Citation : 2022 Latest Caselaw 7398 Ker
Judgement Date : 24 June, 2022
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE MOHAMMED NIAS C.P.
FRIDAY, THE 24TH DAY OF JUNE 2022 / 3RD ASHADA, 1944
WP(C) NO. 21205 OF 2012
PETITIONER:
B.S.JAYAKUMAR
AGED 55 YEARS
S/O.BHASKARAN NAIR,
SUPERINTENDING ENGINEER,
THRISSUR CORPORATION,
THRISSUR
BY ADVS.
SRI.K.K.CHANDRAN PILLAI (SR.)
SRI.ARUN ANTONY
SRI.R.ANAS MUHAMMED SHAMNAD
SRI.BOBBY THOMAS
SRI.A.S.SAJUSH PAUL
SRI.THOMAS JAMES MUNDACKAL
RESPONDENTS:
1 THE STATE CHIEF INFORMATION COMMISSIONER
OFFICE OF THE CHIEF INFORMATION COMMISSIONER,
THIRUVANANTHAPURAM-695001
2 THE SECRETARY
THIRUVANANTHAPURAM CORPORATION,
THIRUVANANTHAPURAM-695001
3 MR.S.SREEKANTHAN TC 401087 PGRA -23
PANCHAMI GARDENS
JAGATHY,
THIRUVANANTHAPURAM-695014
4 THE STATE OF KERALA
REP.BY THE CHIEF SECRETARY,
GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM-695001
WP(C)No. 21205 of 2012
2
5 THE THRISSUR CORPORATION
REP.BY ITS SECRETARY,
THRISSUR-680001
BY ADVS.
SRI.P.K.MANOJKUMAR
SRI.N.NANDAKUMARA MENON SR.
SRI. SANTHOSH P.PODUVAL, SC, THRISSUR
CORPORATION
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR
ADMISSION ON 20.06.2022, THE COURT ON 24.06.2022 DELIVERED
THE FOLLOWING:
WP(C)No. 21205 of 2012
3
MOHAMMED NIAS. C.P.,J
------------------------
WP(C)No. 21205 of 2012
------------------------
Dated this the 24th day of June, 2022
JUDGMENT
The petitioner while working as the Superintending Engineer
in the second respondent Corporation, also acting as the State Public
Information Officer under the Right to Information Act, 2005
(hereinafter referred to as 'the Act') received an application dated
23.03.2011 (Ext.P1) from the third respondent herein asking whether
permission is required for putting up a church and whether any
permission has been given for putting up a church (Alice Devadas
Memorial CSI Church) at Jagathy, Thiruvananthapuram District, close
to the petitioner's residence and if granted, copies of the same were
sought. Since no information was furnished by the third respondent
to the petitioner, he moved the first appellate authority on 25.04.2011
(Ext.P2). Notice of the said appeal dated 28.05.2011 was served on
the petitioner on 31.05.2011 and the petitioner gave a reply dated
6.5.2011 answering the first question and stating that since the
building in question is more than 15 years old, it is not possible to
find out whether permit for the construction activities had been
granted and that a reply would be sent after obtaining the requisite
information from the records.
WP(C)No. 21205 of 2012
2. The third respondent, the applicant not satisfied with the
reply, moved the State Information Commission. On receipt of notice
in the second appeal, the Corporation gave a reply stating that there
was a direction given to the overseer on 30.03.2011 for conducting a
physical inspection of the church in question, but since it was
remaining closed, details could not be got and therefore on enquiry
with the neighours, information was got and a reply was given to the
applicant as aforesaid. The petitioner was transferred to Thrissur
Corporation on 16.7.2011 and the successor in office had given a
reply to the first respondent-Commissioner on 12.05.2011 on similar
lines as Ext.P6 reply. The first respondent considered the appeal on
19.4.2012 and on the same day the Corporation had furnished a reply
to the third respondent stating that from the registers in the
Corporation, it is seen that no permission was granted for
constructing a church and that no number has been assigned to the
building in question and thus a reply was delivered to the petitioner
on 20.04.2011.
3. Earlier the successor in office of the petitioner had given
a reply as Ext.P9 before the Commissioner pointing out that he had
taken charge on 3.10.2011 and that there were several works that
had to be completed before March 31st of the said year and the
Corporation had more than 100 Wards and because of the pressure of
work and also the work of giving replies in the cases pending before WP(C)No. 21205 of 2012
the High Court, Ombudsman, Tribunals, the Human Right
Commission, etc., that there was delay in responding to the
application of the third respondent. The Commission issued yet
another notice on 28.4.2012 holding that there was delay in giving a
reply warranting action under Section 20 of the Act and explanation
was sought for from the petitioner. The petitioner responded to
Ext.P1 stating that though the petitioner had forwarded the
application immediately after its receipt, the physical inspection took
some time as the church was closed and the details had to be
collected from the neighbour's and the fact that there was no
documents available with respect to the construction with the
Corporation, was intimated to the third respondent on 10.05.2011. It
was specifically stated in the reply that it was for want of documents
at the relevant time that resulted in the delay in giving to the reply to
the information sought.
4. By Ext.P12 the State Information Commissioner passed
an order holding that there is a delay of almost one year and that
the reasons given by the petitioner herein that there was delay in
getting information from the officer, who was asked to collect
documents and that no documents were available with the
Corporation office pertaining to the question sought, were not
accepted. Rejecting such contentions, a penalty of an amount of
Rs.10,000/- was imposed by Ext.P12. The petitioner submits that he WP(C)No. 21205 of 2012
came to know about the same only when he received notice from the
department. It is also submitted that he was not heard before passing
Ext.P12 as no chance of personal hearing was given after he
submitted a reply (Ext.P11). The petitioner therefore challenges
Exts.P12 and P13.
5. I have heard Sri.K.K.Chandran Pillai, the learned senior
counsel for the petitioner, Sri.M.Ajay, the learned counsel for the first
respondent and Sri.N.Nanda Kumara Menon, the learned senior
counsel for the second respondent-Corporation.
6. The learned senior counsel argues that he had on receipt
of Ext.P1 application sought information from the person concerned,
invoking Section 5(4) of the Act. The application was received on
24.3.2011 and this was done on 30.03.2011 itself. The learned senior
counsel further contends that since no particular details were given
about the church in question it was difficult to find out from any
register in the absence of any number or specific details to make a
search and the delay caused was not deliberate. He also cited
pressure of work as a reason for not sending a reply within time and
further contends that he was transferred to Thrissur Corporation on
16.7.2011, before which time itself Ext.P4 was sent on 6.5.2011. He
submits that since a reply had already been given under Ext.P4 it
cannot be said that the petitioner had not responded to the question WP(C)No. 21205 of 2012
and the Act does not speak of the manner in which a reply has to be
given. It is his further argument that since no deliberate act occurred
on the part of the petitioner and it was only a case of non-availability
of register at the relevant time that the delay was caused. The
learned senior counsel also contended that physical inspection had to
be carried out for want of specific details and all these reasons
contributed to the delay.
7. Sri.M.Ajay, the learned counsel appearing for the State
Information Commission submits that there is no case anywhere on
the side of the petitioner that the files were missing and the
explanation that for want of details, physical inspection had to be
conducted cannot be accepted at all, since there were no complicated
questions that were put and even the first reply came only after the
filing of the appeal before the first appellate authority. Learned
counsel criticizes the act of the petitioner in issuing Ext.P3, where
questions were put back to the applicant which should not have been
done. He also argues that notice was issued proposing penalty and it
was after receiving a reply from the petitioner that Ext.P12 order was
passed. The reasons furnished by the petitioner were not found to be
acceptable and despite the same leniency was shown and only
Rs.10,000/- was imposed when as a matter of fact the maximum
penalty of Rs.25,000/- ought to have been mulcted. WP(C)No. 21205 of 2012
8. After considering the rival contentions and perusing the
documents, I find considerable force in the arguments of Sri.M.Ajay
that the reasons for the delay are not all that convincing. It is
pertinent to point out that to answer the first query sought for by the
third respondent herein, no time at all was needed as the question
was whether permission was required for constructing a church.
Even for the second query viz., whether any permission has been
granted to the church in question and if so to serve copies of the
same, the petitioner should not have taken as much time as he
ultimately took to reply. The Corporation is bound to have in its
custody the details, registers showing the grant of permits, sanctions,
occupancy certificate, numbering of buildings. The delay in
furnishing reply defeat the very purpose for which the Act is brought
in.
9. Though I notice that the reasons for not giving the reply
in time are not all that satisfactory, considering the fact that the
petitioner had sought the aid of other staff in the Corporation for
giving a reply, shortly, after the receipt of the questions and the fact
that he was transferred to Thrissur Corporation on 16.7.2011 and
that information was furnished to the third respondent on the same
day on which the State Information Commissioner directed. I also
notice that it will be difficult for any Corporation or local body to find
out whether a permission was granted to a particular building from WP(C)No. 21205 of 2012
the registers per se as neither the year of completion nor any
relevant number or any details specifically pointing to the exact
location of the property were shown in the application except stating
that it was a church near to his residence, the address of which was
shown by the petitioner. I also take into account the fact that the
petitioner had since retired from service. As a measure of leniency
and indulgence and going by the requirements to be met for imposing
a penalty, I deem it fit to set aside that part of the order which directs
payment of Rs.10,000/- as penalty.
9. For the reasons mentioned above, I set aside Ext.P12
and P13 and I hold that the imposing of penalty of Rs.10,000/- is not
warranted in the peculiar facts and circumstances of the case.
Accordingly, I allow the writ petition and quash Exts.P12 and P13
orders in so far it directs the petitioner to pay penalty amount of
Rs.10,000/-.
The writ petition is allowed as above.
Sd/-
MOHAMMED NIAS. C.P.,JUDGE.
dlk 21.6.22 WP(C)No. 21205 of 2012
APPENDIX OF WP(C) 21205/2012
PETITIONER'S EXHIBITS Exhibit P1 TRUE COPY OF APPLICATION FILED BY THE 3RD RESPONDENT BEFORE THE 2ND RESPONDENT DATED 23.03.2011 Exhibit P2 TRUE COPY THE APPEAL FILED BEFORE THE SECRETARY OF THE 2ND RESPONDENT DATED 25.4.2011 Exhibit P3 TRUE COPY OF THE NOTE GIVEN TO THE APPELLATE AUTHORITY DATED 28.5.2011 BY THE PETITIONER.
Exhibit P4 TRUE COPY OF THE REPLY GIVEN BY THE PETITIONER DATED 6.5.2011 TO THE 3RD RESPONDENT.
EXHIBIT P5 TRUE COPY OF REPLY DATED 25.6.2011 GIVEN IST RESPONDENT BY THE PETITIONER.
EXHIBIT P6 TRUE COPY OF THE REPORT SUBMITTED BY THE SECRETARY OF THE 2ND RESPONDENT DATED 31.12.2011 TO THE IST RESPONDENT.
EXHIBIT P7 TRUE COPY OF ANOTHER REPORT SUBMITTED BEFORE THE IST RESPONDENT BY THE SECRETARY OF THE 2ND RESPONDENT DATED 12.4.2012.
EXHIBIT P8 TRUE COPY OF ANOTHER REPORT DATED 19.4.2012 SUBMITTED BEFORE THE IST RESPONDENT BY THE SECRETARY OF THE 2ND RESPONDENT.
EXHIBIT P9 TRUE COPY OF A REPORT DATED 19.4.2012 SUBMITTED BEFORE THE IST RESPONDENT BY THE SECRETARY OF THE 2ND RESPONDENT SHOWING THE REASON FOR DELAY IN REPLY.
EXHIBIT P10 TRUE COPY OF SHOW CAUSE NOTICE ISSUED TO THE PETITIONER DATED 28.4.2012 EXHIBIT P11 TRUE COPY OF COVERING LETTER DATED 15.5.2012 FOR SENDING EXT.P11(A) TO THE IST RESPONDNET.
EXHIBIT P11(A) TRUE COPY OF THE EXPLANATION SUBMITTED WP(C)No. 21205 of 2012
BEFORE THE IST RESPONDENT BY THE PETITIONER.
EXHIBIT P12 TRUE COPY OF THE ORDER ISSUED BY THE IST RESPONDENT DATED 31.5.2012 EXHIBIT P13 TRUE COPY OF COMMUNICATION DATED 2.7.2012 RECEIVED FROM THE 5TH RESPONDENT.
EXHIBIT 13(A) TRUE COPY OFLETTER DATED 21.6.2012 RECEIVED BY THE PETITIONER ALONG WITH EXT.P13 EXHIBIT P14 TRUE COPY OF LETTER ADDRESSED TO THE 5TH RESPONDENT DATED NIL.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!