Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sivaprasad B vs The Kerala Water Authority
2023 Latest Caselaw 3350 Ker

Citation : 2023 Latest Caselaw 3350 Ker
Judgement Date : 24 March, 2023

Kerala High Court
Sivaprasad B vs The Kerala Water Authority on 24 March, 2023
            IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                PRESENT
            THE HONOURABLE MR. JUSTICE SHAJI P.CHALY
  FRIDAY, THE 24TH DAY OF MARCH 2023 / 3RD CHAITHRA, 1945
                     WP(C) NO. 34088 OF 2022
PETITIONER:

            REENA ENGINEERING AND CONTRACTING
            COMPANY PVT. LTD.
            602,
            SHIV TOWER,
            PATTO PLAZA,
            PANAJI, GOA,
            REP. BY ITS MANAGING DIRECTOR,
            PIN - 403001
            BY ADVS.P.SHANES METHAR
                    N.KRISHNA PRASAD

RESPONDENTS:

    1       KERALA WATER AUTHORITY
            JALA BHAVAN,
            VELLAYAMBALAM,
            THIRUVANANTHAPURAM,
            REP. BY ITS MANAGING DIRECTOR,
            PIN - 695033
    2       THE SUPERINTENDING ENGINEER
            O/O. SUPERINTENDING ENGINEER,
            KERALA WATER AUTHORITY,
            P H CIRCLE (KOZHIKODE),
            MALAPARAMBA.P.O.,
            KOZHIKODE,
            PIN - 673009
            BY SRI. V.V. JOSHI, STANDING COUNSEL

     THIS     WRIT   PETITION    (CIVIL)     HAVING   COME   UP   FOR
ADMISSION ON     24.03.2023, ALONG        WITH W.P.(C.)NO.4905/2023
AND CONNECTED CASES, THE COURT ON THE SAME DAY DELIVERED
THE FOLLOWING:
 W.P.(C.) No. 34088 of 2022
& connected cases                   2




              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                   PRESENT
              THE HONOURABLE MR. JUSTICE SHAJI P.CHALY
   FRIDAY, THE 24TH DAY OF MARCH 2023 / 3RD CHAITHRA, 1945
                        WP(C) NO. 42505 OF 2022
PETITIONER:

              MOTTY T. ULAHANNAN
              AGED 57 YEARS
              S/O. O.T. ULAHANNAN,
              CONTRACTOR,
              URUMBETH HOUSE,
              NEAR RAILWAY STATION,
              KOTTAYAM-686 001.
              BY ADVS.BABU JOSEPH KURUVATHAZHA
                      MOHAMMED SHAFI.K

RESPONDENTS:

     1        KERALA WATER AUTHORITY,
              JALA BHAVAN, NANDAVANAM,
              VELLAYAMBALAM,
              THIRUVANANTHAPURAM-695 033,
              REPRESENTED BY ITS MANAGING DIRECTOR.
     2        SUPERINTENDING ENGINEER,
              KERALA WATER AUTHORITY,
              PUBLIC HEALTH CIRCLE, KOTTAYAM-686 001.
              BY SRI. P.M.JOHNY,        STANDING COUNSEL
              BY SRI. V.V. JOSHI, STANDING COUNSEL



       THIS    WRIT     PETITION    (CIVIL)    HAVING   COME   UP   FOR
ADMISSION ON 24.03.2023, ALONG WITH W.P.(C.)NO.34088/2022
AND CONNECTED CASES, THE COURT ON THE SAME DAY DELIVERED
THE FOLLOWING:
 W.P.(C.) No. 34088 of 2022
& connected cases                   3




              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                   PRESENT
              THE HONOURABLE MR. JUSTICE SHAJI P.CHALY
   FRIDAY, THE 24TH DAY OF MARCH 2023 / 3RD CHAITHRA, 1945
                         WP(C) NO. 4905 OF 2023
PETITIONER:

              B.UNNIKRISHNAN NAIR,
              SAROVILLA, KADAVILA,
              VANCHIYOOR P.O., ALAMCODE, ATTINGAL,
              THIRUVANANTHAPURAM DISTRICT, PIN - 695102
              BY ADVS.V.PREMCHAND
                      SURYA MOHAN P.
                      FATHIMA SHALU S.

RESPONDENTS:

     1        THE KERALA WATER AUTHORITY,
              JALABHAVAN, REPRESENTED BY ITS MANAGING DIRECTOR,
              THIRUVANANTHAPURAM, PIN - 695033
     2        THE SUPERINTENDING ENGINEER,
              KERALA WATER AUTHORITY,
              AALTHARA JUNCTION, NANADHAVANAM, PALAYAM,
              THIRUVANANTHAPURAM, PIN - 695033
     3        THE EXECUTIVE ENGINEER,
              KERALA WATER AUTHORITY,
              AALTHARA JUNCTION, NANADHAVANAM,PALAYAM,
              THIRUVANANTHAPURAM, PIN - 695033
              BY SRI. P.M.JOHNY, STANDING COUNSEL
              BY SRI. V.V. JOSHI, STANDING COUNSEL

       THIS    WRIT     PETITION    (CIVIL)   HAVING   COME   UP   FOR
ADMISSION ON 24.03.2023, ALONG WITH W.P.(C.)NO. 34088/2022
AND CONNECTED CASES, THE COURT ON THE SAME DAY DELIVERED
THE FOLLOWING:
 W.P.(C.) No. 34088 of 2022
& connected cases                   4




              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                   PRESENT
              THE HONOURABLE MR. JUSTICE SHAJI P.CHALY
   FRIDAY, THE 24TH DAY OF MARCH 2023 / 3RD CHAITHRA, 1945
                         WP(C) NO. 4961 OF 2023
PETITIONER:

              VINOD KUMAR. R,
              AGED 53 YEARS
              S/O BHASKARANPILLAI,
              RESIDING AT KOICKALATHU HOUSE,
              ADINADU SOUTH, KATTILKADAVU P O,
              KARUNAGAPALLY, KOLLAM DISTRICT.,
              PIN - 690542
              BY ADVS.V.PREMCHAND
                      SURYA MOHAN P.
                      FATHIMA SHALU S.

RESPONDENTS:

     1        THE KERALA WATER AUTHORITY,
              JALA BHAVAN,
              REPRESENTED BY ITS MANAGING DIRECTOR,
              THIRUVANANTHAPURAM, PIN - 695033
     2        THE SUPERINTENDING ENGINEER,
              KERALA WATER AUTHORITY,
              P H CIRCLE, ALAPPUZHA DISTRICT,
              PIN - 688001
              BY SRI.    V.V. JOSHI, STANDING COUNSEL

       THIS    WRIT     PETITION    (CIVIL)   HAVING   COME   UP   FOR
ADMISSION ON 24.03.2023, ALONG WITH W.P.(C.)NO.34088/2022
AND CONNECTED CASES, THE COURT ON THE SAME DAY DELIVERED
THE FOLLOWING:
 W.P.(C.) No. 34088 of 2022
& connected cases                   5




              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                   PRESENT
              THE HONOURABLE MR. JUSTICE SHAJI P.CHALY
   FRIDAY, THE 24TH DAY OF MARCH 2023 / 3RD CHAITHRA, 1945
                         WP(C) NO. 5066 OF 2023
PETITIONER:

              M K HANSAR
              AGED 48 YEARS
              S/O M.V. MOHAMMED KASSIM,
              HASEENA COTTAGE,
              PANAYIKULAM.P.O., ALUVA, PIN - 683502
              BY ADVS.TESSY JOSE
                      ELDHO PAUL

RESPONDENTS:

     1        KERALA WATER AUTHORITY
              REPRESENTED BY ITS MANAGING DIRECTOR,
              JALABHAVAN,
              THIRUVANANTHAPURAM-,
              PIN - 695033
     2        THE SUPERINTENDING ENGINEER
              KERALA WATER AUTHORITY,
              PUBLIC HEALTH CIRCLE,
              KOCHI, PIN - 682011
              BY SRI. P.M.JOHNY, STANDING COUNSEL
              BY SRI. V.V. JOSHI, STANDING COUNSEL

       THIS    WRIT     PETITION    (CIVIL)   HAVING   COME   UP   FOR
ADMISSION ON 24.03.2023, ALONG WITH W.P.(C.)NO.34088/2022
AND CONNECTED CASES, THE COURT ON THE SAME DAY DELIVERED
THE FOLLOWING:
 W.P.(C.) No. 34088 of 2022
& connected cases                 6




             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                PRESENT
             THE HONOURABLE MR. JUSTICE SHAJI P.CHALY
   FRIDAY, THE 24TH DAY OF MARCH 2023 / 3RD CHAITHRA, 1945
                         WP(C) NO. 6265 OF 2023
PETITIONER:
          M/S OM DHAR ENGINEERING PVT. LTD.,
          AGED 53 YEARS,II FLOOR, SRINIVASA SQUARE,
          IMAGE HOSPITAL LANE, MADHAPUR, HYDERABAD-500 081,
          REPRESENTED BY AUTHORISED SIGNATORY,
          C INDRAKUMAR, AGED 53 YEARS, S/O SURYA RAO,
          A 404, TRENDSETWINZ, NANAKRAMGUDA,
          HYDERABAD, PIN - 500033
             BY ADVS.V.PREMCHAND
                     SURYA MOHAN P.
                     FATHIMA SHALU S.

RESPONDENTS:


     1       THE KERALA WATER AUTHORITY,
             JALABHAVAN, REPRESENTED BY ITS MANAGING DIRECTOR,
             THIRUVANANTHAPURAM, PIN - 695033
     2       THE SUPERINTENDING ENGINEER,
             KERALA WATER AUTHORITY,PUBLIC HEALTH CIRCLE,
             HIGH ROAD, SAKTHAN TAMPURAN NAGAR,
             THRISSUR, PIN - 680 001
     3       THE EXECUTIVE ENGINEER,
             KERALA WATER AUTHORITY,PUBLIC HEALTH CIRCLE,
             HIGH ROAD, SAKTHANTAMPURAN NAGAR,
             THRISSUR, PIN - 680001
             BY SRI. V.V. JOSHI, STANDING COUNSEL

       THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON

24.03.2023, ALONG WITH W.P.(C.)NO. 34088/2022 AND CONNECTED CASES,

THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 W.P.(C.) No. 34088 of 2022
& connected cases                   7




              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                   PRESENT
              THE HONOURABLE MR. JUSTICE SHAJI P.CHALY
   FRIDAY, THE 24TH DAY OF MARCH 2023 / 3RD CHAITHRA, 1945
                         WP(C) NO. 6406 OF 2023
PETITIONER:

              SIVAPRASAD B,
              AGED 53 YEARS, S/O BHASKARAN PILLAI,
              RESIDING AT CHARUVVILAPUTHENVEEDU,
              THAZHAM SOUTH, CHATHANNOOR P.O.,
              KOLLAM, PIN - 691572
              BY ADVS. V.PREMCHAND
                       SURYA MOHAN P.
                       FATHIMA SHALU S.

RESPONDENTS:


     1        THE KERALA WATER AUTHORITY,
              JALA BHAVAN, REPRESENTED BY ITS MANAGING
              DIRECTOR, THIRUVANANTHAPURAM, PIN - 695033
     2        THE SUPERINTENDING ENGINEER,
              KERALA WATER AUTHORITY, PUBLIC HEALTH CIRCLE,
              KOLLAM, PIN - 691001
     3        THE EXECUTIVE ENGINEER,
              KERALA WATER AUTHORITY, PUBLIC HEALTH DIVISION,
              KOLLAM, PIN - 691001
              BY SRI. V.V. JOSHI, STANDING COUNSEL

       THIS    WRIT     PETITION    (CIVIL)   HAVING   COME   UP   FOR
ADMISSION ON 24.03.2023, ALONG WITH W.P.(C.)NO.34088/2022
AND CONNECTED CASES, THE COURT ON THE SAME DAY DELIVERED
THE FOLLOWING:
 W.P.(C.) No. 34088 of 2022
& connected cases                   8




              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                   PRESENT
              THE HONOURABLE MR. JUSTICE SHAJI P.CHALY
   FRIDAY, THE 24TH DAY OF MARCH 2023 / 3RD CHAITHRA, 1945
                        WP(C) NO. 10218 OF 2023
PETITIONER:

              T. MOHAMMED ALI
              AGED 55 YEARS, S/O. VEERAN HAJI, THADATHIL HOUSE,
              KANAYAM, SHORNUR, PALAKKAD DISTRICT, PIN - 679121
              BY ADVS.SANTHEEP ANKARATH
                      P.ANIRUDHAN

RESPONDENTS:

     1        STATE OF KERALA
              REPRESENTED BY ITS SECRETARY,
              WATER RESOURCES DEPARTMENT, GOVERNMENT
              SECRETARIAT, THIRUVANANTHAPURAM, PIN - 695001
     2        KERALA WATER AUTHORITY
              REPRESENTED BY ITS MANAGING DIRECTOR,
              JALA BHAVAN, VELLAYAMBALAM,
              THIRUVANANTHAPURAM, PIN - 695001
     3        THE SUPERINTENDING ENGINEER
              OFFICE OF THE SUPERINTENDING ENGINEER, P.H.
              CIRCLE, KERALA WATER AUTHORITY, HIGH ROAD,
              SAKTHAN THAMPURAM NAGAR, THRISSUR DISTRICT,
              PIN - 680001
              R1 BY SMT.RESHMI.K.M.,SENIOR GOVERNMENT PLEADER
              R2 & R3 BY SRI.V.V.JOSHI,SC

       THIS    WRIT     PETITION    (CIVIL)   HAVING   COME   UP   FOR
ADMISSION ON 24.03.2023, ALONG WITH W.P.(C.)NO.34088/2022
AND CONNECTED CASES, THE COURT ON THE SAME DAY DELIVERED
THE FOLLOWING:
 W.P.(C.) No. 34088 of 2022
& connected cases                9




                             JUDGMENT

The petitioners in the writ petitions are contractors

engaged by the Kerala Water Authority to do its civil works.

The grievance highlighted by the petitioners is on account

of the direction issued by the Kerala Water Authority to

furnish additional performance guarantee on the basis of

the rates quoted by the petitioners in items wise rates

contract, below 10%. The claims raised by the petitioners

are on the basis of the notifications issued by the State

Government dated 07.01.2021 and 15.03.2022, in the light

of Covid-19 pandemic. As per the notification dated

07.01.2021, State Government has waived furnishing of

additional performance guarantee for the low quoted items

on condition that the bidder shall furnish an undertaking to

execute all low quoted items in full as per contract terms

among other conditions. However, the said notification was

valid only for a period of one year subject to the condition

that the Government is at liberty to review the same. W.P.(C.) No. 34088 of 2022

Anyhow, as per the order dated 15.03.2022, State

Government has extended the relaxation granted for

furnishing performance guarantee in terms of the order

dated 07.01.2021 upto 31.03.2023, which means the

benefit of waiving the additional performance guarantee

was not extended after the expiry of one year period from

the notification dated 07.01.2021.

2. Petitioners have raised various contentions

including that 'they have quoted above the estimated PAC

and therefore, no additional performance guarantee can be

insisted upon on the basis of item wise rates submitted by

the petitioners. But fact remains, the State Government

has issued a notification dated 28.09.2015 as to the

manner in which the lumpsum contracts are to be tackled

in the matter of providing guarantee. The said order was

modified twice in 2019 and as per G.O.P. No.

168/2019/FIN, dated 07.12.2019, it is clarified that if the

quoted amount of lowest bidder(L1) is 'X%' below the

estimated PAC, the Additional Performance Guarantee W.P.(C.) No. 34088 of 2022

amount shall be '(X-10)%' of the estimated PAC. But, in the

matter of items rates contract, it was clarified that if the

rate quoted by the bidder for an item of work is 'X%' below

estimate cost where 'X' lies above 10%, the Additional

Performance Guarantee for that item of work is equal to

'(X-10)%' of the estimate amount for that item of work;

and the total of Additional Performance Guarantee for the

whole work is the total of individual Additional Performance

Guarantee for each item of work calculated as above.

Therefore, when an item wise rates contract was invited by

the Kerala Water Authority irrespective of whether the

contractor has quoted above the estimated probable

amount of contract, the Additional Performance Guarantee

is to be provided if amount is quoted below as per the

principles contained in the Government Order for each item

involved in the contract. This question was considered in

the IIIrd batch of writ petitions as per a common judgment

dated 21.03.2023; in W.P.(C.) No. 38189/2022 and

connected cases and held that the requirement put forth by W.P.(C.) No. 34088 of 2022

the Kerala Water Authority for providing additional

performance guarantee, if the amount quoted is below 10%

for each item of work is in accordance with law. In my

considered opinion, the principle of law laid down by this

Court in the aforequoted judgment would strictly apply to

these writ petitions also.

3. Therefore, after having heard learned counsel for

the petitioners, Sri. P. Shanes Methar, Sri. Babu Joseph

Kuruvathazha, Sri. V. Premchand, Smt. Tessy Jose and Sri.

Santheep Ankarath and learned Standing Counsel for the

Kerala Water Authority, Sri. V.V. Joshi, Sri. P.M. Johny and

Sri. Georgie Johny, the reliefs sought for by the petitioners

in the writ petition to exempt them from providing

additional performance guarantee is declined. But fact

remains, in many of the cases in the batch of writ petitions,

interim orders were passed directing the Kerala Water

Authority to execute agreement with the contractors, on

the contractors furnishing a simple bond undertaking to

furnish additional performance guarantee, if and when W.P.(C.) No. 34088 of 2022

directed so by this Court; and in that background, though

the reliefs were declined, certain directions were issued

which are as follows:-

"1. If the work in accordance with the agreement is completed by the contractors, no Additional Performance Guarantee shall be insisted upon.

2. If the work has progressed to a level exceeding 80%, the tendering authority is left with the liberty to take a decision as to whether any Additional Performance Guarantee is to be insisted upon, taking into account the efficiency, reputation, men and machinery engaged, and other positive factors of the respective contractors.

3. If the work has exceeded 30% of the total work, then the tendering authority is directed to secure Additional Performance Guarantee proportionate to the balance work.

4. In all other cases, the contractors/petitioners are directed to furnish an Additional Performance Guarantee to the tendering authority as specified in the tender documents within three weeks from the date of receipt of a copy of this judgment.

5. In cases where a Performance guarantee is furnished by the contractors in spite of its W.P.(C.) No. 34088 of 2022

relaxation up to 31.03.2023, the said amounts can be adjusted against the Additional Performance guarantee required in the circumstances specified above.

6. In cases where 100% bank guarantee is furnished, instead of 50% by way of treasury fixed deposit, the same is permitted to be continued in the facts and circumstances, if the work has exceeded 30% of the total work.

7. If the tenders are invited on the basis of the Percentage Rate Contracts, then the contractors are liable to furnish the Additional Performance Guarantee on the basis of (X-10)% of the estimated PAC.

8. If the tenders are invited on the basis of Items Rates Contract, then the contractors are liable to furnish Additional Performance Guarantee for each item of work on the basis of (X-10)% of the estimated amount for each item of work.

9. I make it clear that the directions are issued as above taking into account the peculiar facts, features and circumstances involved in these cases consequent to the interim orders granted; and it shall not be treated as a precedent, except in regard to the writ petitions pending in the above context."

W.P.(C.) No. 34088 of 2022

Therefore, the captioned writ petitions are also

disposed of in terms of the directions contained above. The

petitioners herein are all entitled to get the benefit of the

directions contained above if they come under the

categories specified above. The petitioners as well as the

agreement authority are directed to comply with the

conditions and do the necessary as directed above, taking

into account the progress of the work.

Sd/-

SHAJI P. CHALY JUDGE

DCS/24.03.2023 W.P.(C.) No. 34088 of 2022

APPENDIX OF WP(C) 34088/2022

PETITIONER EXHIBITS EXHIBIT P1 TRUE COPY OF THE WORK ORDER - LETTER NO. 2133/D6/2022/PHC - KKD DATED 24.10.2022 ISSUED BY THE 2ND RESPONDENT (RELEVANT PAGES) EXHIBIT P2 TRUE COPY OF THE E-TENDER NOTICE NO.

SE/PHC/KKD/27/2022-23 PUBLISHED BY THE 2ND RESPONDENT EXHIBIT P3 TRUE COPY OF THE G.O.(P) NO. 429/15/FIN DATED 28.09.2015 EXHIBIT P4 TRUE COPY OG THE G.O.(P) NO.

19/2016/FIN DATED 03.02.2016 EXHIBIT P5 TRUE COPY OG THE G.O.(P) NO. 1/2019/FIN DATED 10.01.2019 EXHIBIT P6 TRUE COPY OF THE OM -NO. F.9/4/2020-PPD ISSUED BY THE GOVERNMENT OF INDIA MINISTRY OF FINANCE DATED 12.11.2020 EXHIBIT P7 TRUE COPY OF THE G.O.(P) NO. 7/2021/FIN DATED 07.01.2021 EXHIBIT P8 TRUE COPY OF THE G.O.(P) NO.

32/2022/FIN DATED 15.03.2022 W.P.(C.) No. 34088 of 2022

APPENDIX OF WP(C) 42505/2022

PETITIONER EXHIBITS EXHIBIT P1 TRUE COPY OF THE E-TENDER NOTICE 29.9.2022 ISSUED BY THE 2ND RESPONDENT. EXHIBIT P2 TRUE COPY OF THE SCHEDULE OF WORK ATTACHED TO EXT. P1 TENDER NOTICE. EXHIBIT P3 TRUE COPY OF THE WORK ORDER DATED 17.12.2022 ISSUED BY THE 2ND RESPONDENT.

EXHIBIT P4 TRUE COPY OF THE REPRESENTATION DATED 21.12.2022 SUBMITTED BY THE PETITIONER BEFORE THE 2ND RESPONDENT.

EXHIBIT P5 TRUE COPY OF THE ORDER OF THIS HON'BLE COURT DATED 30.11.2022 IN W.P.(C) NO.38602/2022.

W.P.(C.) No. 34088 of 2022

APPENDIX OF WP(C) 4905/2023

PETITIONER EXHIBITS EXHIBIT-P1 A TRUE COPY OF THE SELECTION NOTICE DATED ON 08/02/2023 ISSUED BY THE SUPERINTENDING EXECUTIVE ENGINEER, 2ND RESPONDENT EXHIBIT-P2 A TRUE COPY OF THE GOP NO 07/2021/ FIN DATED 07/01/2021 ISSUED BY THE GOVERNMENT OF KERALA EXHIBIT-P3 A TRUE COPY OF THE GO NO 32/2022 DATED 15/03/2022 ISSUED BY THE GOVERNMENT OF KERALA EXHIBIT-P4 A TRUE COPY OF THE GO (P) NO.1/2019/FIN DATED 10.01.2019 ISSUED BY THE GOVERNMENT OF KERALA, EXHIBIT-P5 A TRUE COPY OF THE SCHEDULE PREPARED BY THE 1ST RESPONDENT BASED ON WHICH ADDITIONAL PERFORMANCE GUARANTEE DATED NIL EXHIBIT6 A TRUE COPY OF THE RELEVANT PORTION OF THE PRICE SCHEDULE DATED NIL EXHIBIT-P7 A TRUE COPY OF THE RELEVANT PORTION OF THE NOTICE INVITING TENDER (NIT) FOR THE WORK IN QUESTION EXHIBIT-P8 A TRUE COPY OF THE ORDER DATED 11.01.2023 ISSUED BY THE MANAGING DIRECTOR, KERALA WATER AUTHORITY EXHIBIT-P9 A TRUE COPY OF THE INTERIM ORDER DATED 3-2-2023 IN W.P.(C).NO.3338 OF 2023 BEFORE THE HON'BLE HIGH COURT OF KERALA, AT ERNAKULAM W.P.(C.) No. 34088 of 2022

APPENDIX OF WP(C) 4961/2023

PETITIONER EXHIBITS EXHIBIT-P1 A TRUE COPY OF THE SELECTION NOTICE DATED ON 23-1-2023 ISSUED BY THE SUPERINTENDING EXECUTIVE ENGINEER, 2ND RESPONDENT EXHIBIT-P2 A TRUE COPY OF THE GOP NO 07/2021/ FIN DATED 07/01/2021 ISSUED BY THE GOVERNMENT OF KERALA EXHIBIT-P3 A TRUE COPY OF THE GO NO 32/2022 FIN DATED 15/03/2022 ISSUED BY THE GOVERNMENT OF KERALA EXHIBIT-P4 A TRUE COPY OF THE GO (P) NO.1/2019/FIN DATED 10.01.2019 ISSUED BY THE GOVERNMENT OF KERALA EXHIBIT-P5 A TRUE COPY OF THE DEPOSIT RECEIPT DATED NIL ISSUED BY THE FEDERAL BANK EXHIBIT-P6 A TRUE COPY OF THE COMMUNICATION DATED 27.01.2023 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER EXHIBIT-P7 A TRUE COPY OF THE RELEVANT PORTION OF THE NOTICE INVITING TENDER (NIT) FOR THE WORK IN QUESTION EXHIBIT-P8 A TRUE COPY OF THE ORDER DATED 11.01.2023 ISSUED BY THE MANAGING DIRECTOR, KERALA WATER AUTHORITY EXHIBIT-P9 A TRUE COPY OF THE INTERIM ORDER DATED 3-2-2023 IN W.P.(C).NO.3338 OF 2023 BEFORE THE HON'BLE HIGH COURT OF KERALA, AT ERNAKULAM EXHIBIT P10 A TRUE COPY OF THE RELEVANT PORTION OF NIT CONDITIONS WITH RESPECT TO THE WORK IN QUESTION W.P.(C.) No. 34088 of 2022

APPENDIX OF WP(C) 5066/2023

PETITIONER EXHIBITS EXHIBIT P1 TRUE COPY OF THE G O (P) NO 7/2021/FIN DATED 7-1-2021 EXHIBIT P2 TRUE COPY OF THE RELAVENT PAGES OF THE N I T ISSUED BY THE RESPONDENT NO 2 EXHIBIT P3 TRUE COPY OF THE SELECTION NOTICE ISSUED BY THE 2ND RESPONDENT IN FOVOUR OF THE PETITIONER DATED 10-2-2023 EXHIBIT P4 TRUE A COPY OF THE RELAVENT PAGES OF THE ACCEPTED BOQ ISSSUED BY THE RESPONDENT NO 2 EXHIBIT P5 TRUE COPY OF THE G O (P) NO 32/2022/F I N DATED 15-3-2022 ISSUED BY THE ADDITIONAL CHIEF SECRETARY ,FINANCE GOVERNMENT OF KERALA W.P.(C.) No. 34088 of 2022

APPENDIX OF WP(C) 6265/2023

PETITIONER EXHIBITS EXHIBIT-P1 A TRUE COPY OF THE SELECTION NOTICE DATED ON 07/02/2023 ISSUED BY THE SUPERINTENDING ENGINEER, 2ND RESPONDENT EXHIBIT-P2 A TRUE COPY OF THE GOP NO 07/2021/ FIN DATED 07/01/2021 ISSUED BY THE GOVERNMENT OF KERALA EXHIBIT-P3 A TRUE COPY OF THE GO NO 32/2022 DATED 15/03/2022 ISSUED BY THE GOVERNMENT OF KERALA EXHIBIT-P4 A TRUE COPY OF GO (P) NO.1/2019/FIN DATED 10.01.2019 ISSUED BY THE GOVERNMENT OF KERALA EXHIBIT-P5 A TRUE COPY OF THE RELEVANT PORTION OF THE NOTICE INVITING TENDER (NIT) FOR THE WORK IN QUESTION EXHIBIT-P6 A TRUE COPY OF THE ORDER DATED 11.01.2023 ISSUED BY THE MANAGING DIRECTOR, KERALA WATER AUTHORITY EXHIBIT-P7 A TRUE COPY OF THE INTERIM ORDER DATED 3/2/2023 IN WP(C) NO.3338/2023 BEFORE THE HON'BLE HIGH COURT OF KERALA, AT ERNAKULAM W.P.(C.) No. 34088 of 2022

APPENDIX OF WP(C) 6406/2023

PETITIONER EXHIBITS EXHIBIT-P1 A TRUE COPY OF THE SELECTION NOTICE DATED ON 06/02/2023 ISSUED BY THE SUPERINTENDING ENGINEER, 2ND RESPONDENT EXHIBIT-P2 A TRUE COPY OF THE GOP NO 07/2021/ FIN DATED 07/01/2021 ISSUED BY THE GOVERNMENT OF KERALA EXHIBIT-P3 A TRUE COPY OF THE GO NO 32/2022 DATED 15/03/2022 ISSUED BY THE GOVERNMENT OF KERALA EXHIBIT-P4 A TRUE COPY OF THE GO (P) NO.1/2019/FIN DATED 10.01.2019 ISSUED BY THE GOVERNMENT OF KERALA.

EXHIBIT-P5 A TRUE COPY OF THE RELEVANT PORTION OF THE NOTICE INVITING TENDER (NIT) FOR THE WORK IN QUESTION EXHIBIT-P6 A TRUE COPY OF THE ORDER DATED 11.01.2023 ISSUED BY THE MANAGING DIRECTOR, KERALA WATER AUTHORITY EXHIBIT-P7 A TRUE COPY OF THE INTERIM ORDER DATED 3/2/2023 IN WP(C) NO.3338/2023 BEFORE THE HON'BLE HIGH COURT OF KERALA, AT ERNAKULAM W.P.(C.) No. 34088 of 2022

APPENDIX OF WP(C) 10218/2023

PETITIONER EXHIBITS EXHIBIT P 1 TRUE COPY OF LETTER NO. KWA/ PHC/ TSR/ D5/ 4869/ 2022 DATED 06.03.2023 ISSUED BY THE 3RD RESPONDENT TO THE PETITIONER EXHIBIT P 2 TRUE COPY OF G.O.(P) NO. 72/2021/ FIN DATED 7.1.2021 ISSUED BY THE FINANCE DEPARTMENT (INDUSTRIES & PUBLIC WORKS- B), GOVERNMENT OF KERALA.

EXHIBIT P 3 TRUE COPY OF GO(P) NO. 32/2022/ FIN DATED 15.3.2022 ISSUED BY FINANCE DEPARTMENT (INDUSTRIES & PUBLIC WORKS- B), GOVERNMENT OF KERALA.

EXHIBIT P 4 TRUE COPY OF RELEVANT PAGES OF NOTICE INVITING TENDER (E-TENDER NO. 111/ SE/ PHC/ TSR/ 2022-23) ISSUED BY THE 2ND RESPONDENT.

EXHIBIT P 5 TRUE COPY OF INTERIM ORDER DATED 30.11.2022 IN WP(C) NO. 38602/2022 PASSED BY THIS HONOURABLE COURT. EXHIBIT P 6 TRUE COPY OF GO (P) 429/2015/ FIN DATED 28.9.2015 ISSUED BY FINANCE DEPARTMENT (INDUSTRIES & PUBLIC WORKS-B), GOVERNMENT OF KERALA.

EXHIBIT P 7 TRUE COPY OF G.O. (P) NO. 1/2019/FIN DATED 10.1.2019 ISSUED BY FINANCE DEPARTMENT (INDUSTRIES & PUBLIC WORKS- B), GOVERNMENT OF KERALA.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter