Friday, 17, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

K.M.Shafi vs District Collector, Kasaragod
2025 Latest Caselaw 2219 Ker

Citation : 2025 Latest Caselaw 2219 Ker
Judgement Date : 4 August, 2025

Kerala High Court

K.M.Shafi vs District Collector, Kasaragod on 4 August, 2025

                                                  2025:KER:58206


          IN THE HIGH COURT OF KERALA AT ERNAKULAM

                           PRESENT

              THE HONOURABLE MR. JUSTICE S.MANU

   MONDAY, THE 4TH DAY OF AUGUST 2025 / 13TH SRAVANA, 1947

                   WP(C) NO. 21326 OF 2016

PETITIONER:

    1    *K.M.SHAFI
         S/O.MOHAMMED, AGED 70 YEARS, MELPARAMBA,
         KALANAD P.O., KASARAGOD.
         *DECEASED. LEGAL HEIRS IMPLEADED
    2    *ADDL.P2 ABDUL MAJEED K.S
         AGED 47 YEARS, S/O. (LATE) K.M. SHAFI, NOOR MAHAL,
         THOTTIL, DELI, KALANAD, KASARAGOD,PIN - 671317
         *IS IMPLEADED AS ADDL.P2 AS PER ORDER DATED
         30/06/2025 IN IA 1/2025

    3    *ADDL.P3 MOHAMMED ASHKAR
         AGED 43 YEARS, S/O. LATE K.M. SHAFI, THODE HOUSE
         DELI, KALANAD, KASARAGOD, PIN - 671317
         *IS IMPLEADED AS ADDL.P3 AS PER ORDER DATED
         30/06/2025 IN IA 1/2025

    4    *ADDL.P4 KADEEJATH RAZEENA
         AGED 36 YEARS,D/O. LATE K.M. SHAFI, THODE HOUSE
         DELI, KALANAD, KASARAGOD, PIN - 671317
         *IS IMPLEADED AS ADDL.P4 AS PER ORDER DATED
         30/06/2025 IN IA 1/2025)

    5    *ADDL.P5 ASIATH RELIATH
         AGED 33 YEARS, D/O. LATE K.M. SHAFI, THODE HOUSE,
         DELI, KALANAD, KASARAGOD, PIN - 671317
         *IS IMPLEADED AS ADDL.P5 AS PER ORDER DATED
         30/06/2025 IN IA 1/2025

    6    *ADDL.P6 ZOHARA
         AGED 63 YEARS, W/O. LATE K.M. SHAFI, THODE HOUSE,
         DELI, KALANAD P.O., KASARAGOD, PIN - 671317
         *IS IMPLEADED AS ADDL.P6 AS PER ORDER DATED
         30/06/2025 IN IA 1/2025
                                                                 2025:KER:58206
                                         2
W.P.(C) No.21326 of 2016




             BY ADVS.
             SHRI.K.V.PAVITHRAN
             SHRI.JAYANANDAN MADAYI PUTHIYAVEETTIL
             SRI.NIAS MOOPAN
             SHRI.P.SAJU



RESPONDENTS:

     1       DISTRICT COLLECTOR, KASARAGOD

     2       TAHSILDAR
             REVENUE RECOVERY, KASARAGOD.

     3       EXECUTIVE ENGINEER
             PWD, BUILDINGS DIVISION, KASARAGOD.

     4       SUPERINTENDING ENGINEER
             PWD BUILDINGS (NORTH) CIRCLE, KOZHIKODE.

     5       CHIEF ENGINEER
             PWD BUILDINGS, THIRUVANANTHAPURAM.

     6       STATE OF KERALA
             REPRESENTED BY SECRETARY, PUBLIC WORKS DEPARTMENT,
             THIRUVANANTHAPURAM.


             BY ADV.

             SRI.TONY AUGUSTINE, GOVERNMENT PLEADER


      THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON   04.08.2025,      THE   COURT   ON       THE   SAME   DAY   DELIVERED   THE
FOLLOWING:
                                                      2025:KER:58206
                                    3
W.P.(C) No.21326 of 2016


                           JUDGMENT

Original writ petitioner was awarded the work of construction

of Sub Registrar office building at Rajapuram in Kasaragode under

an agreement dated 01.02.2006. Period fixed for completion of

the work was nine months and the probable amount of contract

was Rs.7,60,395/-. Original writ petitioner could not carry out the

work within the period of nine months. He fell ill. On account of his

poor health condition, he made a request to relieve him. During

the pendency of this Writ petition, the original petitioner expired

and wife and children got impleaded to prosecute the Writ Petition

further.

2. It was contended that the delay in conducting the work

and completing the same was on account of the change of design

and time taken for obtaining revised administrative sanction.

Contractor approached the Hon'ble Minister for Public Works and

submitted a representation requesting to relieve him from the

contract without any liabilities.

3. On 09.03.2012, the 3rd respondent issued Ext.P6 notice

to the contractor fixing a liability of Rs.13,06,726/-. Contractor

submitted a reply to Ext.P6 on 28.03.2012. He again addressed 2025:KER:58206

the Hon'ble Minister. However, the 4th respondent issued final

notice and terminated the contract. By the letter dated

31.10.2015 issued in this regard, liability of Rs.25,83,698/- was

fixed on the contractor/original petitioner after deducting the

security deposit of Rs.39,000/-. Ext.P8, the PAC after

rearrangement of the work has been shown as Rs.33,83,093/-.

Original PAC before rearrangement was Rs.7,60,395/-. Final

liability was calculated as Rs.26,22,698/-. Less security, the

liability was fixed at Rs.25,83,698/-. Work was thereafter

rearranged. Revenue recovery proceedings were initiated for

recovery of the amount as fixed in Ext.P8. The Writ Petition was

filed challenging Ext.P8 and P10 revenue recovery notice. The 3 rd

respondent filed a detailed counter affidavit disputing the

contentions of the petitioner.

4. Heard the learned counsel appearing for the petitioner

and the learned Government Pleader for the respondents.

5. Learned counsel for the petitioner mainly raised a

contention that the work was rearranged in 2015 following the

schedule of rates in 2012. The learned counsel pointed out that

the original work was as per the schedule of rates of 2004. He 2025:KER:58206

submitted that it is highly unjust and improper to calculate the

risk and cost and fix liability on the basis of the revised schedule

of rates as the original work was awarded following the schedule

of rates of 2004 which was much less. The learned counsel relied

on circular dated 08.08.2023 issued by the PWD wherein it has

been stated that balance estimate of the work terminated at the

risk and cost needs to be prepared using the same schedule of

rates with which the original estimate was prepared. The learned

counsel also pointed out that in the PWD Manual also it has been

provided that rearrangement of works should be done as

expeditiously as possible and there should not be any substantial

changes in the specifications on the balance works rearranged.

The learned counsel further contended that only 38 items of work

were included in the original agreement whereas in the revised

agreement total number of 54 items of works were included.

Hence he contended that the PAC after rearrangement of work

was for 54 items of work instead of 38 items of work which were

originally contemplated. He hence submitted that the calculation

of final liability is therefore incorrect, unjust and improper. He 2025:KER:58206

submitted that Ext.P8 and further proceedings for recovery are not

legally sustainable.

6. The learned Government Pleader submitted that the

petitioner failed to execute the work within the stipulated time

limit without any justifiable reasons. Other than the poor health

condition, no reason sufficient for excusing the petitioner from the

responsibility was pointed out. He submitted that as narrated in

the counter affidavit, the petitioner did not start the work within

the agreement period and hence the work was terminated by

order dated 04.12.2007. On the basis of the request of the

original petitioner, the termination was revoked. Even after

revocation, he didn't turn up to start the work. Thereafter he

explained his inability to execute the work. Hence the contract was

terminated with cost by proceedings dated 15.11.2010. The

learned Government Pleader pointed out that as per the provisions

of the contract vide Clause No.13 of notice inviting tender, the

contractor was liable for the cost of rearrangement of the work.

The learned Government Pleader further submitted that as per the

terms of the contract, the contractor was liable to pay for the loss

sustained by the Government for rearrangement of the work. He 2025:KER:58206

also pointed out that there was no delay on the part of the

Department in obtaining administrative sanction as contended in

the Writ Petition. He made specific reference to the contents of

paragraph No.5 of the counter affidavit in this regard.

7. After hearing the learned counsel for the petitioner as

also the learned Government Pleader, I am of the view that in

view of the specific contentions raised by the leaned counsel for

the petitioner that more items of work were included when the

work was rearranged and the entire amount for rearrangement of

work, calculated on the basis of the 54 items of work was not

liable to be taken into account as the original agreement was only

for 38 items of work needs to be considered by the Executive

Engineer. It is not discernible on a reading of Ext.P8 as to whether

the inclusion of additional items of work was taken into account by

the Executive Engineer while fixing liability on the contractor.

8. It is also to be noted that the learned counsel for the

petitioner pointed out the circular issued by the Department on

08.08.2023 which stipulates that the balance estimate of the

works terminated at the risk and cost needs to be prepared using

the same SOR in which the original estimate was prepared.

2025:KER:58206

9. The learned Government Pleader submitted that the

said circular was issued only in 2014 and therefore the benefit of

the circular cannot be claimed by the petitioners. Learned counsel

for the petitioner responded stating that the said practice was

followed before the issuance of the circular and the Executive

Engineer overlooked the same while issuing Ext.P8. This aspect

also needs to be considered by the Executive Engineer.

10. To facilitate such a reconsideration of the entire issue

by the Executive Engineer, I set aside Ext.P8. The Executive

Engineer shall reconsider the matter and take a fresh decision. In

order to ensure fairness in the decision making process, I direct

that the Executive Engineer shall provide opportunity of hearing to

the additional petitioners or their representative before taking a

fresh decision in the matter. Additional petitioners shall be free to

raise all available contentions before the Executive Engineer. All

relevant aspects shall be taken note of by the Executive Engineer

before taking a fresh decision. The Executive Engineer shall issue

notice to the additional petitioners after fixing a date for hearing.

The entire exercise shall be completed and a fresh decision shall

be taken within a period of four months from the date of receipt of 2025:KER:58206

a copy of this judgment. Needless to say, as I set aside Ext.P8,

revenue recovery proceedings initiated on the basis of same shall

also stand quashed.

With the above directions, the Writ Petition is disposed of.

Sd/-

S.MANU JUDGE PV 2025:KER:58206

APPENDIX OF WP(C) 21326/2016

PETITIONER EXHIBITS

EXHIBIT P1 TRUE COPY OF THE SCHEDULE OF WORKS TO BE DONE ALONG WITH PLAN.

EXHIBIT P2 TRUE COPIES OF THE MEDICAL REPORTS OF THE PETITIONER.

EXHIBIT P3 TRUE COPY OF THE LETTER DT.19-2-2009 OF R3 TO R4 TO TAKE DECISION TO RELIEVE THE PETITIONER FOR CONTRACT.

EXHIBIT P4 TRUE COPY OF THE LETTER DT.27-2-2009 OF R4 TO R5 TO RELIEVE THE PETITIONER FOR THE CONTRACT.

EXHIBIT P5 TRUE COPY OF THE REPRESENTATION DT.6-2- 2009 OF PETITIONER ADDRESSED TO THE HON'BLE MINISTER.

EXHIBIT P6                 TRUE COPY OF THE LETTER DT.9-3-2012 OF R3
                           TO   THE    PETITIONER   INTIMATING   THE
                           LIABILITY AS RS.13,06,726/-
EXHIBIT P6A                TRUE COPY OF THE REPLY DT.28-3-2012 OF
                           THE PETITIONER ADDRESSED TO R3.
EXHIBIT P7                 TRUE COPY OF THE REPRESENTATION TO THE
                           HON'BLE MINISTER THROUGH THE MLA
EXHIBIT P8                 TRUE COPY OF THE LETTER DT.31-10-2015 OF
                           R3 FIXING THE LIABILITY AS RS.25,83,698/-
EXHIBIT P9                 TRUE COPY OF THE AGREEMENT SCHEDULE AND
                           PLAN OF THE SUBSEQUENTLY ARRANGED WORK.
EXHIBIT P10                TRUE COPY OF THE DEMAND NOTICE DT.31-5-
                           2016 ISSUED BY R2 UNDER REVENUE RECOVERY
                           ACT.
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter