar Group has not invoked the penalty clause

while approving the final bill. Therefore, from Ext.B6 final bill produced by the

defendant itself it is revealed that the consultant M/s.Kumar Group has certified the

final bill only on 26.10.1999. Since as per Ext.B8 tender the final bill is to be certified

by the architect namely the consultant of the defendant and it was done by the

consultant only on 26.10.1999, the suit filed on 1.10.2002 is well within the period of

three years from 26.10.1999. In other words, the suit is not barred by limitation as

argued by the learned counsel or the appellant. Point No.1 is answered accordingly.

13. Point No.2:- Since as per Ext.B6 final bill approved by M/s.Kumar

Group the plaintiff is entitled to get a total sum of 42,93,278.90 and only

Rs.33,00,000/- was paid in advance, towards the balance amount due as per the final

bill, the plaintiff is entitled to get a sum of Rs.9,93,278.91 rounded to Rs.9,93,279/-.

Further, the plaintiff claimed a sum of Rs.25000/- being the earnest money deposited RFA 677/2008 & Cross Objection 21/2023

2025:KER:50337

by him. Since the plaintiff has deposited Rs.25000/- as earnest money deposit along

with Ext.A1, he is entitled to get back Rs.25000/- also. Therefore, the total amount

due to the plaintiff will come to Rs.1018279/-(993279+25000). Along with the said

amount, the plaintiff has claimed interest at the rate of 18% per annum. The learned

counsel for the appellant relying upon Ext.B8 tender, would argue that as per Ext.B8,

the plaintiff is not entitled to get any interest for the delayed payment. In this context

it is to be noted that the plaintiff has completed the work and final bill was presented

before the consultant of the defendant and the consultant has approved the final bill as

early as on 26.10.1999. Since without assigning any valid reasons the defendant

refused to pay the balance amount, the plaintiff is entitled to get reasonable rate of

interest for the said amount from 26.10.1999 till the date of realization. The judgment

of the trial court to the extent it limited the rate of interest at 6% per annum from the

date of the judgment till payment was challenged by the plaintiffs in the Cross-

objection.

14. Relying upon the decision of a learned Single Judge of this Court in

State Bank of Travancore and Ors v. M.A.Beegum, MANU/KE/5901/2019, the

learned counsel would argue that in the case of arrears of rent, this Court has awarded

interest only at the rate of 6% per annum.

15. On the other hand, the learned counsel for the respondents/plaintiffs

relying upon the decision of a Division Bench of this Court in Indian Overseas Bank

v. Electro Accoustics Private Limited, MANU/KE/1153/2012 would argue that in a RFA 677/2008 & Cross Objection 21/2023

2025:KER:50337

suit for realization of money, the Division Bench held that interest awarded by the

trial court at the rate of 12 % is reasonable. He has also relied upon anther Division

Bench decision of this Court in Rosy George v. State Bank of India , 1993 KHC 33,

in a Suit for money filed by Bank in which it was held that future interest awarded at

the rate of 14% which is the minimum rate of interest charged by the Bank, was

reasonable.

16. In this context it is to be noted that the decisions relied upon by the

learned counsel for the plaintiff are suits filed by Banks and their object is to earn a

return and make profit by doing business in money transactions. In the decision in

State Bank of Travancore (supra), cited by the learned counsel for the appellant, the

Suit relates to non payment of rent to the landlord. In the instant case, the plaintiff has

undertaken the work of interior and furnishing of the office of the defendant. In the

above circumstances, considering the entire facts, I hold that interest at the rate of 9%

per annum will be a reasonable rate of interest in this case. Point answered

accordingly.

17. In the result, this appeal and Cross-objection are disposed of limiting the

amount to be paid under the decree to Rs.1018279/- along with interest at the rate of

9% per annum from 26.10.1999 till the date of the decree and at the same rate

thereafter till realization with proportionate costs.

Sd/-

C.Pratheep Kumar, Judge

Mrcs/27.6.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter