Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

P.K.Ramachandran vs State Of Kerala
2023 Latest Caselaw 3374 Ker

Citation : 2023 Latest Caselaw 3374 Ker
Judgement Date : 24 March, 2023

Kerala High Court
P.K.Ramachandran vs State Of Kerala on 24 March, 2023
           IN THE HIGH COURT OF KERALA AT ERNAKULAM
                            PRESENT
         THE HONOURABLE MR. JUSTICE A.MUHAMED MUSTAQUE
                               &
        THE HONOURABLE MRS. JUSTICE SHOBA ANNAMMA EAPEN
  FRIDAY, THE 24TH DAY OF MARCH 2023 / 3RD CHAITHRA, 1945
                      RFA NO. 270 OF 2017
   AGAINST THE JUDGMENT AND DECREE DATED 29.10.2015 IN
  O.S.NO.85/2007 OF III ADDITIONAL SUB COURT, ERNAKULAM
                            ------
APPELLANTS/DEFENDANTS:

   1     THE STATE OF KERALA, REPRESENTED BY THE SECRETARY
         TO GOVERNMENT, PUBLIC WORKS DEPARTMENT, GOVERNMENT
         SECRETARIAT, THIRUVANANTHAPURAM.
   2     THE SUPERINTENDING ENGINEER, P.W.D.BUILDINGS &
         LOCAL WORKS, CENTRAL CIRCLE, T.B.ROAD, THRISSUR.

         BY SENIOR GOVERNMENT PLEADER, SRI.B.UNNIKRISHNA
         KAIMAL


RESPONDENT/PLAINTIFF:

  **1   P.K.RAMACHANDRAN, AGED 74 YEARS, S/O.KUNJU
        PANICKER, RESIDING AT DEEPA MANDIR KARUVELIPADY,
        KOCHI, THOPPUMPADY VILLAGE, KOCHI TALUK,
        ERNAKULAM.(DIED)
Addl.R2 A.R.DEEPA, SREELAKSHMI PRRA-9 PALLICHAMBEL ROAD,
        PALARIVATTOM P.O., KOCHI-682025.
Addl.R3 A.R.DENOOP, DEEPA MANDIR, KARUVELIPADY,
        THOPPUMPADY P.O., KOCHI-682005.
       BY ADVS.
       K.BABU THOMAS
       MARYKUTTY BABU

THIS REGULAR FIRST APPEAL HAVING BEEN FINALLY HEARD ON
17.01.2023, ALONG WITH RFA NO.374/2017, THE COURT ON
24.03.2023 DELIVERED THE FOLLOWING:
 RFA Nos.270 & 374/2017             ..2..




               IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
            THE HONOURABLE MR. JUSTICE A.MUHAMED MUSTAQUE
                                  &
           THE HONOURABLE MRS. JUSTICE SHOBA ANNAMMA EAPEN
        FRIDAY, THE 24TH DAY OF MARCH 2023 / 3RD CHAITHRA, 1945
                          RFA NO.374 OF 2017
         AGAINST THE JUDGMENT AND DECREE DATED 29.10.2015 IN
        O.S.NO.85/2007 OF III ADDITIONAL SUB COURT, ERNAKULAM
APPELLANT/PLAINTIFF:

   *1   P.K.RAMACHANDRAN, DEEPA MANDIR, KARUVELIPADY,
        THOPPUMPADY P.O., KOCHI TALUK, ERNAKULAM, KOCHI-682005.
Addl.A2 A.R.DEEPA, D/O.LATE P.K.RAMACHANDRAN,
        AGED 53 YEARS, SREELAKSHMI, PRRA-9, PALLICHAMBEL ROAD,
        PALARIVATTOM P.O., KOCHI-682025.
Addl.A3 A.R.DENOOP, AGED 45 YEARS,
        S/O.LATE P.K. RAMACHANDRAN, DEEPA MANDIR, KARUVELIPADY,
        THOPPUMPADY P.O. KOCHI -682005.
        (THE LEGAL REPRESENTATIVES OF THE DECEASED SOLE
        APPELLANT ARE IMPLEADED IN THE PARTY ARRAY AS
        ADDITIONAL APPELLANTS 2 AND 3 VIDE ORDER DTD.01/08/2018
        IN IA 1224/2018
        BY ADVS.
        SRI.K.BABU THOMAS
        SMT.MARYKUTTY BABU

RESPONDENTS/DEFENDANTS:

    1      STATE OF KERALA, REPRESENTED BY THE SECRETARY TO
           GOVERNMENT, PUBLIC WORKS DEPARTMENT, GOVERNMENT
           SECRETARIAT, THIRUVANANTHAPURAM-695001.
    2      THE SUPERINTENDING ENGINEER, P.W.D.BUILDINGS & LOCAL
           WORKS, CENTRAL CIRCLE, T.B.ROAD, THRISSUR-680001.

           BY SENIOR GOVERNMENT PLEADER, SRI.B.UNNIKRISHNA KAIMAL

THIS REGULAR FIRST APPEAL HAVING BEEN FINALLY HEARD ON
17.01.2023, ALONG WITH RFA.NO.270/2017, THE COURT ON 24.03.2023
DELIVERED THE FOLLOWING:
 RFA Nos.270 & 374/2017            ..3..



      A.MUHAMED MUSTAQUE & SHOBA ANNAMMA EAPEN, JJ.
   ----------------------------------------------
             RFA Nos.270 & 374 of 2017
   ----------------------------------------------
       Dated this the 24th day of March, 2023


                            JUDGMENT

A.Muhamed Mustaque, J.

These appeals arise from the judgment of the

Sub Court, Ernakulam in O.S.No.85/2007 dated

29.10.2015.

2. The above suit was for declaration and

realization of money based on the contract entered

between the plaintiff and the State Public Works

Department, the defendants in the suit. The suit

has been decreed substantially in favour of the

plaintiff. These appeals are preferred by the

plaintiff and the defendants. The parties, for

brevity, in these appeals are referred to as the

plaintiff and the defendants.

3. The plaintiff was awarded a work for the

construction of 350 bedded ward of an Ayurveda RFA Nos.270 & 374/2017 ..4..

hospital at Thripunithura on 09.09.1997. The

period of the contract was 24 months. The work was

completed on 14.12.2005. The suit was laid for the

unpaid value of the work. The plaintiff's claim

and the claim allowed by the trial court can be

summarized as follows:

Nature of claim Plaint claim Allowed by the trial court The unpaid value of Rs.2,35,46,148/- Rs.2,35,46,148/-

 the work carried out
 between     21.9.1999
 and 1.12.2004 based
 on 1996 PWD Schedule
 and     1999      PWD
 schedule rate.
 The unpaid value of Rs.47,84,011/-           Rs.45,29,922/-
 the work carried out
 between     1.12.2004
 and 14.12.2005.
 Unpaid agreed       rate Rs.89,70,231/-      Rs.87,60,427/-
 for   flooring      with
 marble tiles.
 Unpaid    value    of Rs.15,72,751/-         Rs.15,72,752/-
 works   using   semi-
 wire cut bricks in
 the place of country
 burnt bricks.
 Interest    on    delayed Rs.75,48,807/-     Rs.22,48,751/-
 payment
 The value of cement Rs.10,57,446/-           Rs.10,57,446/-
 procured   from the
 open market
 RFA Nos.270 & 374/2017                ..5..



4. Heard the learned counsel appearing for

the plaintiff and the learned Government Pleader.

5. We note that there was a considerable

delay in handing over the site and in supplying

materials as agreed. No one has a case that the

plaintiff had committed any default. The plaintiff

was paid a sum of Rs.9,29,06,994/- pending suit on

16.02.2009. The final bill was prepared on

25.11.2005. Though an argument has been raised by

the learned Government Pleader based on

limitation, in the light of the fact that the

final bill itself was prepared only in the year

2005 and the suit was filed on 01.02.2007, we find

no merit in this argument. We, thus, overrule the

argument of the learned Government Pleader.

6. The following issues were framed by the

court below:

1.Whether the plaintiff had made construction as

per the agreement or not.

2. Whether the plaintiff is entitled to get a RFA Nos.270 & 374/2017 ..6..

decree for realization of the amount

claimed.

7. We have already overruled the objection of

the learned Government Pleader on the point raised

on the limitation. According to the learned

Government Pleader, the plaintiff received the

money after the final bill. The plaintiff also

executed a supplemental agreement and in the light

of the supplemental agreement and the acceptance

of the final bill, the contractor cannot claim any

other amount other than as agreed in the

agreement.

8. The learned Government Pleader referred to

the following Clauses in the supplemental

agreement:

Clause-3 in supplemental agreement No.1 is as

follows:

"The decision of the Superintending Engineer regarding the amounts payable for the extra item shall be final and legally binding on the contractor and cannot be questioned by the RFA Nos.270 & 374/2017 ..7..

contractor in any manner whatsoever."

The recital in the supplemental agreement No.7 is

as follows:

"whereas the contractor further agreed that no further claim will be preferred on account of extension of the period of the contract".

Clause 2 in supplemental agreement No.8 is as

follows:

"The contractor shall not claim any enhanced rate or compensation whatsoever for or on account of such extra items due to the increased rate of labour or materials or any other ground."

The proceedings of the Superintending Engineer and

his order dated 19.4.2020, in Clause 1, states

that due to the extension of time for completion,

no claim for enhanced rate will be allowed for the

work.

9. While allowing the claim, the trial court

relied on the opinion of the expert's report. The RFA Nos.270 & 374/2017 ..8..

rates were quoted in accordance with the 1996

schedule by 60% in July 1999 and 80% in December,

2004. The expert, accordingly, calculated the

measured work and found that the plaintiff was

entitled to a sum of Rs.2,73,33,999/- as against

the claim for Rs.2,35,46,148/-. The question is

whether the plaintiff is entitled to an enhanced

claim in the light of the change of the PWD

schedule of rates.

10. The learned counsel for the plaintiff

Sri.Babu Thomas, placing reliance on the judgments

in M/s.Aries and Aries v. Tamil Nadu Electricity

Board [AIR 2017 SC 1897] and Assam State

Electricity Board and others v. Buildworth

Pvt.Ltd. [AIR 2017 SC 3336], argued that the

plaintiff is entitled to escalation charges for

the works delayed beyond the scheduled period of

completion if the plaintiff is not at fault in

completing the work.

11. The contract provisions have to be read RFA Nos.270 & 374/2017 ..9..

keeping in mind the duty attached to the parties

to the contract to perform the contract in

accordance with the terms and conditions in the

contract. The various clauses referred to as above

cannot deter the plaintiff from claiming

escalation charges if the delay was not occasioned

by the act of the plaintiff. In this case, the

site was handed over to the plaintiff after two

years. The materials were not supplied as per the

agreement. No attribution of the fault has been

made as against the plaintiff. The trial court

correctly came to the conclusion that the delay

was occasioned by the PWD itself. In P.M.Paul v.

Union of India [1989 supp.(1) scc 368], the apex

court opined that escalation is a normal incident

arising out of a gap of time in this inflationary

age in performing any contract. No one has a case

that a calculation made by experts based on the

prevalent schedule is erroneous. In such

circumstances, we affirm the impugned judgment RFA Nos.270 & 374/2017 ..10..

awarding unpaid value work for Rs.2,35,46,148/-

and Rs.45,29,922/-.

12. The next claim is for the value of

marble. As per the contract, the agreed rate for

flooring the marble tiles included in item No.49

of the schedule of works, the plinth area was

10564.15 sq. m. The rate agreed was 1073.38 per

sq.m.. The plaintiff admittedly carried out the

marble flooring in the additional area. As per the

expert report, the total area is 11169.45 sq.m.

The plaintiff was paid for 10564.15 sq.m. in 2004.

The expert opined that for the additional work

done, the plaintiff was entitled to

Rs.87,60,427/-. We do not find any error in the

calculation of this amount.

13. The next claim was for the unpaid value of

the work using semi-wire cut bricks in the place

of country bricks. The expert calculated the total

value of the semi-wire cut machinery at

Rs.56,72,560/-. The plaintiff was paid RFA Nos.270 & 374/2017 ..11..

Rs.40,99,808/-. The balance has thus arrived at

Rs.15,72,752/-. We also affirm the finding of the

trial court.

14. The next claim was for reimbursement of

the materials procured from the open market.

Exts.A9, A14, A20, A33, A38, A41, A42, A43, A62,

A63, A65, A70 and A78 were relied by the plaintiff

to substantiate his claim. The above are

communications issued by the plaintiff. There is

no contradiction of the claim for these amounts as

referred to in the above letters. Admittedly, the

Department failed to provide the materials in

time. We, thus, affirm that finding also.

15. The plaintiff filed a claim for

Rs.75,48,807/- towards interest for the delayed

payment. The court below allowed Rs.22,48,751/-

towards interest for the delayed payment. This

was subsequently incorporated in the original

decree as it appears that there was an omission to

include it in the judgment pronounced on RFA Nos.270 & 374/2017 ..12..

29.10.2015. This portion was included only on

05.07.2016 as per the order in I.A. No.980/2016.

It is seen from the judgment, 6% interest was

allowed. The amount was calculated at

Rs.22,48,751/- and subsequently incorporated in

the decree. This can be treated as a clerical

mistake and no illegality has been committed by

the court below in calculating the interest.

16. The claim for the plaintiff that he is

entitled to the enhanced rate of interest is

untenable as it is not a commercial transaction.

However, the plaintiff is entitled to pendente

lite interest at 6% and future interest. So also

the plaintiff is entitled to the cost before the

court below though it was not granted by the trial

court. Thus:

I. RFA 270/2017 is dismissed. No order as

to costs.

II. RFA No.374/2017 is partly allowed.

The plaintiff is entitled to pendente lite RFA Nos.270 & 374/2017 ..13..

and future interest at 6% till realization

of decree on the reliefs granted other

than for the decreed amount of

Rs.22,48,571/- ordered to be paid towards

interest.

III. The plaintiff is also entitled to the

proportionate cost in the trial court.

The plaintiff is also entitled to

proportionate cost in the appeal.

Sd/-

A.MUHAMED MUSTAQUE, JUDGE

Sd/-

                                          SHOBA ANNAMMA EAPEN, JUDGE

ln
 RFA Nos.270 & 374/2017         ..14..




                    APPENDIX OF RFA 270/2017

PETITIONER ANNEXURES
ANNEXURE I         TRUE COPY OF SIGNED MEASUREMENT BOOK
                   DATED 09.02.2009.
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter