Monday, 20, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Concord Construction vs Kochi Metro Rail Ltd. - Kmrl
2022 Latest Caselaw 6756 Ker

Citation : 2022 Latest Caselaw 6756 Ker
Judgement Date : 14 June, 2022

Kerala High Court
Concord Construction vs Kochi Metro Rail Ltd. - Kmrl on 14 June, 2022
                     IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                      PRESENT
                       THE HONOURABLE MR.JUSTICE V.G.ARUN
         TUESDAY, THE 14TH DAY OF JUNE 2022 / 24TH JYAISHTA, 1944
                             WP(C) NO. 19141 OF 2022
PETITIONER:

              CONCORD CONSTRUCTION,
              HEAD OFFICE AT KALLATRA COMPOUND,
              RAILWAY STATION ROAD, KANHANGAD,
              KASARGOD DISTRICT PIN- 671 315,
              REPRESENTED BY ITS PARTNER,
              DR. KALLATRA ABDUL MUNEER

              BY ADVS.
              ALIAS M.CHERIAN
              K.M.RAPHY
              AJAI ALIAS CHALAPPURAM
              BRISTO S PARIYARAM


RESPONDENTS:

     1        KOCHI METRO RAIL LTD. - KMRL
              JLN STADIUM METRO STATION, 4TH FLOOR KALOOR,
              ERNAKULAM, PIN - 682017
              REPRESENTED BY ITS MANAGING DIRECTOR.

     2        THE GENERAL MANAGER (PROJECTS),
              KOCHI METRO RAIL LIMITED,
              JLN STADIUM METRO STATION, 4TH FLOOR KALOOR,
              ERNAKULAM, PIN - 682017

              BY ADVS.
              SC FOR KMRL: JAJU BABU (SR)
              M.U. VIJAYALAKSHMI

     THIS     WRIT    PETITION   (CIVIL)   HAVING   COME   UP   FOR   ADMISSION   ON
14.06.2022, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C) NO. 19141 OF 2022
                                  2




                           JUDGMENT

Dated this the 14th day of June, 2022

The petitioner was awarded certain works by the

first respondent Kochi Metro Rail Limited (KMRL). The

works were awarded under Ext.P1 dated 12.04.2021.

According to the petitioner, due to adverse climatic

conditions and other factors, including the second

phase of COVID-19 pandemic and resultant lockdown,

the work did not progress as expected. This resulted

in the petitioner being issued with Ext.P5 notice dated

04.05.2022, granting the petitioner 14 days time to

offer explanation for the lack of progress, failing which

the contract will stand automatically terminated. The

petitioner submitted Ext.P7 explanation, pointing out

various reasons for not completing the work as per

schedule. As the explanation was not satisfactory, the

petitioner was issued with Ext.P8, informing that the

termination had come into effect on expiry of 14 days

from the date of issuance of Ext.P5 and that in

furtherance of the termination, KMRL intends to WP(C) NO. 19141 OF 2022

conduct inspection of the site and prepare an

inventory of the works completed and pending. This

writ petition is filed challenging Ext.P8, primarily on

the ground that the petitioner was not afforded an

opportunity of hearing before passing the order.

2. Learned Counsel for the petitioner submitted

that, had the petitioner been given an opportunity of

hearing, he would have been able to convince the

officials of the respondents that, the delay in

completion of the work was for reasons beyond the

petitioner's control. It is further contended that,

having granted 14 days time under Ext.P5 and the

petitioner having availed such opportunity by

submitting a detailed explanation, it was only

appropriate for the respondents to have considered

the explanation and heard the petitioner before

passing Ext.P8.

3. Learned Senior Counsel appearing for the

respondents submitted that the respondents were

compelled to terminate the contract, on finding that WP(C) NO. 19141 OF 2022

not even 5% of the work had been completed as per

schedule. Moreover, in spite of being granted

opportunity by extending the contract period, the

recalcitrance on the petitioner's part continued. As

further delay in completing the work would cause

substantial prejudice not only to the respondents but

to the public at large, the contract had to be

terminated. Hence the proceedings under Exts.P5

and P8.

4. Having heard the learned Counsel on either

side, I find merit in the contention that, having been

issued with Ext.P5 granting 14 days time for offering

explanation and the petitioner having offered Ext.P7

explanation, it is only proper for the respondents to

afford an opportunity of hearing to the petitioner

before taking the final decision. In that view of the

matter, Ext.P8 order is directed to be treated as a

show cause notice and the petitioner afforded an

opportunity of hearing before proceeding further.

In the result, the writ petition is disposed of, WP(C) NO. 19141 OF 2022

directing the respondents to consider Ext.P8 as a

show cause notice and afford an opportunity of

hearing to the petitioner before taking further

proceedings based on Ext.P8. For that purpose, the

petitioner shall be issued with a notice, specifying the

date and time on which authorised representative of

the petitioner should appear for hearing. On such

appearance, competent officer of the respondents

shall hear the petitioner's version. Once such

opportunity is given, appropriate orders can be

passed within two weeks.

Sd/-

V.G.ARUN

JUDGE NB/14-6 WP(C) NO. 19141 OF 2022

APPENDIX OF WP(C) 19141/2022

PETITIONER'S EXHIBITS

EXHIBIT P1 TRUE COPY OF LETTER OF AWARD NO.

KMRL/PROCUREMENT/LOA/2021-22/02 DATED 12/04/2021 ISSUED BY THE 1ST RESPONDENT EXHIBIT P2 TRUE COPY OF NOTICE TO PROCEED NO.

KMRL/PRJ/GMP/KNCO2/449/2020/1187 DATED 28/04/2021 ISSUED BY THE 2ND RESPONDENT EXHIBIT P3 TRUE COPY OF LETTER NO. KMRL/PRJ/GMP/ 449/2020/ KNCO2/1756 DATED 09.03.2022 ISSUED THE 1ST RESPONDENT EXHIBIT P4 TRUE COPY OF LETTER NO CC/KMRL/BD/150/1273/ 2022 DATED 12.03.2022 ISSUED BY THE PETITIONER EXHIBIT P5 TRUE COPY OF NOTICE OF TERMINATION OF CONTRACT NO. KMRL/PRJ/GMP/449/2020/ KNC02/1862 DATED 04/05/2022 ISSUED BY THE 2ND RESPONDENT EXHIBIT P6 TRUE COPY OF RELEVANT PAGES OF THE CONTRACT NO:

KMRL/PRJ/GMP/449/2020/KNC02- TENDER DOCUMENTS, VOLUME 2 OF GENERAL CONDITIONS OF CONTRACT OF KOCHI METRO RAIL LIMITED EXHIBIT P7 TRUE COPY OF REPLY NO CC/KMRL/BD/150/1331/ 2022 DATED 13/05/2022 GIVEN BY THE PETITIONER EXHIBIT P8 TRUE COPY OF ORDER OF TERMINATION BEARING NO KMRL/PRJ/GMP/449/2020/KNC02/1899 DATED 04/06/2022 ISSUED BY THE 2ND RESPONDENT

RESPONDENTS EXHIBITS: NIL

TRUE COPY P.A. TO JUDGE

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter