Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Zerone Consulting Pvt Ltd vs K.S.E.B
2022 Latest Caselaw 24 Ker

Citation : 2022 Latest Caselaw 24 Ker
Judgement Date : 3 January, 2022

Kerala High Court
Zerone Consulting Pvt Ltd vs K.S.E.B on 3 January, 2022
               IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
         THE HONOURABLE MR.JUSTICE MURALI PURUSHOTHAMAN
     MONDAY, THE 3RD DAY OF JANUARY 2022 / 13TH POUSHA, 1943
                       WP(C) NO. 19554 OF 2013
PETITIONER:

          M/S.ZERONE CONSULTING PVT LTD
          FIRST FLOOR, GCDA COMPLEX, JOURNALIST COLONY ROAD,
          KALOOR, KOCHI - 17., REP. BY ITS DIRECTOR, ASHIQ AL
          JHAN.
              BY ADVS.
                  S.ANANTHAKRISHNAN
                  N.K.SUBRAMANIAN



RESPONDENTS:

    1     KERALA STATE ELECTRICITY BOARD
          REP. BY ITS SECRETARY, VYDHYUTHIBHAVAN, TRIVANDRUM -
          695 001.
    2     THE SUB-ENGINEER
          KSEB, ELECTRICAL SECTION, KALOOR, KOCHI - 682 017.
    3     ASSISTANT ENGINEER
          KSEB, ELECTRICAL SECTION, KALOOR, KOCHI - 682 017.
    4     DEPUTY CHIEF ENGINEER
          KSEB, ELECTRICAL CIRCLE, POWER HOUSE ROAD, KOCHI -
          682 018.


              SMT.NAZEEBA.O.H.,SC, KERALA STATE ELECTRICITY BOARD
              SRI.B.PREMOD, SC,KERALA STATE ELECTRICITY BOARD



     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
05.10.2021, THE COURT ON 03.01.2022 DELIVERED THE FOLLOWING:
 W.P.(C) 19554/2013                     2

                                  JUDGMENT

The petitioner is a company engaged in the development of

software and related services and certified to be so by the Software

Technology Parks of India (STPI). The petitioner's premises are private

bonded warehouses and the Commissioner of Customs has approved the

premises as 100% Export Oriented Units (EOU) by Ext.P3 license.

According to the petitioner, due to paucity of space, petitioner has taken

on lease additional space of 1761 Sq. Ft. for monthly rent at Door No.

36/2214C of the Corporation of Cochin and the said space is also

utilized for software development and the same has been certified and

recognized by the Director of STPI and approved as a private bonded

warehouse and 100% EOU by the Commissioner of Customs in Ext. P3

license. Out of this total area of 1761 Sq. Ft., an extent of 500 Sq. Ft.

was used by the petitioner for training its employees and prospective

employees under the trade name 'EazyLearn', as part of software

development activity. According to the petitioner, the cost of the training

is usually charged to the prospective employees and the cost is refunded

if the prospective employees are not absorbed by the Company after the

training.

2.The petitioner applied for electricity connection to the additional

space taken on lease under LT-IV tariff as the petitioner is engaged in

the software development business in the said premises. The petitioner

was provided electricity connection under LT-IV tariff by the Board.

3. While so, the 2nd respondent, the Sub-Engineer inspected the

said premises and issued Ext. P7 site mahazar stating that the petitioner

is also engaged in training activity and recommended to change the

tariff to the Training Center's tariff. In Ext. P7, it is also stated that the

petitioner has exceeded the sanctioned connected load. The petitioner

filed Ext. P8 explanation objecting to the findings in the mahazar and

requested for a joint inspection. However, without reference to Ext. P8

explanation, the petitioner was issued with Ext. P9 provisional short

assessment bill for Rs. 84,685/-. According to the petitioner, while the

recommendation in Ext. P7 site mahazar was only to change the tariff to

Training Center's tariff viz; LT-VI(B), the tariff was changed from LT-IV

to LT-VII (A) (Commercial tariff).

4. Challenging Ext. P7 site mahazar, Ext. P9 provisional short

assessment bill and the tariff category change, the petitioner filed an

appeal before the Assistant Engineer, the 3rd respondent. However, the

3rd respondent rejected the appeal by Ext. P10 order. The petitioner,

therefore, preferred Ext. P11 appeal before the Deputy Chief Engineer,

the 4th respondent. As per Ext. P13 order, the 4th respondent rejected the

appeal. According to the petitioner, no plausible reasons have been

stated in Ext. P13 to justify the change in tariff and the calculation of

connected load therein is incorrect and vitiated by errors apparent on the

face of the record.

5. The petitioner challenged the action of the respondents before

the Consumer Disputes Redressal Forum and the said Forum partly

allowed the complaint holding that the petitioner has to be charged

under LT VI (B), ie. Training centers' tariff. However, the State

Commission reversed the said order and dismissed the complaint

holding that the Forum lacks jurisdiction to entertain the complaint.

Accordingly, the petitioner has preferred this writ petition challenging

Ext. P7 site mahazar, Ext. P9 bill, Ext. P10 and Ext. P13 orders and the

change of tariff to LT-VII(A) and the bills issued thereunder.

6. A counter affidavit is filed on behalf of the respondents resisting

the averments in the writ petition. It is stated therein that an electric

connection bearing Consumer No.8296 was given to the petitioner on

13.10.2006 under LT-IV tariff having a connected load of 32960 Watts.

However, on an inspection conducted on 09.05.2007 by the officials of

the Board, it was found that the petitioner is running a firm in the same

premises in the name 'Easy Learn Training Project and Placement'. It is

further stated that the said firm is a training center, for IT and other

professionals and providing placement in various companies and the

same was displayed in the display board of the Company and thus there

is misuse of energy by taking electric connection in a considerably

lower tariff and using for higher tariff purpose. As per the Board rules,

whenever a consumer is using a single connection for different purposes

covering under different tariffs, the consumer should be assessed totally

in higher tariff. It is also stated that before passing Ext. P13 order, the

Deputy Chief Engineer visited the premises and came to a conclusion

that the training conducted by the firm is not part of the procedure of

production line for software development which can be billed under LT-

IV tariff and that the firm is engaged in multiple activities and therefore,

the activity for which higher tariff is applicable is to be considered for

the whole installation and the decision to apply LT-VII (A) tariff is right.

With regard to the contentions of the petitioner regarding the calculation

of connected load, the counter affidavit states that the calculation is

correct and the same was verified by the appellate authority.

7.The petitioner has filed a reply affidavit reiterating the

contentions in the writ petition and traversing the averments of the

respondents in the counter affidavit. The petitioner has also filed an

interlocutory application dated 17.12.2020 in the writ petition stating

that in view of Covid-19 pandemic, the petitioner has surrendered the

building to which the connection was obtained to the landlord and for

direction to the respondents to consider their request dated 29.07.2020

to dismantle the connection given in the name of the petitioner.

8.I have heard Sri. S. Ananthakrishnan, the learned counsel for the

petitioner and Sri. B.Premod, the learned standing counsel for the

Kerala State Electricity Board.

9.According to Sri. Ananthakrishnan, training imparted to

employees and prospective employees under the trade name 'EazyLearn'

is integral part of petitioner's software development activity and

therefore, the tariff applicable to the petitioner is LT-IV. The learned

counsel submits that the Deputy Chief Engineer has misconstrued

'EazyLearn' as a 'firm', whereas the same is part of petitioner's software

development company. Even if it is assumed that the petitioner is

engaged in training activity, the higher tariff applicable for the whole

installation can only be LT-VI(B), the one applicable to training centers

and not LT-VII(A). According to the learned counsel, the reasons stated

in Ext. P13 order by the Deputy Chief Engineer to apply LT-VII(A)

tariff is not based on materials but on conjunctures and surmises. Sri.

Ananthakrishnan also contends that the finding regarding Connected

Load is also factually incorrect and there are errors apparent on the face

of the record in Ext.P13 order. The learned counsel took me through

Ext.P11 appeal memorandum filed before the Deputy Chief Engineer

wherein it is averred that the total load of the air conditioners comes to

18.3 tons (8.3+5.5+2.5+2) and that of the UPS comes to 7.5 KVA. In

Ext. P13, the Deputy Chief Engineer has taken the total tonnage of the

air conditioners as 25.8 tons (18.3 + 7.5) and calculated the total load of

air conditioners as 32.64 KW and further added 7.5 KVA towards power

rating of UPS. The learned counsel contends that if this error is rectified,

the connected load of the petitioner will be well below the sanctioned

load. Sri. Ananthakrishnan submits that the respondents have not

rebutted the contentions of the petitioner regarding the calculation of

connected load.

10. Per contra, Sri. Premod would contend that the Deputy Chief

Engineer after inspecting the premises of the petitioner found that the

training conducted by the petitioner is not part of software development

activity which can be billed under LT-IV tariff meant for industrial

purpose and that since the firm is engaged in multiple activities, the

activity for which higher tariff is applicable is to be considered for the

whole installation and therefore the decision to apply LT-VII (A) tariff

cannot be faulted. Sri. Premod also submits that power plugs wrongly

included in the assessment in Ext. P7 site mahazar have been excluded

by the appellate authority while assessing the connected load in Ext. P13

and the tonnage of air conditioners was calculated as per the statement

of the petitioner in Ext. P11 and there are no errors in the calculation of

connected load.

11. I have considered the rival submissions. So far as the

contentions of Sri. Ananthakrishnan with regard to change of tariff from

LT-IV to LT-VII(A), it will be apposite to extract the findings of the

appellate authority in Ext. P13 as hereunder:-

"In the circumstances, I need verify and find out whether the training being conducted as admitted by the appellant is a part of the procedure or production line for software development which can be billed under LT IV tariff. I visited the firm and the appellant was present at site. The lady Manager at the reception desk and the appellant informed that the trainees undergoing training at the center will not be fully absorbed in the company. Also it is not being done as a part of appointment but as a

commercial training package accepting a consolidate fee. On completion if vacancy exists they will be given job in the firm where they are doing software development also. So, this can be considered as a firm with multiple activity and hence the one for which the higher tariff is applicable is to be considered for the whole installation and hence the action of applying LT VII A tariff is correct."

The contention of the petitioner is that training imparted to employees

and prospective employees in the training center for its software export

needs is integral part of the petitioner's software development activity.

This contention was rejected by the appellate authority stating that the

trainees undergoing training at the center will be given job in the

company only if vacancy exists. This cannot be a cogent reason to arrive

at a finding that the training imparted at the center is not part of the

petitioner's software development activity. Further, there is no mention

in Ext. P13 regarding the training said to be imparted to the employees

of the company. The reasons that weighed with the appellate authority to

consider the petitioner as a firm with multiple activities are not plausible

and are based only on inferences.

12.According to the respondents, the petitioner is engaged in

multiple activities and therefore, the activity for which higher tariff is

applicable is to be considered for the whole installation. Multiple

activities of the petitioner according to the respondents are (i) software

development and (ii) training. In Ext. P7, the 2nd respondent has

recommended to change the tariff as applicable to training centers. The

tariff applicable to training centers is LT-IV (B). The activity of the

petitioner for which higher tariff is applicable is training. Being so, there

is no justifiable reason in Ext. P13 order as to why commercial tariff

under LT-VII(A) has been made applicable to the petitioner.

13.The learned counsel for the petitioner was able to demonstrate

from Ext. P11 appeal memorandum and Ext. P13 order that the finding

regarding Connected Load is factually incorrect and there is error

apparent on the face of the record in Ext.P13 order. The total tonnage of

the air conditioners was assessed by the 4th respondent inclusive of the

power load of UPS. This depicts non-application of mind on the part of

the appellate authority, the 4th respondent, in passing Ext.P13 order on a

statutory appeal.

14.Accordingly, I set aside Ext.P13 order. The 4th respondent is

directed to consider Ext.P11 appeal afresh after hearing the petitioner

through virtual or physical mode and pass appropriate orders in

accordance with law with regard to the tariff applicable to the petitioner

and the assessment of connected load. The 4th respondent shall decide

the appeal within two months from the date of receipt of a copy of this

judgment. All coercive steps against the petitioner pursuant to Ext. P9

shall stand deferred till the 4th respondent decides the appeal. Nothing

stated above shall be construed as an expression of any opinion on the

merits of the appeal. The request of the petitioner dated 29.07.2020 to

dismantle the connection given in the name of the petitioner may also be

considered appropriately, if not already done.

The writ petition is disposed of with the above directions.

Sd/-

MURALI PURUSHOTHAMAN JUDGE

APPENDIX OF WP(C) 19554/2013

PETITIONER's EXHIBITS EXT.P1: TRUE COPY OF LICENSE RENEWAL LETTER DT. 15/4/2010. EXT.P2: TRUE COPY OF THE GREEN CARD ISSUED TO THE PETITIONER. EXT.P3: TRUE COPY OF THE CUSTOMS BONDED HOUSE LICENSE. EXT.P4: TRUE COPY OF THE LETTER DT. 27/7/2006 OF STPI APPROVING THE NEW PREMISES.

EXT.P5: TRUE COPY OF THE TRADEMARK APPLICATION DT. 13/9/2005. EXT.P6: TRUE COPY OF THE RELEVANT PAGES OF THE TARIFF ORDER. EXT.P7: TRUE COPY OF SITE MAHAZER DT. 9/5/2007.

EXT.P8: TRUE COPY OF THE LETTER DT. 22/5/07 OF THE PETITIONER. EXT.P9:TRUE COPY OF THE BILL DT. 22/5/07.

EXT.P10: TRUE COPY OF THE ORDER OF 3RD RESPONDENT DT.

30/06/2007.

EXT.P11: TRUE COPY OF THE MEMORANDUM OF APPEAL DT.18/08/2007. EXT.P12: TRUE COPY OF THE NOTES OF ARGUMENTS DT. 18/8/2007. EXT.P13: TRUE COPY OF THE ORDER OF 4TH RESPONDENT DT.

2/01/2008.

EXT.P14: TRUE COPY OF THE RELEVANT PAGES OF IT POLICY OF 2007 & 2012.

EXT.P15: TRUE COPY OF THE RELEVANT PAGES OF THE TARIFF ORDER. EXT.P16: TRUE COPY OF BILL DT. 29/8/2006.

EXT.P17: TRUE COPY OF THE CERTIFICATE DT. 8/10/2010 OF THE MANUFACTURER.

EXT.P18: TRUE COPY OF THE RELEVANT PAGES OF TERMS & CONDITIONS OF SUPPLY 2005.

EXT.P19: TRUE COPY OF THE ORDER OF THE CONSUMER FORUM, ERNAKULAM.

EXT.P20: TRUE COPY OF THE ORDER OF THE CONSUMER STATE COMMISSION.

spc/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter