Citation : 2025 Latest Caselaw 5693 Ker
Judgement Date : 18 August, 2025
2025:KER:61185
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE C. JAYACHANDRAN
MONDAY, THE 18TH DAY OF AUGUST 2025 / 27TH SRAVANA, 1947
WP(C) NO. 20083 OF 2023
PETITIONERS:
1 BHARGAVAN PILLAI,
AGED 60 YEARS
S/O KRISHNA KURUP, PADINJAREVEETIL,KIZHAKETHIL,
KURUMPALA (S) POST, PANDALAM, PATHANAMTHITTA DISTRICT,
PIN - 689501
2 REGHU KUMAR G,
AGED 60 YEARS
S/O GOPALAN ACHARY, CHAITHRAM HOUSE, KURAMPALA (S)
POST, PANDALAM, PATHANAMTHITTA DISTRICT, PIN - 689501
3 MURALEEDHARAN K,
AGED 59 YEARS
S/O KOCHU KUNJU, VALUTHUNDIL, KURAMPALA (S) POST,
PANDALAM, PATHANAMTHITTA DISTRICT, PIN - 689501
BY ADVS.
SRI.P.M.RAFEEK
SRI.U.NIDHIN
SMT.GIA MATHAI KANDATHIL
SMT.SARA JOHN
RESPONDENTS:
1 DISTRICT GEOLOGIST,
DEPARTMENT OF MINING AND GEOLOGY,DISTRICT OFFICE,
PATHANAMTHITTA DISTRICT, PIN - 689533
2 STATE ENVIRONMENTAL IMPACT ASSESSMENT AUTHORITY-SEIAA,
REP. BY ITS MEMBER SECRETARY, 4TH FLOOR, KSRTC BUS
TERMINAL COMPLEX, THIRUVANANTHAPURAM, PIN - 695001
W.P.(C)No. 20083 of 2023
..2..
2025:KER:61185
3 NATIONAL HIGHWAYS AUTHORITY OF INDIA - NHAI,
G-586, SECTOR-10, DWARAKA P.O, NEW DELHI, REP.
BY ITS CHAIRMAN, PIN - 110075
4 CHAIRPERSON (DISTRICT COLLECTOR),
DISTRICT DISASTER MANAGEMENT AUTHORITY, 2ND
FLOOR, DISTRICT COLLECTORATE, PATHANAMTHITTA,
KERALA, PIN - 689645
5 PANDALAM MUNICIPALITY,
PANDALAM, PATHANAMTHITTA,
REP. BY ITS SECRETARY, PIN - 689501
6 SECRETARY,
PANDALAM MUNICIPALITY, PANDALAM,
PATHANAMTHITTA DIST., PIN - 689501
7 VISWASAMUDRA ENGINEERING PVT. LTD,
RAHEJAN BUILDING, HAMEED KUNJU NAGAR, PADA
NORTH,KARUNAGAPALLY, KOLLAM,REP. BY ITS
AUTHORIZED SIGNATORY, PIN - 690518
BY ADVS.
SHRI.LEJO JOSEPH GEORGE - FOR R3
SRI.K.R.ARUN KRISHNAN
SRI.E.C.KURIAKOSE
SRI.S.SREEKUMAR (SR.)
SMT.DEEPA K.RADHAKRISHNAN
SHRI.SANAL C.S
SHRI.VISHAK K.V.
SMT.DEVISHRI.R - GOVERNMENT PLEADER
SRI.M.P.SREEKRISHNAN - STANDING COUNSEL
SMT.T.S.MAYA - PANDALAM MUNICIPALITY
SRI.B.G.BIDAN CHANDRAN - STANDING COUNSEL (NHAI)
THIS WRIT PETITION (CIVIL) HAVING BEEN CAME UP FOR
HEARING ON 29.07.2025, THE COURT ON 18.08.2025 DELIVERED
THE FOLLOWING:
W.P.(C)No. 20083 of 2023
..3..
2025:KER:61185
"C.R."
J U D G M E N T
Dated this the 18th day of August, 2025
The petitioners, 3 in number, are residing in and around
'Erichurili Mala', a hillock at Kurumbala Village,
Pathanamthitta. They are apprehensive of the large scale
excavation of earth from the said hillock by the 7th
respondent, who purchased that land recently. The
excavation apprehended is in connection with the
construction of Kottukulangara to Kollam highway bypass.
Ext.P1 is a mass petition given to the Director of Mining.
Ext.P2 is the quarrying permit issued to the 7th
respondent permitting excavation and removal of ordinary
earth from 43.20 Ares of land in Erichurili Mala. Although
environmental clearance is mandatory, the 2 nd respondent
State Environmental Impact Assessment Authority ('SEIAA',
for short) had issued Ext.P3 expressing no objection to
grant exemption from obtaining environmental clearance for
sourcing or borrowing of earth for the construction of the
..4..
2025:KER:61185
National Highway. Ext.P4 is a Circular issued by the
Government of Kerala exempting the requirement of
environmental clearance to borrow ordinary earth for
highway related works and for construction of village
roads and other government sponsored schemes. The
petitioners would maintain that Ext.P4 Circular is illegal.
Ext.P5 is a notification issued by the Ministry of
Environment, Forest and Climate Change (MoEF & CC) dated
28.03.2020, granting exemption for certain cases from the
requirement of environmental clearance, which was brought
in by virtue of amendment to Appendix-IX of the EIA
notification, 2006. Serial no. 6 therein is extraction or
sourcing or borrowing of ordinary earth for the linear
projects such as roads, pipelines etc. The exemption
granted vide Ext.P5 was challenged before the National
Green Tribunal by filing Original Application nos.
190/2020 and 68/2020. The National Green Tribunal observed
that grant of blanket exemption for excavation of earth is
against the norms of sustainable development. Ext.P6 is an
O.M issued by the MoEF & CC, which is a clarification
..5..
2025:KER:61185
issued on the applicability of EIA notification, 2006, for
excavation of ordinary earth from borrow area for linear
projects. After deliberation by the Expert Appraisal
Committee (EAC) and based on its recommendations, and also
in view of the direction of the National Green Tribunal,
the Ministry decided that exemption from E.C for
extraction or sourcing or borrowing of ordinary earth for
linear projects shall be subject to Standard Operating
Procedure enclosed to the Office Memorandum. The
petitioner would maintain that the linear project of
Kottukulangara to Kollam highway bypass is a project,
which requires separate E.C for excavating earth. Ext.P7
is a letter issued by the 2 nd petitioner to the 1st
respondent pointing out the illegality in issuing Ext.P2
quarrying permit to the 7th respondent. Ext.P8 is a
similar letter issued by the 2nd petitioner to the 2nd
respondent pointing out the illegality in grant of Ext.P3
'No Objection'. Ext.P9 is an Order whereby the 4 th
respondent, Chairperson of the District Disaster
Management Authority, has evacuated residents near to
..6..
2025:KER:61185
Athiramala due to heavy rainfall, which is produced to
point out that the topography and landscape of 'Erichurili
Mala' are similar to those of Athiramala. By Ext.P10
representation, the 2nd petitioner requested the 4th
respondent Chairperson/District Collector, to take steps
to stop the excavation of earth from 'Erichurili Mala'.
Ext. P11 is a resolution passed by the 5 th respondent to
obtain a 'Non-Objection Certificate' for carrying out
quarrying operations. By Ext. P12 representation, the 2 nd
petitioner requested the 6th respondent to issue a stop
memo to the 7th respondent, preventing the latter from
making preparations for excavating earth from 'Erichurili
Mala' without obtaining a permit from the 5 th respondent.
The petitioners would maintain that Exts.P2 and P3 are
illegal and liable to be quashed. It is highlighted by the
petitioners that an environmental clearance from the 2 nd
respondent is a mandatory pre-condition for quarrying the
subject site and Ext.P2 quarrying permit issued, in the
absence of the same, is illegal. On such premise, the
petitioners seek Exts.P2 and P3 to be quashed, besides
..7..
2025:KER:61185
issuance of a Writ of Mandamus directing respondent nos. 4
and 5 to take steps to stop excavation of earth from
'Erichurili Mala' by the 7th respondent.
2. The contesting 7th respondent filed counter affidavit
inter alia contending as follows:
The 7th respondent is the selected bidder of the National
Highway Authority of India (the 3rd respondent) for the
work of National Highway (six-lane) from Kottukulangara to
Kollam bypass, which requires huge amount of ordinary
earth. Accordingly, the 7th respondent purchased land in
Pathanamthitta. 7th respondent made application under the
Kerala Minor Mineral Concession Rules, 2015, seeking
permission to excavate ordinary earth. Accordingly,
permission was issued and the 7th respondent company paid
the royalty. A revised mining plan was filed by the 7th
respondent company as per the guidelines issued by the
MoEF & CC, produced with Ext.R7(a). By Ext.R7(b), the
revised mining plan was approved by the 1st respondent
Geologist. A clarification was sought to the Judgment of
..8..
2025:KER:61185
the Hon'ble Supreme Court in Noble M. Paikada v. Union of
India [2024 SCC Online SC 369] and by Order dated
15.05.2024, the Hon'ble Supreme Court clarified that work
orders which were issued prior to 21.03.2024 will not be
affected by the Judgment in Noble M. Paikada (supra). The
subject work order was issued to the 7th respondent
company on 06.08.2021, wherefore respondent no. 7 is
entitled to the exemption granted by virtue of the
clarificatory Order. The 3rd respondent/NHAI by Ext.R7(c)
letter brought the above matter to the notice of the
Geologist. On such premise, the 7th respondent seeks the
Writ Petition to be dismissed.
3. Heard Sri.P.M.Rafeek, learned counsel the
petitioners; Smt.Devishri R., the learned Government
Pleader on behalf of respondents 1 and 4;
Sri.M.P.Sreekrishnan, the learned Standing Counsel for the
2nd respondent SEIAA; Sri.B.G Bidan Chandran, learned
Standing Counsel for the 3rd respondent NHAI;
Smt.T.S.Maya, for the 5th respondent Municipality and
..9..
2025:KER:61185
learned Senior Counsel Sri.S.Sreekumar, duly instructed by
Advocate K.R.Arun Krishnan, on behalf of the contesting
7th respondent. Perused the Records.
4. From the arguments raised by the learned counsel for
the respective parties, the issue centers around the
Judgment of the Hon'ble Supreme Court in Noble M. Paikada
(supra), as also, the clarificatory Order of the Hon'ble
Supreme Court to that Judgment, which is produced along
with Ext.R7(c) by the 7th respondent. The impact of this
clarificatory Order dated 15.5.2024 has already been
considered by, as many as, four learned single judges of
this Court. The first is the Order dated 11.11.2024 in I.A
No. 1/2024 and W.P(C)No.32704/2024, produced at Ext.P19
rendered in a similar fact situation, wherein the 8 th
respondent/concessionaire claimed the benefit of the
clarificatory Order obtained by the National Highway
Authority of India to the Judgment in Noble M. Paikada
(supra). In that case also, the issue involved was the
excavation of a large hill, on the premise that the 8 th
..10..
2025:KER:61185
respondent therein was the contractor appointed by the
NHAI to execute a work, which falls under the exemption
granted by the clarificatory Order above referred. The
learned Single Judge took stock of the fact that the 8 th
respondent therein had not obtained any E.C for conducting
mining/excavation activities. The work order referred to
in Ext.R8 A in that case does not mention about sourcing
or borrowing of ordinary earth from the site in question.
The work order only refers to a linear project. The
exemption from E.C was granted only by virtue of the
amendment to the EIA notification (produced as Ext.P5 in
the present Writ Petition), which was struck down by the
Supreme Court in the Judgment in Noble M. Paikada (supra).
Thus, the exemption from obtaining E.C, a mandatory
requirement for extraction, would not survive any more and
that the clarification issued by the Supreme Court was
only for projects, for which work orders were issued
before the cut off date, that is, 21.03.2024. The learned
Single Judge found that the excavation of ordinary earth
by the 8th respondent therein (the contractor of the NHAI
..11..
2025:KER:61185
in the project in question) cannot be brought within the
scope of the exemption granted under the clarificatory
Order and therefore, the requirement of an environmental
clearance cannot be dispensed with. Accordingly, the
request for vacating the interim order, which directed
prevention of excavation was dismissed. Although the said
Order is passed in I.A, the matter is exhaustively seen
dealt with.
5. The next judgment is the one produced at Ext.P20,
wherein a police protection was sought for, on the premise
that the work in question stood accepted by the
clarificatory Order of the Supreme Court. There, the issue
is seen considered by the learned Single Judge at length
and found in paragraph no.10 that, although the work order
was issued prior to the cut off date, the permit was
issued thereafter and as on the date of issuance of the
permit, the exemption provided for extraction of earth for
linear projects was not in existence. Accordingly, the
police protection sought for was dismissed.
..12..
2025:KER:61185
6. The third judgment to be taken note of is the one
produced at Ext.P25 in W.P.(C)No.2090/2025, wherein a
Grama Panchayat sought for quashing a quarrying permit.
There also, Noble M. Paikada (supra) and the clarificatory
Order of the Hon'ble Supreme Court dated 15.05.2024 have
been considered by the learned Single Judge. After taking
stock of Ext.P20 judgment of the learned Single Judge, as
also the judgment of the Division Bench in
W.A.No.1877/2024 (which took stock of the fact that
Ext.P20 judgment was rendered in a Writ Petition seeking
police protection and hence the findings would not
preclude the petitioner therein from seeking substantive
relief and declaration), the learned Single Judge held
himself in complete agreement with the interpretation made
in Ext.P20 judgment. That apart, the learned Single Judge
also took stock of the precautionary principle and the
judgments on the point, ultimately to hold that the
quarrying operations cannot be continued without a prior
E.C. It could thus be seen that the benefit of the
..13..
2025:KER:61185
clarificatory Order of the Hon'ble Supreme Court in Noble
M. Paikada (supra) was not considered in favour of the
project proponent therein.
7. The fourth one is by yet another learned Single Judge
in Wilson K John and Others v. Joint Secretary,
Industries Department and Others [W.P.(C)No.12684/2024 and
connected matters]. A common judgment was rendered in
three Writ Petitions. The main issue involved in those
cases was, whether an environmental clearance has to be
obtained by the concessionaires, who have undertaken the
work on behalf of the NHAI for quarrying earth to be used
for the development of the Highway, the precise issue
which was fallen for consideration in the subject Writ
Petition as well. After taking stock of Noble M. Paikada
(supra) and the clarificatory Order, the learned Single
Judge toed in line with the law laid down by the learned
Single Judge in M/s Oriental Structural Engineers Private
Limited v. The Circle Inspector of Police and Others
[W.P.(C)No.34959/2024 - Ext.P20], the Division Bench
..14..
2025:KER:61185
judgment rendered in appeal therefrom [W.A.No.1877/2024],
and the judgment of the learned Single Judge in
Nedukunnam Grama Panchayath v. The State of Kerala and
Others [W.P.(C)No.2090/2025]. Ultimately, the learned
Single Judge held that the benefit of the clarificatory
Order is sought by the concessionaire, whereas, the Order
only safeguards the work orders for linear projects. It
has been held that every person who undertakes the work of
such linear projects are not entitled to exception. The
benefit of the clarificatory Order is only for the work
orders issued by the NHAI, which cannot be extended to the
concessionaire. The obligation of the concessionaire to
extract, source or borrow ordinary earth has to be met by
undertaking the work of mining or by procuring ordinary
earth from suppliers. For excavation of ordinary earth,
the suppliers will have to obtain the environmental
clearance. To say that the concessionaire requires no EC
for excavating soil would be extending the clarification
issued by the Hon'ble Supreme Court beyond its scope and
intent. Thus, the claim of the concessionaire/contractor
..15..
2025:KER:61185
was negated in that case as well. An appeal was carried
before the Division Bench from the above-referred judgment
of the learned Single Judge in Writ Appeal No.497/2025 and
connected cases. Although appellants pressed for an
interim order, the same was refused vide Order dated
11.04.2025, produced at Ext.P24, finding that there is no
prima facie reason to stay the impugned judgment, so as to
permit the appellants to remove the ordinary earth.
8. With these input, I will now consider the issue at
hand, for the correct appreciation of which, this Court
will have to start from Ext.P5 notification dated
28.03.2020. That notification, by virtue of the amendment
brought into Appendix-IX to the EIA Notification, 2006,
granted exemption to certain cases from the requirement of
environmental clearance. Serial No.6 to the amended
Appendix-IX is 'extraction or sourcing or borrowing of
ordinary earth for the linear projects such as roads,
pipelines etc.'. This exemption granted vide Ext.P5 was
put to challenge, which was ultimately decided by the
..16..
2025:KER:61185
Hon'ble Supreme Court in Noble M. Paikada (supra). The
Hon'ble Supreme Court struck down the above serial no.6 of
the amended Appendix-IX of the EIA notification and
quashed the same. Thereupon, the NHAI preferred an interim
application seeking clarification of the above judgment.
It is in that application, Ext.R7(c) Order has been passed
by the Hon'ble Supreme Court on 15.05.2024.
9. Before analyzing the scope of the clarificatory
Order, this Court has directed the 3 rd respondent to
produce the interim application filed before the Hon'ble
Supreme Court, so as to understand the context in which
that application was filed, as also, its scope. From a
perusal of paragraph no.6 of that application, the
applicant-NHAI would espouse the magnitude of the adverse
impact which will be faced by NHAI. The same is seen
espoused in paragraph no.12 as well. In paragraph no.14,
it is specifically averred that, to discharge the
statutory functions of the NHAI, it is empowered to award
infrastructural contracts to private companies,
..17..
2025:KER:61185
contractors/concessionaires etc., for construction,
development, maintenance and operations of National
Highways. The requirement of ordinary earth in connection
with the project is seen espoused in paragraph no.15,
wherein the inbuilt mechanism to ensure environmental
protection is also seen referred to. Paragraph no.32
refers to about 485 infrastructural road projects in
progress at different parts of the country, which are in
different stages of completion. Annexure-P3 to the
petition is a list of all the ongoing projects of the
National Highway. Paragraph no.34 again specifically
refers to the implications on the contractor/
concessionaire of the judgment in Noble M. Paikada
(supra). The plight of the concessionaires/contractors
that they may not be able to absorb the overhead costs
arising out of the delay etc., are also seen espoused.
Ultimately, the prayer sought for was to recall the
judgment in Noble M. Paikada (supra) or in the alternative,
to allow the applicant/NHAI to complete the NH projects,
which are mentioned in Annexure-P3 to the petition.
..18..
2025:KER:61185
10. It is in the above state of affairs as pleaded in the
petition and as noticed above, that Ext.R7(c) Order has
been passed by the Hon'ble Supreme Court, clarifying that
the projects, for which work orders were issued by the
applicant/NHAI prior to 21.03.2024, will remain unaffected
by the judgment in Noble M. Paikkada (supra). By virtue of
the clarification Order, NHAI was directed to file an
affidavit giving a list of the projects for which work
orders have been issued prior to 21.03.2024 and also to
produce the copies of the work orders and other relevant
documents showing service of the work order on contractors
within a period of one month from the date of the
clarificatory Order. It could thus be seen that the
Supreme Court was fully aware of the fact that the work
orders are being executed through contractors/
concessionaires. It was again clarified that the work
orders which were issued prior to 28.03.2020 require
environmental clearance, and therefore the benefit of the
clarificatory Order will not be available to such work
orders.
..19..
2025:KER:61185
11. It could thus be seen that the Hon'ble Supreme Court
has clarified that in respect of projects of NHAI, of
which the work orders were issued prior to 21.03.2024, but
after 28.03.2020, will remain unaffected by the judgment
in Noble M. Paikada (supra). In other words, the
declaration of law made by the Supreme Court, insofar as
Ext.P5 notification amending Appendix-IX to the EIA
notification, 2006, and quashing the same, has been
rendered inapplicable to those works which are specified
above. This would be the impact of the clarificatory Order
issued by the Supreme Court.
12. Now, the moot question is whether a contractor who is
executing the work of NHAI, which stands exempted by
virtue of the clarificatory Order dated 15.05.2024, can
claim the benefit of that Order. I am of the opinion that
he is, provided the extraction, sourcing or borrowing of
ordinary earth is exclusively for the linear projects. An
..20..
2025:KER:61185
interpretation otherwise would defeat the precious right
secured by the NHAI by seeking a clarification to the
judgment and obtaining the same by Order dated 15.05.2024.
It goes without saying that the scope of an Order has to
be addressed and interpreted on the strength of the
pleadings placed before the Court and the arguments
addressed. As already taken note of, the specific pleading
which was before the Hon'ble Supreme Court in the
clarification petition preferred by NHAI was the
difficulties which they would face on account of the
judgment in Noble M. Paikada (supra), in respect of
on-going projects. The fact that the works of NHAI are got
implemented by engaging contractors/concessionaires is
very much pleaded in that interim application. Besides,
the impact of the judgment in Noble M. Paikada (supra) on
such contractors is also pleaded. Thus, Ext.R7(c)
clarificatory Order passed, taking stock of such
pleadings, has to be read and interpreted meaningfully, so
as to give effect to that Order; and not in a manner
circumventing the benefit obtained by NHAI. This is all
..21..
2025:KER:61185
the more so, when Ext.R7(c) clarificatory Order
specifically refers to provide proof regarding service of
work orders on the contractors. Thus, if the contractor is
specifically confining his activity to the work of the
NHAI and if his quarrying permits also reflect such
limitation of confining to the exempted work of the NHAI,
then to deny the benefit of the clarificatory Order only
for the reason it is sought for by the contractor would
defeat the very purpose of the clarificatory Order.
Ideally, it is for the NHAI to seek the benefit of the
clarificatory Order. However, if a Writ Petition is filed
challenging the authority of the contractor to indulge in
quarrying activity, though enabled by a permit or license,
it would quite be open for the NHAI to point out that the
work which is undertaken by the contractor pertains to the
exempted works of the NHAI only. However, this has to be
done either by NHAI or by the contractor/concessionaire by
producing adequate and sufficient documents, in support
thereof.
..22..
2025:KER:61185
13. Coming to the instant facts, Ext.P2 is the quarrying
permit issued to the 7th respondent/contractor for
extraction of ordinary earth. The same is dated
21.03.2023, which has expired, by now, as submitted by the
learned Senior Counsel for the 7th respondent. The area
from which ordinary earth is permitted to be extracted has
an extent of 43.20 ares in survey nos.391/2-1, 390/5 and
390/6 of Kurampala Village, Adoor. Ext.P3 is the No
Objection issued by SEIAA for granting exemption from
obtaining environmental clearance for sourcing or
borrowing earth for the purpose of the works of the
National Highway. Coming to Ext.R7(a), the same is a
communication issued by the NHAI to the Geologist,
indicating that the 7th respondent has been appointed by
the NHAI for six laning of the existing NH-66 from
Kottukulangara-Kollam Bypass. Apart from the extent of
land above-referred, another extent of land having 0.8818
hectares of land situated in Enadimangalam Village is also
seen referred to in Ext.R7(a). A perusal of the above as
..23..
2025:KER:61185
well as other documents produced in this Writ Petition
would only indicate that the quarrying permit issued to
the 7th respondent is not confined to the exempted works
of the NHAI. There is nothing to indicate that the
proposed quarrying in terms of Ext.P2 is confined and
limited to the exempted work of the NHAI by virtue of the
clarificatory Order dated 15.05.2024. If that be so, the
concessionaire/contractor cannot be brought in within the
scope of the exemption from the judgment in Noble M.
Paikada (supra) as clarified by Order dated 15.05.2024.
There is every chance of misuse, if the
contractor/concessionaire is also afforded with the
benefit of the clarificatory Order in the above-referred
state of affairs.
14. Yet another aspect which looms large is the absence
of any material as to how much quantity of earth is
required for the exempted linear project of the NHAI in
question. This Court is at a loss to find that no
material, or for that matter even a counter, has been
..24..
2025:KER:61185
placed on record by the 3rd respondent/NHAI in the instant
Writ Petition, despite the Writ Petition having been filed
in the year 2023. Thus, there is absolutely no guarantee
that the quarrying activity to be undertaken by the 7 th
respondent by virtue of Ext.P2 permit is confined only to
the requirements of the NHAI for the exempted work.
Therefore, the relief sought for in the Writ Petition can
only be allowed.
15. Before parting with the judgment, this Court should
address an argument raised by the learned Senior Counsel
on the views taken by the learned Single Judges on the
point that the work permits were issued only after the cut
off date stipulated by the Hon'ble Supreme Court in the
clarificatory Order, though the work orders were issued
before the cut off date. According to the learned Senior
Counsel, when the Supreme Court has focused and emphasized
on the date of issuance of work orders and called for the
data of such works where orders have been issued before
the cut off date, it is impermissible for this Court to
..25..
2025:KER:61185
adopt a different yardstick to negate the benefit, on the
premise that the permit has been issued after that cut off
date. It may be that there is some force in that argument
of the learned Senior Counsel. However, inasmuch as this
Court is dis-inclined to accept the contentions of the 7 th
respondent, the said argument will be of no impact,
insofar as the ultimate outcome of the Writ Petition is
concerned.
16. In the circumstances, the Writ Petition succeeds, and
it is declared that the 7th respondent cannot undertake
quarrying activities for extracting ordinary earth on the
strength of Ext.P2 quarrying permit. Respondents 1, 4 and
5 will take effective steps to ensure that no quarrying
activity is conducted by the 7 th respondent, on the
strength of Ext.P2.
The Writ Petition (Civil) is disposed of as above.
Sd/-
C. JAYACHANDRAN JUDGE TR/vdv
..26..
2025:KER:61185
APPENDIX OF WP(C) 20083/2023
PETITIONER EXHIBITS
Exhibit P1 TRUE COPY OF THE MASS PETITION DATED 10/6/2022 GIVEN TO THE 1ST RESPONDENT. Exhibit P2 TRUE COPY OF THE QUARRYING PERMIT ISSUED BY THE 1ST RESPONDENT TO THE 7TH RESPONDENT.
Exhibit P3 TRUE COPY OF THE LETTER DATED
22/2/2020 ISSUED BY THE 2ND
RESPONDENT.
Exhibit P4 TRUE COPY OF THE SAID CIRCULAR NO.
A3/117/2017/ENVT DATED 17/8/2017 FROM ENVIRONMENT (A) DEPARTMENT.
Exhibit P5 TRUE COPY OF THE NOTIFICATION DATED 28/03/2020 ISSUED BY THE MOEF AND CC.
Exhibit P6 TRUE COPY OF THE OFFICIAL MEMORANDUM DATED 8/8/2022 ISSUED BY THE MOEF AND CC Exhibit P7 TRUE COPY OF THE SAID LETTER DATED 12/6/2023 ISSUED BY THE 2ND PETITIONER TO THE 1ST RESPONDENT.
Exhibit P8 TRUE COPY OF THE LETTER DATED
14/06/2023 ISSUED BY THE 2ND
PETITIONER TO THE 2ND RESPONDENT.
Exhibit P9 TRUE COPY OF THE ORDER ISSUED BY THE
4TH RESPONDENT FOR EVACUATING PEOPLE NEAR 'ATHIRAMALA' DATED 19/10/2021. Exhibit P10 TRUE COPY OF REPRESENTATION DATED 9/06/2023 ISSUED BY THE 2ND PETITIONER TO THE 4TH RESPONDENT.
Exhibit P11 TRUE COPY OF THE RESOLUTION PASSED BY THE 5TH RESPONDENT DATED 27/7/2022.
Exhibit P12 TRUE COPY OF THE SAID REPRESENTATION DATED 9/6/2023 ISSUED BY THE 2ND PETITIONER TO THE 6TH RESPONDENT.
Exhibit P13 PHOTOGRAPHS SHOWING THE PRESENT LIE AND NATURE OF 'ERICHURILI MALA'.
Exhibit P14 TRUE COPY OF THE INTERIM ORDER DATED
..27..
2025:KER:61185
1/2/2023 IN WP© NO. 3549/2023.
Exhibit P15 TRUE COPY OF THE INTERIM ORDER DATED 9/3/2023 IN WP© NO. 3549/2023.
Exhibit P16 TRUE COPY OF THE INTERIM ORDER DATED 5/5/2023 IN WP©15258/2023.
Exhibit P17 TRUE COPY OF THE INTERIM ORDER DATED 6/6/2023 IN WP©15258/2023.
RESPONDENT EXHIBITS
Exhibit R7 (a) A TRUE COPY OF THE PLAN SUBMITTED BY THE 7TH RESPONDENT WITH FORWARDING LETTER OF NATIONAL HIGH WAY DATED 24.01.2024 Exhibit R7 (b) A TRUE COPY OF THE APPROVAL LETTER ISSUED BY THE GEOLOGIST DATED 06.03.2024 PETITIONER EXHIBITS
Exhibit P18 A TRUE COPY OF THE INTERIM ORDER DATED 8/8/2024 IN W P (C) NO. 27562/2024 RESPONDENT EXHIBITS
Exhibit R7(a) A TRUE COPY OF THE PLAN SUBMITTED BY THE 7TH RESPONDENT WITH FORWARDING LETTER OF NATIONAL HIGH WAY DATED 24.01.2024 Exhibit R7(b) A TRUE COPY OF THE APPROVAL LETTER ISSUED BY THE GEOLOGIST IS PRODUCED HEREWITH AND MARKED AS DATED 06.03.2024 Exhibit R7(c) A TRUE COPY OF THE LETTER DATED 13.06.2024 ALONG WITH THE DOCUMENTS PETITIONER EXHIBITS
Exhibit P19 A TRUE COPY OF THE INTERIM ORDER DATED 11.11.2024 PASSED BY THE HON'BLE SINGLE JUDGE IN I.A NO.1/2024 IN W.P ©NO 32704 OF 2024 Exhibit P20 A TRUE COPY OF THE JUDGEMENT DATED 1/11/2024 IN W.P © NO. 34959 OF 2024
..28..
2025:KER:61185
Exhibit P21 A TRUE COPY OF THE JUDGMENT DATED 21/3/2024 OF THE HON'BLE SUPREME COURT OF INDIA IN CIVIL APPEAL NO.1628/2021
Exhibit P22 A TRUE COPY OF THE INTERIM ORDER DATED 15/5/2024 OF THE HON'BLE SUPREME COURT OF INDIA IN CIVIL APPEAL NO.1628/2021
Exhibit P23 A TRUE COPY OF THE JUDGMENT OF THE SINGLE BENCH OF THIS HON'BLE COURT DATED 10/3/2025 IN W.P.(C) NO.12684/2024 AND A BATCH OF CONNECTED CASES Exhibit P24 A TRUE COPY OF THE INTERIM ORDER DATED 11/4/2025 OF THE HON'BLE DIVISION BENCH OF THIS HON'BLE COURT IN W.A NO.497/2025 AND CONNECTED APPEALS Exhibit P25 A TRUE COPY OF THE JUDGMENT DATED 10/2/2025 IN W.P.(C) NO. 2090/2025 RESPONDENT ANNEXURES
ANNEXURE R3(A) COPY OF THE APPLICATION DATED 07.05.2025 IN CIVIL APPEAL NO. 1628- 1629 OF 2021.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!