Friday, 17, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

R.Mohandas vs State Of Kerala
2025 Latest Caselaw 1547 Ker

Citation : 2025 Latest Caselaw 1547 Ker
Judgement Date : 25 July, 2025

Kerala High Court

R.Mohandas vs State Of Kerala on 25 July, 2025

RFA No.668/2004




                                 1
                                                2025:KER:55008

              IN THE HIGH COURT OF KERALA AT ERNAKULAM

                              PRESENT

            THE HONOURABLE MR. JUSTICE C.PRATHEEP KUMAR

     FRIDAY, THE 25TH DAY OF JULY 2025 / 3RD SRAVANA, 1947

                        RFA NO. 668 OF 2004

         AGAINST THE JUDGMENT AND DECREE DATED 30.06.2003 IN OS
NO.1282 OF 1995 OF PRINCIPAL SUB COURT, THIRUVANANTHAPURAM

APPELLANT/PLAINTIFF:

             R.MOHANDAS
             S/O. K.N. RAGHAVAN, AGED 39,
             RESIDING AT SANTHINIKETH,
             CHIRACKAL P.O., KANNUR.

             BY ADVS.
             SHRI.AJITH KRISHNAN
             SHRI.T.R. RAJASEKHARAN NAIR


RESPONDENTS/DEFENDANTS:

     1       STATE OF KERALA, REPRESENTED BY THE CHIEF
             SECRETARY, GOVT. SECRETARIAT, THIRUVANANTHAPURAM.

     2       THE SUPERINTENDING ENGINEER
             IRRIGATION SOUTH CIRCLE, THIRUVANANTHAPURAM.


             BY ADVS.
             GOVERNMENT PLEADER SRI.JIBU.T.S.


       THIS REGULAR FIRST APPEAL HAVING BEEN FINALLY HEARD ON
15.07.2025, THE COURT ON 25.07.2025 DELIVERED THE FOLLOWING:
 RFA No.668/2004




                                     2
                                                     2025:KER:55008


                            JUDGMENT

Dated this the 25th day of July, 2025

The plaintiff in OS No.1282/1995 on the file of the Principal Sub

Court, Thiruvananthapuram is the appellant. (For the purpose of

convenience, the parties are referred to as per their rank before the trial

court.)

2. The plaintiff filed the suit for realisation of money. The

plaintiff was a contractor by profession. In response to notice inviting

tenders by the defendant for the work of Anti Sea Erosion (ASE) for the

construction of seawall for a length of 500 metres between BLS 17 and

22 at Poonthura during May 1992, the plaintiff quoted 54% above the

estimated rate of 1990 Schedule of rates and the above work was

allotted to the plaintiff by tender committee in its meeting held on

4.8.1992. Sanction for the said work was accorded by the Government

as per order dated 26.9.1992 for a sum of Rs.30.5 lakhs and the same

was accepted by the defendant. As per the selection notice, work was to

be completed within 12 months from the date of handing over the site.

2025:KER:55008

The site was handed over to the plaintiff on 10.2.1992 and the time for

completion of the work was extended till 31.5.1994 and the plaintiff

completed the said work within the extended period.

3. According to the plaintiff, for the completion of the above

work, granite stones of 200 dm3 , 45 dm3, 20 to 40 dm3 and soling stones

were required and as per the contract the plaintiff' has to bring such

stones from the departmental quarry at Vattappara. The estimate was

prepared including conveyance for transporting granite from Vattappara

to the work site at Poonthura, which situates at a distance of 9 km from

the work site. The plaintiff quoted the rate on the assumption that

granite will be available from the Vattappara Quarry. In the meantime,

the Government assigned similar works at other places also and other

contractors were also to collect granite from the said quarry.

Accordingly, the plaintiff could secure only a small portion of the

granite from the Vattappara quarry. Since he could not procure adequate

quantity of stones from Vattappara, consequential non-availability of the

same was notified to the authorities concerned. Finding the impossibility

2025:KER:55008

of obtaining the required quantity of granite from Vattappara quarry, the

departmental authorities directed the plaintiff to collect stones required

for the work from other sources and to complete the work within the

stipulated time. Accordingly, the plaintiff brought granite from a quarry

at Parippally about 50 km away from the work site. For bringing the

granite from the Parippally quarry, the plaintiff had to spend an extra

amount for conveyance and the present suit has been preferred claiming

a total sum of Rs.52,46,652/- being the additional conveyance expenses

and seigniorage.

4. The defendant filed a written statement disputing the claim

raised by the plaintiff. According to them, enough granite was available

in Vattappara quarry and it was the duty of the plaintiff to employ

sufficient number of workers for quarrying operation and for collecting

sufficient material for the work, since as per the contract, it is the duty

of the contractor to bring the required granite from the places of his

choice. The department is not liable to pay any additional amount in

that respect. In the written statement, the defendant denied the

2025:KER:55008

allegation that sufficient quantity of granite was not available at

Vattappara quarry. According to them, it was the duty of the plaintiff to

extract sufficient quantity of granite from the Vattappara quarry. No

complaint was raised regarding the non-availability of required material

from the Vattappa quarry, either by the plaintiff or any other contractor,

who were also extracting the material from the same quarry during the

same period. It is also contended that during the same period, other

contractors have carried out similar ASE works extracting materials

from the Vattappara quarry and completed the works in time. The other

contractors have not made any complaint regarding non-availability of

required materials from that quarry. Vattappara quarry is large enough

to provide sufficient material for the work. None of the departmental

officials have given any direction to the plaintiff to obtain material from

any other quarry. If the plaintiff has procured any quantity of stones

from any other source, it is for his own convenience. Since the

department has assigned a quarry to collect the materials and the same is

incorporated in the agreement, the plaintiff is bound to collect the

materials only from that quarry. It is also contended that the plaintiff had

2025:KER:55008

collected the entire quantity of materials from Vattappara quarry. It is

also contended that the plaintiff received the amount for the above work

without raising any objection and as such he is estopped from raising

further claims in that respect. The plaintiff has not sustained any loss in

that respect. In the light of the above contentions, the defendant prayed

for dismissing the suit.

5. The trial court raised four issues. The evidence in the case

consists of oral testimonies of PW1 to 4 and DW1 and Exhibits A1 to

A21, B1 to B7 and C1 series. After evaluating the evidence on record,

the trial court dismissed the suit. Being aggrieved by the above

judgment and decree of the trial court, the plaintiff preferred this appeal

raising various grounds.

6. Now, the point that arises for consideration is the following:

Whether the impugned judgment and decree of the trial court dismissing the suit calls for any interference in the light of the grounds raised in the appeal?

7. Heard Sri. Ajith Krishnan, the learned counsel for the appellant

2025:KER:55008

and Sri. Jibu T.S., the learned Government Pleader.

8. The point: The plaintiff is a contractor, who had undertaken the

work of construction of seawall for a length of 500 metre between BLS

17 and 22 at Poonthura. The accepted estimated was Rs.40,20,068/-,

which was 54% above the estimate rate. The period of completion was

12 months and it was subsequently extended to 31.5.1994. Admittedly,

the plaintiff completed the construction within the extended period of

31.5.1994, to the satisfaction of the department.

9. As per the agreement entered into between the parties

(Exhibit B1), the work consists of supplying and dumping of armour

stones of 200 dm3, 45 dm3, 20 to 40 dm3 and soling stones and formation

of sea wall. Further, the stones were to be extracted by the contractor

from the government quarry at Vattappara which situates 9 km away

from the work site. The case of the plaintiff is that when the contract

was given to him, he alone was there to extract granite from the

Vattappara quarry and initially he engaged 12 labourers for that purpose.

Further according to him, thereafter the department has allotted other

2025:KER:55008

similar works to other contractors and to such contractors also the same

quarry at Vattappara was allotted and as such there was non-availability

of sufficient quarry at Vattappara. Therefore, according to the plaintiff,

with the consent of the departmental officials, he procured granite from

a distant quarry at Parippally, for which he had to spend additional

amounts for extra conveyance and as such he is entitled to get the

amount claimed in the plaint.

10. The contention taken by the defendant is that the quarry at

Vattappara was large enough to supply sufficient quantities of granite for

the work and that it is the duty of the contractor to employ sufficient

number of workers to extract sufficient quantities of granite from the

allotted quarry. They further contended that in similar works undertaken

by other contractors, they have collected sufficient quantities of granite

from the same quarry and there was no similar complaint from anybody

else. It was also contended that, if the plaintiff for his own convenience

collected granite from another quarry, that too without the permission of

the defendant, they are not liable to pay any extra conveyance expense,

if any, incurred by the plaintiff.

2025:KER:55008

11. The plaintiff would contend that in connection with the

construction of another seawall, the Government was satisfied that he

had to collect granite from Parippally quarry and acknowledging the

same, extra conveyance charge was allotted to him. Ext.A2 is the said

Government Order, G.O.Rt. No.1065/93/Irrn. dated 30.9.1993. In

Ext.A2 it was stated that the High Level Committee considered the

representation given by the plaintiff and observed that there was

shortage of granite at Vattappara, that the plaintiff was forced to bring

materials from far off places to complete the work in time and therefore,

the committee suggested that it is justifiable to pay the conveyance

charges to the contractor as a very special case. It was in the above

context, the Government was pleased to accept the recommendation of

the High Level Committee to pay 60% of the allowable rate to the

contractor as conveyance charge, 'as a very special case'.

12. The learned Government Pleader invited my attention to the

fact that it was an emergent case in which, restoration of damaged

seawall at Panathurakkara for a length of 610 metres between BLS 212

and 218 was to be made in a war-footing and it was in the above

2025:KER:55008

circumstance, it was considered as "a very special case" by the

Government. The said fact is evident from Ext.A2 itself. It is also

revealed from Ext.A2 that it was on the basis of the recommendation of

the High Level Committee the government had issued such an order. In

the instant case there was no such special circumstance and as such the

above Government Order cannot be applied as a precedent in the instant

case.

13. The learned counsel for the appellant has invited my

attention to another work undertaken by the same plaintiff involving a

similar construction in which the Principal Sub Court,

Thiruvananthapuram in OS No.538/1995 awarded a sum of

Rs.19,49,780/- towards extra conveyance. In appeal this court in RFA

No.373/2003 enhanced the compensation to Rs.35,52,833/- along with

interest @6% per annum. Since the above decision in O.S. No.538/1995

is with respect to the construction of a seawall, on the basis of another

contract with the same department, the said decision cannot be relied

upon in the present case.

2025:KER:55008

14. The learned Government Pleader relying upon Exhibit B1

contract would argue that, as per the terms of the contract, the contractor

cannot claim any additional amount except for any extra work entrusted

to him and according to him, since in the instant case, no extra work was

allotted, the plaintiff is not entitled to claim any additional amount. It is

true that as per the terms of Ext.B1 contract, the contractor is not entitled

to claim any additional amount, except for any extra work entrusted to

him. In the instant case the amount claimed by the plaintiff cannot be

styled as extra work entrusted by the defendant and as such the plaintiff

cannot claim any additional amount on that head.

15. The learned counsel for the plaintiff has extensively relied

upon the Exhibit C1 commission report prepared by the expert

commissioner (PW2) in support of the plaint claim. In Exhibit C1

report, the Commissioner noted that when he visited the department

quarry at Vattappara, the area allotted to the plaintiff was seen in an

abandoned stage, without any blasting of quarry, in the near future. In

this context it is to be noted that he visited the quarry in 2000, while the

seawall construction was completed in 1992-94. At the time of

2025:KER:55008

evidence, it is revealed that the said quarry has an area of 4.5 acres and

even according to the plaintiff, the area allotted to him has an extent of

1.5 acres. The Commissioner reported that, from the other portions of

the same quarry, in the possession of private parties, blasting and

operations were going on, even in the year 2000.

16. From the evidence on record it is revealed that the granite

available in Vattappara is very hard and is of good quality and hence

difficult to cut into pieces while that at Parippally is soft and easy to cut

into pieces. In Ext.C1 commission report the commissioner specifically

noted the nature and quality of the rock available in Vattappara quarry,

in page 6 as follows:

"The commission had also noted that the texture and type of rock available in Vattappara quarry comes under very hard blue granite type of stone with close grains and this type of stones is difficult to break into the required size and shape of amour tones with dimensions 90 x 50 x 45Cm, Thus the out- turn of amour stones of the above size that can be produced from the blasted boulders at this quarry site will be less when compared to other type granite stones which can be cut into the required size easily."

2025:KER:55008

17. With regard to the quality of the rock available at Parippally,

in page 7, the Commissioner noted that:

"The texture and type of rock in this quarry is different from that found in Vattappara quarry and it is seen that the rock is easy to be cut into the required sizes."

18. From the above report, it is evident that the rock available in

Vattappara quarry is very hard, granite type of stone, which requires more

labour for breaking into required size, while the quality of the rock available

at Parippally is easy to cut into required size. Therefore, even from Ext.C1

report it is revealed that enough granite was available at Vattappara, both in

the area allotted to the plaintiff as well as in the nearby private quarries. In the

above circumstance, if the plaintiff proceeded to Parippally, without

exhausting the quarries available at Vattappara, it can only because the rock

available there is light and less labour and expense was enough to cut them

into pieces of required size. In short, even if the plaintiff abandoned the

department quarry at Vattappara and proceeded to collect granite from other

quarries, it is for his own convenience, to reduce his expense and labour.

19. At the same time, in the same report, the Commissioner further

2025:KER:55008

stated that, in the meantime, certain other works were allotted to other

contractors, that those contractors also have to collect the materials from

Vattappara quarry and hence the plaintiff could use only a portion of the

Vattappara quarry, which reduced the availability of the stones. Even

according to PW1, about 1½ acres of quarry was allotted to him from

Vattappara quarry and he has no case that the above 1½ acres allotted to him

was allotted to anybody else. The above version in the commission report is

in tune with the case pleaded in the plaint. After reporting that when he

visited the department quarry at Vattappara, the area allotted to the plaintiff

was seen in an abandoned stage without any blasting in the near future and at

the same time, in the nearby private quarries blasting operations are going on,

such a finding arrived at by the commissioner is without any basis and

beyond the scope of his authority. Therefore, Ext.C1 report cannot be relied

upon to hold that sufficient granite was not available in the department quarry

and other private quarries at Vattappara.

20. From the evidence of the plaintiff as PW1, it is revealed that he

was engaged in similar work as a contractor for the past 15 years and he had

undertaken about 48 ASE works so far. During the cross examination, he

admitted that he was selected for the work involved in this case on 7.11.1992.

2025:KER:55008

When it was suggested that he had executed the agreement with the defendant

only after two months from the date of selection, he pleaded ignorance. From

the records it is revealed that he executed the agreement with the defendant

only on 8.1.1993. Admittedly, he could not complete the work within the

original period of one year and hence it was extended till 31.5.1994.

21. Admittedly, as per Ext.B1 agreement, the contractor had to

collect the required granite from the departmental quarry at Vattappara.

During the cross examination, he claimed that at Vattappara quarry,

initially he had engaged 12 labourers for quarrying operation. Though

according to the plaintiff, sufficient material was not available at

Vattappara quarry and that is why he started bringing stones from

Parippally quarry, there is no reliable evidence in that respect. At the

same time, as deposed by DW1, there was no prohibition for the

contractor to bring the material from anywhere he chooses, provided it is

of the required quality.

22. Similarly, though the plaintiff claimed that shortage of

granite at Vattappara was intimated to the officials of the defendant and

2025:KER:55008

that he started bringing stones from Parippally quarry with the

permission of the defendant, there is absolutely no evidence in that

respect. In the written statement the defendant specifically denied the

above claim made by the plaintiff. Though during the cross examination,

he claimed that there are documents issued by the defendant to prove

that he was authorised to bring the stones from Parippally quarry, he

could not produce any such documents.

23. Though the plaintiff produced Ext.A8 as the copy of the

letter issued to the defendant in that respect, there is no such pleading

and it was not produced along with the plaint. There is no evidence to

prove that Ext.A8 was served on the defendant and as such it could not

be relied upon. Exts.A11 to 21 produced by the plaintiff do not relate to

the work in question, but relate to some earlier works. Though in those

letters it is stated that due to labour problem sufficient quantity of

granite is not available, in this case he has no such case. Moreover, in

those letters there is no mention of the collection of granite from

Parippally quarry. Even if there was non-availability of sufficient granite

2025:KER:55008

at Vattappara quarry as claimed by the plaintiff, he was very much aware

of that fact, well before selection notice was issued to him on 7.11.1992,

agreement was executed on 8.1.1993 and he took charge of the site on

10.2.1993. It was in the above context he quoted 54% above the estimate

prepared for the work.

24. DW1, the Assistant Executive Engineer Irrigation North

subdivision deposed that the department officials have not received any

request from the plaintiff seeking permission to take stones from any

other quarry and that the officials have never certified the quality of the

stones from Parippally quarry or any other quarry. The specific case of

the defendant is that the plaintiff collected entire stones from Vattappara

itself and not from anywhere else. In order to prove non-availability in

Vattappara he examined PW3 and to prove supply of stones from

Parippally he examined PW4. Though PW3 claimed that the plaintiff

could not engage his own workers and that he himself engaged workers

and extracted stone and supplied them to plaintiff, the same is not

believable for more than one reason. Firstly because PW3 had no

2025:KER:55008

explosive license and secondly because PW1 admitted that initially he

himself engaged 12 labourers for blasting rock from Vattappara. PW4

spoke about supply of stones to the plaintiff in 1991, while the present

work was in 1992-94. He also could not state the name of the owner of

the quarry from where stones were supplied to the plaintiff. In the above

circumstance the trial court was justified in disbelieving PWs 3 and 4.

Though the commissioner (PW2) reported that the plaintiff brought

stones from Parippally, it was copied from the plaint and not from any

other reliable source and hence unreliable.

25. Except the oral testimonies of PWs 1,2 and 4 there is no

other evidence to prove that the plaintiff brought any granite from

Parippally for the work in question. Regarding the quantity of granite, if

any brought from quarries other than Vattappara also, there is no

evidence. I have already found that the evidence of PW4 is not reliable,

while PW2 has no direct knowledge in that respect. The plaintiff could

not produce even a scrap of paper to prove that he had purchased any

granite from any quarries other than Vattappara, for the work in

2025:KER:55008

question. In short, the plaintiff is claiming a huge amount from the

government department towards extra conveyance allowance, without

producing even a scrap paper from his side to prove any such

expenditure from his pocket.

26. At the time of evidence there was an attempt to show that a

sufficient number of private quarries were also not available near the

department quarry at Vattappara and that stones of the required size were

not available in those quarries. During the cross-examination PW1

deposed that he did not know the details of private quarries present near

the department quarry. As already noted, even in Ext.C1, PW2 reported

that when he visited Vattappara quarry in the year 2000, though the area

allotted to the plaintiff was seen abandoned for years, nearby private

quarries were in operation. However, during the time of evidence he had

taken a stand that no such private quarries were noted by him. Though

PW3 admitted that there are 6 small quarries near Kovalam, according

to him, they were not producing armour stones. PW4 has not denied the

suggestion that about 50 other quarries were working near Kovalam.

2025:KER:55008

When it was suggested that in several other quarries in the district,

stones of required size were being produced, he pleaded ignorance.

27. At the same time, DW1 categorically deposed that there

were about 50 other quarries near Vattappara quarry and that in those

quarries stones of required size were produced. From the above evidence

of PW3 and DW1 and from Ext.C1 it can be safely concluded that there

were a sufficient number of private quarries also near to the department

quarry at Vattappara. Even if sufficient quantity of granite was not

available from the department quarry at Vattappara, the plaintiff could

have collected the remaining granite from the private quarries available

near to the department quarry and only after exhausting those nearby

quarries he could have proceeded to the distant quarries. The reason why

the plaintiff avoided those private quarries which are present at

Vattappara and proceeded to the distant quarry at Parippally, as now

claimed, is also not explained. Similarly, he also ought to have obtained

the prior permission of the defendant, if he wanted to claim any extra

conveyance charge from them.

2025:KER:55008

28. Even according to the plaintiff, the defendants have entered

into similar contracts with several other contractors and the same quarry

at Vattappara was allotted to them also. In this context it is to be noted

that, none of the other contractors have any difficulty in getting

sufficient granite from Vattappara. They also have not raised any similar

claim against the defendants. It is also to be noted that the plaintiff

received the bill amount from the defendant without protest.

29. As argued by the learned Government Pleader, in Exhibit B1

agreement, there is no provision for paying any additional amount

towards extra conveyance in case the contractor brings material from far

away places. Since as per Exhibit B1, the plaintiff was bound to collect

granite from the nearby department quarry at Vattappara and if the

plaintiff at his own instance and convenience brought stones from a

distant place, without the prior permission of the defendants, the

additional expenses, if any, met by him is to be borne by him.

30. The plaintiff, who had 15 years of experience in the field and

undertook 48 similar works very well knew the nature, extent, quality

2025:KER:55008

and availability of the rock at Vattappara when he entered into

agreement with the defendant. Since the plaintiff entered into contract

with the defendant after fully knowing about the nature, extent, quality

and availability of the granite in the department quarry at Vattappara, he

was not justified in claiming compensation for extra conveyance on the

ground that he unilaterally brought granite from a far away place.

31. On the other hand, as noted above, in this case there is no

reliable evidence to prove that the plaintiff has in fact brought any

granite from the Parippally quarry, as claimed. Even if he had brought

any portion of the granite used for the work from any quarry other than

the department quarry at Vattappara, there is nothing to show that it was

from Parippally. Even if any such portion was brought from any quarry

other than the department quarry at Vattappara, there is also no reliable

evidence to prove it's separate quantity. The present suit filed after

receiving the bill amount without protest, on the basis of Ext.A2 issued

by the government 'as a very special case', in a different context and

praying for applying the same yardstick in the present contract is an

2025:KER:55008

experimental one, devoid of any merits. In the above circumstance, the

trial court was perfectly justified in dismissing the suit. I do not find any

irregularity or illegality in the impugned judgment and decree of the trial

court so as to call for any interference and as such, this appeal is liable

to be dismissed. Point answered accordingly.

32. In the result, this appeal is dismissed with costs.

All pending interlocutory applications shall stand closed.

Sd/-

C. PRATHEEP KUMAR, JUDGE sou.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter