Friday, 17, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

P.T.Davis vs Power Grid Corporation Of India Ltd
2024 Latest Caselaw 9845 Ker

Citation : 2024 Latest Caselaw 9845 Ker
Judgement Date : 5 April, 2024

Kerala High Court

P.T.Davis vs Power Grid Corporation Of India Ltd on 5 April, 2024

Author: V.G.Arun

Bench: V.G.Arun

             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                              PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
    FRIDAY, THE 5TH DAY OF APRIL 2024 / 16TH CHAITHRA, 1946
                        CRP NO. 315 OF 2021
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.356 OF 2013 OF I
                ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

            POWER GRID CORPORATION OF INDIA,
            SENIOR GENERAL MANAGER (COCHIN), CONSTRUCTION AREA
            OFFICE, MAVELIPURAM COLONY, KAKKANAD, ERNAKULAM-682
            030.
            BY ADV ANJANA KANNATH


RESPONDENT/S:

    1       P.T.DAVIS,
            AGED 48 YEARS
            S/O.P.P.THOMAS, PALATTY HOUSE, MAJAPRA VILLAGE,
            ANGAMALY-683 581.
    2       SPECIAL TAHSILDAR (LA),
            POWER GRID CORPORATION OF INDIA LTD., CHEVARAMBALAM,
            KOZHIKODE-17.
            BY ADV P.T.JOSE


OTHER PRESENT:

            SR.GP.V.TEKCHAND;SC FOR KSEB A.ARUNKUMAR;SC FOR
            POWERGRID MILLU DANDAPANI


        THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
15.01.2024, ALONG WITH CRP.335/2021, THE COURT ON 05.04.2024
DELIVERED THE FOLLOWING:
 CRP Nos.315 & 335/2021

                                 -2-



              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
    FRIDAY, THE 5TH DAY OF APRIL 2024 / 16TH CHAITHRA, 1946
                         CRP NO. 335 OF 2021
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.356 OF 2013 OF VI
                ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

             P.T.DAVIS
             AGED 47 YEARS
             S/O.P.P.THOMAS, PALATTY HOUSE, MANJAPRA P.O.,
             ANGAMALY - 683 581.
             BY ADVS.
             P.T.JOSE
             S.ASHITHA


RESPONDENT/S:

     1       POWER GRID CORPORATION OF INDIA LTD
             CONSTRUCTION AREA OFFICE, KAKKANAD, NOW IN PAO/400,
             220KV SUBSTATION, KUMARAPURAM P.O., PALLIKKARA,
             KOCHI - 682 303 REP. BY DEPUTY MANAGER.
     2       THE SPECIAL TAHSILDAR (LA)
             POWERGRID CORPORATION OF INDIA LTD., CHEVARAMBALAM,
             KOZHIKODE, NOW IN KAKKANAD P.O. - 682 030.
     3       ADDL.R3 - STATE OF KERALA
             REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI
             - 68230.
     4       ADDL.R4 - KERALA STATE ELECTRICITY BOARD
             REPRESENTED BY CHAIRMAN AND MANAGING DIRECTOR, KSHB
             LTD., THIRUVANANTHAPURAM.
             BY ADV ANJANA KANNATH


         THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
15.01.2024, ALONG WITH CRP.315/2021, THE COURT ON 05.04.2024
DELIVERED THE FOLLOWING:
 CRP Nos.315 & 335/2021

                                 -3-



                               ORDER

Dated this the 05th day of April, 2024

These revision petitions are filed

challenging the order passed by the Additional

District Judge-VI, Ernakulam in O.P.(Electricity)

No.356 of 2013. The original petition was filed

by the revision petitioner in CRP No.335 of 2021

(hereinafter called 'the claimant'), being

dissatisfied with the compensation awarded

towards the damage and loss sustained due to the

drawing of 400 KV lines across his property by

the Power Grid Corporation of India Ltd

(hereinafter called 'the Corporation'). The

essential facts are as under;

The claimant is in ownership and possession

of landed property having an extent of 1 Acre 12

cents comprised in Sy.Nos.596/6 and 596/7 in

Block No.20 of Manjapra Village in Aluva Taluk.

The land was cultivated with various yielding and CRP Nos.315 & 335/2021

non-yielding trees. According to the claimant, to

facilitate drawing of the lines and smooth

transmission of power, large number of trees were

cut from his property. The drawing of high

tension lines rendered the land underneath and

adjacent to the lines useless, resulting in

diminution of the value of the property. In spite

of the huge loss suffered by the claimant, only

an amount of Rs.1,83,178/- was paid as

compensation towards the value of yielding and

non-yielding trees cut. Surprisingly, no

compensation was granted for diminution in land

value. Hence, the original petition was filed,

seeking enhanced compensation towards the value

of trees cut and diminution in land value.

2. The court below rejected the claim for

enhanced compensation for the value of trees cut

since no evidence in support of the claim was

produced. As far as the claim for enhanced

compensation towards diminution in land value is

concerned, the court below relied on Ext.A13 CRP Nos.315 & 335/2021

document as well as Exts.C3 and C3(a) commission

report and plan. The Advocate Commissioner

reported that the Patricks Academy, Primary

Health Centre, Government Homeo Dispensary,

Government Hospital, Government High School and

Jyothis Central School etc are situated within

close proximity to the claimant's property. The

court took note of the fact that while the

property in Ext.A13 document is having public

roads on the northern side, the petition schedule

property has no direct public road access. Based

on these factors, the court below fixed the land

value of the claimant's property by deducting 10%

of the land value shown in Ext.A13 document. The

court below also took note of the fact that no

electric line has been drawn across the petition

schedule property. Relying on Ext.C3(a) plan, the

extent of outer corridor, which passes through

the extreme western side of the claimant's

property, was held to be 8.846 cents. The court

also noted that the remaining portion of land was CRP Nos.315 & 335/2021

not affected since the only outer corridor passes

through the extreme western side of the petition

schedule property. For the outer corridor, 20%

of the land value was granted as compensation.

Accordingly, the claimant was found entitled to

compensation of Rs.3,58,386/-. Dissatisfied with

the quantum of enhancement, the claimant has

filed CRP No.335 of 2021, whereas the Corporation

has filed CRP No.315 of 2021 contending that the

enhancement ordered is far in excess of the

actual damage sustained.

3. Heard Adv.P.T.Jose for the claimant and

Adv.Millu Dandapani for the Corporation.

4. Learned Counsel for the claimant

contended that the court below committed gross

illegality in refusing to grant enhanced

compensation for the loss sustained due to the

cutting of valuable trees, in spite of the

Advocate Commissioner assessing and reporting the

loss. It is submitted that the Patricks Academy,

Primary Health Centre, Government Homeo CRP Nos.315 & 335/2021

Dispensary, Government Hospital, Government High

School and Jyothis Central School etc are

situated within close proximity to the claimant's

property. Without considering these crucial

factors, 10% deduction was made from the value of

the property involved in Ext.A13 document.

5. It is further submitted that the court

below grossly erred in granting only 20% of the

land value as compensation for the outer

corridor. Considering the extent of damage

sustained and the diminution in land value

consequent to the drawing of lines, the court

below ought to have granted compensation as

claimed.

6. Learned Counsel for the Corporation

contended that, compensation towards diminution

in land value granted is exorbitant. The court

below also erred in relying on Ext.A13 for fixing

the land value of the claimant's property. As

there is no electric line drawn across the

petition schedule property, 20% of the land value CRP Nos.315 & 335/2021

granted for the outer corridor as compensation is

exorbitant.

7. A careful scrutiny of the impugned order

reveals that the claim for enhancement of

compensation towards the value of trees cut was

rightly rejected since no supporting material,

other than the findings in the Advocate

Commissioner's report, was made available. The

court below also took note of the fact that even

the Commissioner could not see any trees or stump

of the trees at the time of inspection.

Therefore, the court below rightly held that the

evidence let in by the claimant was not

sufficient to discard the contemporaneous

valuation statement prepared, by the Corporation.

8. As far as the diminution in land value

is concerned, the factors to be taken into

consideration, as laid down in KSEB v. Livisha

[(2007) 6 SCC 792] are as under;

"10. The situs of the land, the distance between the high voltage CRP Nos.315 & 335/2021

electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."

On careful scrutiny of the impugned order, it is

seen that the compensation was enhanced after

taking all the above factors into consideration.

The nature of the land, the cultivation therein,

the commercial importance of the area and the

manner in which the land was affected by drawing

of the lines are all seen considered in fixing

the land value as well as the percentage of

diminution. The court below has deducted only 10%

of the land value shown in Ext.A13, which

according to me, is reasonable. The discretion

was properly exercised in granting 20% of the CRP Nos.315 & 335/2021

land value as compensation for the outer

corridor.

9. Having held as above, I find a patent

mistake in the order, which is liable to be

corrected in exercise of this Court's revisional

jurisdiction. It is seen that initially the

Corporation had paid Rs.1,83,178/- towards the

value of trees cut alone and had refused to pay

any amount towards diminution in land value. As

per the impugned order, the court below rejected

the claim for enhancement of compensation towards

value of trees cut and awarded compensation

towards diminution in land value. Even though the

court below did not grant compensation for the

value of trees cut, the impugned order contains a

direction to deduct the compensation already paid

from the enhanced compensation awarded. This may

be interpreted as a direction to deduct the

compensation initially paid towards value of

trees from the compensation towards diminution in

land value granted by the court below. The CRP Nos.315 & 335/2021

impugned order, to that extent, need to be

corrected.

For the aforementioned reasons, the civil

revision petition filed by the claimant is

allowed in part. The direction in the impugned

order, to deduct the compensation already paid

from the enhanced compensation is deleted. The

enhanced compensation awarded by the court below

shall be paid within three months, without any

deduction. If any amount is deposited pursuant to

the order of this Court or otherwise, the same

shall forthwith be released to the claimant on

his filing appropriate application.

The civil revision petition filed by the

Corporation is dismissed.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter