Citation : 2022 Latest Caselaw 2477 Ker
Judgement Date : 4 March, 2022
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MRS. JUSTICE ANU SIVARAMAN
FRIDAY, THE 4TH DAY OF MARCH 2022 / 13TH PHALGUNA, 1943
WP(C) NO.28586 OF 2021
PETITIONER :-
MOIDEEN HAJI P.K., AGED 81 YEARS
S/O. BEERAN HAJI, PUTHUKUDI THARIF MANZIL,
PONMUNDAM P.O, TIRUR,
MALAPPURAM DISTRICT, PIN - 676 106.
BY ADV K.I.ABDUL RASHEED
RESPONDENTS :-
1 TIRUR MUNICIPALITY
REPRESENTED BY ITS SECRETARY, TIRUR,
MALAPPURAM DISTRICT, PIN - 676 101.
2 THE SECRETARY,
TIRUR MUNICIPALITY, TIRUR,
MALAPPURAM DISTRICT, PIN - 676 101.
3 THE DISTRICT TOWN PLANNER,
TIRUR, MALAPPURAM DISTRICT, PIN - 676 101.
BY ADVS.
SRI.P.VENUGOPAL, SC, TIRUR MUNICIPALITY
SRI.SAYED MANSOOR BAFAKHY THANGAL
SMT.VINITHA B., SR.GP
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION
ON 04.03.2022, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
WP(C) NO.28586 OF 2021
-: 2 :-
JUDGMENT
Dated this the 4th day of March, 2022
This writ petition is filed seeking the following reliefs :-
"i) Issue a Writ of mandamus directing the respondents to issue occupancy certificate to the petitioner based on the completion certificate submitted by the petitioner as evidenced by Ext.P7 forthwith.
ii) Issue a Writ of mandamus directing the respondents to issue the occupancy certificate, without taking into account minor variation in the completion plan, if the variations do not conflict with the Kerala Municipality Building Rules as stated in Proviso to Rule 17(1) of the Rules."
2. Heard the learned counsel for the petitioner and the
learned Standing Counsel appearing for the Municipality.
3. It is submitted by the learned counsel for the petitioner
that the petitioner had been issued with Ext.P5 building permit on
26.3.2014 for the construction of a two storied building in his
property. It is submitted that though the construction of the
building is completed in the year 2016, the building permit had
been cancelled alleging minor variations in the construction
carried out. It is submitted that thereafter, the petitioner had
submitted application for regularisation and had also pointed out
that the minor variations sought for do not require any further
permissions in accordance with the Kerala Municipality Building WP(C) NO.28586 OF 2021
Rules. It is stated that the application submitted by the petitioner
for regularisation was also rejected. However, while matters stood
so, the respondents had convened an Adalath to consider
applications for occupancy certificate and by Ext.P9 had decided to
set aside the decision for cancellation of the permit. It is submitted
that in the above situation, there is no impediment to grant
occupancy certificate to the petitioner. However, long after
Ext.P9, even though requests had been made repeatedly by the
petitioner, no steps are taken to issue the occupancy certificate.
The learned counsel for the petitioner submits that it was only on
account of a road widening as proposed in a DTP Scheme that the
request for occupancy certificate has not been considered by the
Municipality. It is submitted that the said proposal for further road
widening had evidently been given up by the Municipality itself as
is evident from Exts.P2 and P4. It is submitted that the application
of the petitioner for occupancy certificate is liable to be considered
without reference to the objection with regard to the further road
widening in the DTP Scheme.
4. A statement has been placed on record by respondents 1
and 2. It is submitted that the petitioner had been issued with a
building permit, but in an inspection conducted it was found that
the construction was in violation of the permit, which was why a WP(C) NO.28586 OF 2021
stop memo as well as an order of revocation of the building permit
had been issued to the petitioner. It is submitted that on 16.8.2016
the petitioner submitted the completion plan before the 1 st
respondent, but the petitioner was informed that the said request
cannot be considered since the permit stood cancelled and the
petitioner was directed to submit an application for regularisation.
It is submitted that though an application was submitted by the
petitioner for regularisation on 31.5.2018, the same was
incomplete and that the petitioner had been required to submit a
proper application which was considered and referred to the 3 rd
respondent. It is stated that the 3 rd respondent, by letter dated
18.12.2018, had replied that there is violation of the DTP Scheme
and had directed to cure the Scheme. It is submitted that on
14.8.2019, an adalath was convened in the Municipality and it was
decided not to insist on the compliance of the DTP Scheme as the
Municipal Council had decided to reduce the width of the proposed
road to 14 metres. It was also decided to renew the building
permit and issue occupancy certificate, if the application is
otherwise in compliance with the Kerala Municipality Building
Rules. It is stated that though there is an observation in the
adalath not to insist for compliance of the DTP Scheme, since the
width of the proposed road in the Scheme is 18 metres and since WP(C) NO.28586 OF 2021
the Scheme remains in force, the application has to be considered
in accordance with the DTP Scheme.
5. I have considered the contentions advanced on either
side. It is evident that Ext.P5 permit had been issued to the
petitioner as early as on 26.3.2014. By Ext.P2 dated 20.11.2012, a
resolution had also been passed by the Panchayat stating that the
road widening is being limited to 14 metres. Ext.P4, which is the
minutes of the meeting which considered the application of the
petitioner for building permit, also contains a reference to such
decision. Ext.P9 would show that in the Municipal Adalath
conducted also, a decision had been taken not to insist on the 18
metre width of the road as per the DTP Scheme in the light of
Ext.P2 resolution of the Municipality and Ext.P4.
6. Having considered the contentions advanced and in view
of the fact that the permit had been issued by the Municipality in
the year 2014 considering Ext.P2 resolution as well, I am of the
opinion that the Municipality cannot now raise a contention that
the width of the road has to be maintained at 18 metres under the
DTP Scheme to deny the benefit of an occupancy certificate to the
petitioner. In view of Ext.P2 resolution as well as Exts.P4 and P9, I
am of the opinion that the request made by the petitioner for
occupancy certificate has to be considered without adverting to the WP(C) NO.28586 OF 2021
objection with regard to the width of the road to be maintained at
18 metres under the DTP Scheme.
In the above view of the matter, this writ petition is
disposed of with the following directions :-
The respondents shall take up the request made by the
petitioner for occupancy certificate and the request for
regularisation, if any and consider and pass orders on the same in
accordance with law, taking note of Ext.P5 building permit granted
to the petitioner. In case there are violations from the building
permit, the question whether the same can be regularised in
accordance with law shall also be considered by the respondents.
The respondents shall consider the request made by the petitioner
for occupancy certificate de hors the contention raised with regard
to the DTP Scheme which has been decided to be relaxed in the
light of Exts.P2 and P9. Appropriate orders shall be passed within
a period of one month from the date of receipt of a copy of this
judgment.
Sd/-
ANU SIVARAMAN JUDGE
Jvt/5.3.2022 WP(C) NO.28586 OF 2021
APPENDIX OF WP(C) 28586/2021
PETITIONER EXHIBITS
Exhibit P1 TRUE COPY OF THE LAND TAX RECEIPT DATED 25.10.2021 ISSUED BY THE VILLAGE OFFICER, TIRUR.
Exhibit P2 TRUE COPY OF THE RESOLUTION DATED 20.11.2012 TAKEN BY THE 1ST RESPONDENT.
Exhibit P3 TRUE COPY OF BUILDING PLAN SUBMITTED ALONG WITH THE BUILDING PERMIT APPLICATION DATED 14.02.2014.
Exhibit P4 TRUE COPY OF THE NOTICE OF AGENDA DATED 14.03.2014 CIRCULATED BY THE 2ND RESPONDENT.
Exhibit P5 TRUE COPY OF THE BUILDING PERMIT NO. B1/89/14 DATED 26.03.2014 ISSUED TO THE PETITIONER.
Exhibit P6 TRUE COPY OF THE ORDER NO. PW3/BA89/124 DATED 19.07.2016.
Exhibit P7 TRUE COPY OF THE RECEIPT DATED 16.08.2016 ISSUED BY THE 2ND RESPONDENT FORT RECEIVING THE COMPLETION PLAN.
Exhibit P8 TRUE COPY OF THE LETTER NO. PW3-B1/293/16 DATED 12.02.2018.
Exhibit P9 TRUE COPY OF THE RELEVANT PAGE OF THE FILE RECORDING THE DECISION OF THE ADALATH CONDUCTED ON 14.08.2019.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!