Friday, 17, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Ardeshir B. Cursetjee & Sons Ltd vs M/S.Soma Enterprises Limited
2025 Latest Caselaw 1542 Ker

Citation : 2025 Latest Caselaw 1542 Ker
Judgement Date : 25 July, 2025

Kerala High Court

M/S.Ardeshir B. Cursetjee & Sons Ltd vs M/S.Soma Enterprises Limited on 25 July, 2025

Author: Sathish Ninan
Bench: Sathish Ninan
                                                 2025:KER:54805
             IN THE HIGH COURT OF KERALA AT ERNAKULAM

                               PRESENT

             THE HONOURABLE MR. JUSTICE SATHISH NINAN

                                   &

         THE HONOURABLE MR.JUSTICE P. KRISHNA KUMAR

   FRIDAY, THE 25TH DAY OF JULY 2025 / 3RD SRAVANA, 1947

                        RFA NO. 810 OF 2014

AGAINST THE JUDGMENT DATED 28.02.2014 IN OS NO.1046 OF 2011

              OF III ADDITIONAL SUB COURT, ERNAKULAM

APPELLANT/PLAINTIFF:
          M/S.ARDESHIR B. CURSETJEE & SONS LTD.
          24/1567, SUBRAMANIAN ROAD, W/ISLAND, COCHIN-13,
          REPRESENTED BY ITS GENERAL MANAGER.
          BY ADVS. SMT.KRIPA ELIZABETH MATHEWS
          SMT.C.B.SUMA DEVI
          SMT.SNEHA RAJIV
          SHRI.VINAYAK MOHANDAS
RESPONDENTS/DEFENDANTS:
    1     M/S.SOMA ENTERPRISES LIMITED
          2, AVENUE 4, BANJARA HILLS HYDERABAD, ANDHRA
          PRADESH 500 034, REPRESENTED BY ITS CHAIRMAN AND
          MANAGING DIRECTOR.
    2     MS SOMA ENTERPRISE LIMITED
          N.H.CONNECTIVITY ICTT-VALLARPADAM, WARD NO.2,
          GODOWN ROAD, CHERANELLORE, COCHIN 682 034
          REPRESENTED BY ITS MANAGER.
          BY ADV SRI.MILLU DANDAPANI

THIS REGULAR FIRST APPEAL HAVING COME UP FOR HEARING ON
25.07.2025,     THE   COURT   ON   THE   SAME   DAY   DELIVERED   THE
FOLLOWING:
                                                                 2025:KER:54805


            SATHISH NINAN & P. KRISHNA KUMAR, JJ.
              = = = = = = = = = = = = = = = = = =
                      R.F.A.No.810 of 2014
              = = = = = = = = = = = = = = = = = =
             Dated this the 25th day of July, 2025

                                 JUDGMENT

Sathish Ninan, J.

The suit for money under a works contract, was

dismissed by the trial court. The plaintiff is in appeal.

2. The defendant invited tenders for undertaking

dredging and excavation works in connection with the

construction of four-lane National Highway connectivity to

ICTT at Vallarpadam, Cochin. In response, the plaintiff

submitted Ext.A2 quotation dated 21.02.2009. The plaintiff's

quotation was accepted and Ext.A3 work order dated

06.03.2009 was issued by the defendant.

3. According to the plaintiff, during the course of

Ext.A3 work, the defendant issued another work order

(Ext.A4) dated 16.09.2009, for carrying out of certain

dredging works using Beaver 1200 dredger. The quantity of 2025:KER:54805

works under Exts.A3 and A4 work orders was approximately

1,00,000 cubic meters each. Out of Ext.A3 work order, the

plaintiff was provided with work for only 31,207.07 cubic

meters. The bills under Ext.A3 work order were not paid. So

also, they were not provided with the required drawings and

technical specifications. Hence, the plaintiff was unable to

carry out the works. The contract has been breached. The

machineries of the plaintiff were not permitted to be

removed from the site. Accordingly, the suit was instituted

for realisation of Rs.1,09,89,271/-, being, loss of profit

for the shortage of quantity, unpaid bills, and value of

machinery.

4. The defendant filed a written statement denying

the plaint allegations and the plaint claim. According to

the defendant, though pursuant to Ext.A3 work order dated

06.03.2009, the plaintiff had commenced the dredging works,

they were unable to satisfactorily undertake the work for

lack of the necessary and proper machinery and accessories.

2025:KER:54805

To carry out the work, machinery like IHC Beaver 1200

dredger, floaters, elbows, etc., were necessary. To enable

the plaintiff to meet the additional expenses and to carry

out the remaining work, the defendant issued Ext.A4 work

order providing a higher rate. The Ext.A4 work order is only

a continuation of Ext.A3 work order. It was alleged that the

plaintiff failed to mobilise the required machinery and

accessories and failed to carry out the work. Consequent

thereto, the defendant had to make alternate arrangements

for completion of the works and thus suffered damages.

5. The allegation of failure on the part of the

defendant to supply the agreed quantity was denied. It was

contended that Ext.A4 work order was the quantity of work

that remained under Ext.A3 work order. Regarding the claim

for the balance amount due for the work done under Ext.A3

work order, it was contended that Rs.20,00,000/- was

advanced by the defendant to the plaintiff towards

mobilisation advance under Ext.A4 work order; the works 2025:KER:54805

under Ext.A4 having not been carried out, the bill amount is

to be deducted therefrom. Even thereafter, excess amounts

remained with the plaintiff. With regard to the claim for

the value of machinery and equipments, it was contended that

only some equipments were available at the site, and they

could have been removed by the plaintiff after repaying the

excess amount received by them.

6. The trial court held that Exts.A3 and A4 work

orders related to a single work, and that Ext.A4 was in

respect of the balance work that remained under Ext.A3 work

order. No works were done under Ext.A4. Thus, the claim for

damages for non-supply of the agreed quantity was negatived.

With regard to the claim for unpaid bill, the trial court

found that the plaintiff had received Rs.20,00,000/- towards

mobilisation advance under Ext.A4 work order, which is in

excess of the unpaid bill amount under Ext.A3 work order.

Regarding the claim for the value of machineries, it was

found that the claim is unsupported by evidence.

2025:KER:54805

Accordingly, the suit was dismissed.

7. We have heard Sri.Vinayak Mohandas, the learned

counsel on behalf of the appellant-plaintiff and Sri.Millu

Dandapani, the learned counsel on behalf of the respondent-

defendant.

8. The points that arise for determination are: -

(i) Did Ext.A4 work order relate to part of the work under Ext.A3 work order?

(ii) Is the claim of the plaintiff for damages under the head 'deficit quantity' under Ext.A3 work order sustainable?

(iii) Is the plaintiff entitled to realise any amounts from the defendant under the head of 'unpaid bills' under Ext.A3 work order?

(iv) Is the plaintiff entitled to realise any amounts from the defendant towards 'value of machinery'?

(v) Does the decree and judgment of the trial court warrant any interference?

9. The plaint claim is under three heads: (i) Loss of

profit for failure to provide the agreed quantity under

Ext.A3 work order, (ii) Money due for unpaid bills under

Ext.A3 work order; and (iii) Value of equipments and 2025:KER:54805

machineries left at the site. While the plaintiff's claim

that there is no overlapping of the works between Exts.A3

and A4 work orders, according to the defendant, Ext.A4 work

order was in respect of the unfinished work under Ext.A3

work order.

10. Firstly, we proceed to consider the plaint claim

by accepting the plaintiff's case that the work orders were

not a part of the single work. As per Ext.A3 work order, the

quantity of work was approximately 1,00,000 cubic meters.

The plaint claim that under Ext.A3, the plaintiff completed

approximately 31,207.07 cubic meters of work (approximately

1/3rd of the work) is not disputed by the defendant. The

claim is for the loss of profit on the failure of the

defendant to supply the remaining quantity of the work. The

plaintiff claims 50% of the agreed rate, towards loss of

profit for the remaining work. But for the bald claim of

loss of profit of 50%, there is total lack of evidence with

regard to the reasonable profit that the plaintiff would 2025:KER:54805

have received as a direct consequence of the breach. There

is no evidence regarding the expenses incurred or would have

incurred. There is no material before the court even to fix

the quantum ex hypothesi. Therefore, the court cannot grant a

decree under the said head.

11. Next, we proceed to consider the claim for unpaid

bills under Ext.A3 work order. The plaintiff's claim that an

amount of Rs.11,69,000/- remained unpaid, seems to be not in

dispute as such. But it is the defendant's case that an

amount of Rs.20,00,000/- was paid by the defendant to the

plaintiff under the head 'mobilisation advance' under Ext.A4

work order. The work under Ext.A4 has not been carried out

by the plaintiff. The unpaid bill is to be adjusted from the

said advance, and the balance is to be repaid to the

defendant, is the case.

12. The fact that no works were carried out pursuant

to Ext.A4 work order, is undisputed. The plaintiff does not

have any claim under the said head. Such fact is asserted by 2025:KER:54805

the learned counsel for the appellant-plaintiff even during

the course of arguments. Therefore, when the claim is for an

amount of approximately Rs.11,00,000/- and an amount of

Rs.20,00,000/- advanced by the defendant is with the

plaintiff, and the stand of the defendant is that the unpaid

bill amount can be appropriated by the plaintiff from the

said advanced amount, the further claim of the plaintiff

under the said head cannot be countenanced.

13. Now coming to the claim for value of machinery

left at the site, it is the case of the plaintiff that the

defendant obstructed the plaintiff from removing the

machineries and equipments from the site. The claim is for

an amount of Rs.32,84,880/- under the said head. While

considering the said claim, the averment at paragraph 5 of

the plaint that, pursuant to Ext.A3 work order, the

plaintiff had purchased and mobilised dredgers, pipelines of

Beaver 1200, floaters, elbows, etc., at huge cost, is of

relevance. This is so because Ext.A3 work order did not 2025:KER:54805

refer to carrying out the work using Beaver 1200 dredger at

all. It was Ext.A4 work order, which had specifically

stipulated carrying out the work using Beaver 1200 dredger.

Therefore, the claim of the plaintiff that, as per Ext.A3

work order dated 06.03.2009, the plaintiff had arranged

Beaver 1200 dredger and the equipments required for the

same, prima facie appears to be unacceptable.

14. To prove the alleged purchase of equipments and

its value, the plaintiff relies on Exts.A24 to A31 invoices.

Noticeably, those invoices are during the period March and

April 2008, whereas Ext.A3 work order was issued only one

year later, in March 2009. Therefore, the claim of the

plaintiff that the machineries and equipments were procured

for the work in question under Exts.A24 to A31 invoices are

apparently unfounded.

15. To prove that there remained equipments of the

plaintiff at the site at the time when disputes arose

between parties, the plaintiff relies on Ext.A34 survey 2025:KER:54805

report dated 07.04.2010 prepared by a private surveyor. The

report suggests that certain pipes and floaters were found

at the site. Such report was prepared without notice to the

defendant. The report does not mention the value of the

materials. The size(diameter) of the pipes, as reported in

Ext.A34, is smaller than that claimed by the plaintiff. All

those apart, the plaintiff could have very well moved the

trial court seeking assessment of its value and sought

permission to remove them and thus mitigated the damages.

However, he did not choose to do so. There is no proof with

regard to the value of such materials.

16. To prove what all machineries and equipments were

brought to the site, the plaintiff could have very well

produced the daybook and movement register, which are

admittedly available with him. However, such records are not

produced. Coupled with the above is the admission of the PW1

that Beaver 1200 dredger was available at Cochin in

connection with another work at Shipyard. The witness 2025:KER:54805

deposed thus:

"Beaver 1200 ക ച യ ൽ available ആയ ര ന . അത ഷ പ ർഡ work ന വ ണ ഇ ക ക ണ നത യ ര ന . പപത യ ക site ൽ Beaver 1200 ക ണ നത യ വരഖ ഉവണ ? (Q) വന കണ . (A)"

Therefore, in the absence of any evidence to show the

materials at the site and its value, and on the failure of

the plaintiff to take steps for mitigation of the damages, a

decree cannot be granted under the said head.

17. Incidentally, it is to be noticed that, while the

claims under the heads could not be substantiated by the

plaintiff, admittedly, an amount of Rs.20,00,000/- was

advanced by the defendant to the plaintiff under Ext.A4 work

order as mobilisation advance. No work was done under

Ext.A4, and there is no claim thereunder. The unpaid bill

amount under Ext.A3 work order is only Rs.11,69,000/-. If

that be so, more than Rs. 8 lakhs is with the plaintiff.

18. Thus, we find that, even going by the plaintiff's

case, that Exts.A3 and A4 works were independent of each

other and related to different works, the claims are not 2025:KER:54805

liable to be granted.

19. Now, we proceed to consider the contention of the

defendant that Ext.A4 work order related to the unfinished

works under Ext.A3 work order. According to the defendant,

with the machinery available with the plaintiff, only a

portion of the work under Ext.A3 could be carried out. To

carry out the remaining works under Ext.A3, machineries of

sufficient capacity including, IHC Beaver 1200 dredgers,

floaters, etc., were necessary. To enable the same, Ext.A4

work order was issued by enhancing the rate. It is the

continuation of the original work, is the contention. Here,

Ext.B7 letter dated 02.02.2010 issued by the defendant to

the plaintiff is of significance. Paragraph 2 of the said

communication reads thus:

"Kindly see the reference No.01 vide which we have given order for dredging of about 1 lakh cum. But your capabilities were not sufficient enough to dredge the various locations we asked for. Later you only suggested dredging to be carried out using the Beaver 1200 dredger. Accordingly new work order (ref.2) has been issued with a revised rate along with a mobilization advance of Rs.20 lakhs. Thereafter you have shown least interest in doing the work. Instead you were 2025:KER:54805

keen on writing letters and blaming others in order to hide your incapability to execute the work."

Such statements seem un-rebutted. Under Ext.A4 work order,

the description of the work is specifically for "Dredging

using Beaver 1200 dredger". Admittedly, Ext.A4 work order

was issued when only approximately 31,000 cubic meters of

quantity of work was done under Ext.A3 work order. The above

probabilises the defendant's claim that it was for carrying

out the remaining part of the work under Ext.A3 work order,

which could not be carried out with the available machinery,

that Ext.A4 work order was issued for a higher rate.

20. A perusal of Exts.A3 and A4 work orders indicates

that both are related to "dredging the canal area". While

Ext.A3 specified the work areas at "Moolampilly and

Mulavukadu", Ext.A4 work order related to "work areas at

various alignment locations". There is no case that there

was more than one project site. Further, PW1 in cross-

examination admitted that the works under Ext.A3 work order 2025:KER:54805

(approximately 1/3rd) were carried out utilising machinery of

lesser capacity. The relevant deposition reads thus:

"ELLICOT-1 ഉപവയ ഗ ച ണ 31,207 Cum. work ക"യ$ത. അത Beaver കനക ൾ റച capacity ഉളത ണ."

Exts.A5 to A11 are the letters and bills with regard to the

work for approximately 31,000 cubic meters under Ext.A3 work

order. Pertinently, Ext.A11, which is last in series, is

dated 25.08.2009, and it makes up the quantity of

31,000(approx.) cubic meters. This is followed by Ext.A4

work order dated 16.09.2009. These circumstances taken

together probabilises the defendant's claim that Ext.A4 work

order related to carrying out the unfinished work under

Ext.A3, with the machinery of higher specifications and

capacity. Admittedly, no works were done pursuant to Ext.A4

work order.

21. Therefore, the claim of the plaintiff that the

defendant failed to provide the agreed quantity of work

under Ext.A3 work order, and the claim for loss of profit 2025:KER:54805

thereunder, are only to be turned down.

22. The claims under the other two heads, namely,

value of unpaid bills and value of the machineries, have

already been dealt with by us. Whether Exts.A3 and A4 work

orders are independent of each other or are related to the

same work is found to be of no consequence upon the claims.

23. On the above discussions, we find that the trial

court was justified in having negatived the plaintiff's

claims. The decree and judgment of the trial court are

founded on the evidence and warrant no interference.

Resultantly, the appeal fails and is dismissed. No

costs.

Sd/-

SATHISH NINAN JUDGE

Sd/-

P. KRISHNA KUMAR JUDGE yd

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter