Citation : 2021 Latest Caselaw 19215 Ker
Judgement Date : 14 September, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE P.B.SURESH KUMAR
TUESDAY, THE 14TH DAY OF SEPTEMBER 2021 / 23RD BHADRA,
1943
WP(C) NO. 15259 OF 2021
PETITIONER:
SHRI.G.BALAKRISHNAN NAIR,
AGED 62 YEARS, S/O. GOPALA PILLAI,
GOKULAM, 32/2255A, NEW KALAVATH ROAD,
PALARIVATTOM, KOCHI-682025.
BY ADVS.
S.SREEKUMAR (SR.)
P.MARTIN JOSE
P.PRIJITH
THOMAS P.KURUVILLA
R.GITHESH
AJAY BEN JOSE
MANJUNATH MENON
SACHIN JACOB AMBAT
HARIKRISHNAN S.
RESPONDENTS:
1 STATE OF KERALA,
REPRESENTED BY ITS PRINCIPAL SECRETARY,
IRRIGATION AND WATER RESOURCES DEPARTMENT,
SECRETARIAT, THIRUVANANTHAPURAM-695001.
2 THE CHIEF ENGINEER,
IRRIGATION AND ADMINISTRATION,
THIRUVANANTHAPURAM-695013.
3 THE SUPERINTENDING ENGINEER,
IRRIGATION SOUTH CIRCLE, 2ND FLOOR,
CWC BUILDING, LMS COMPOUND,
THIRUVANANTHAPURAM-695033.
W.P.(C) No.15259 of 2021 2
4 MR. PRAVEEN KUMAR K.G.,
SOUPARNIKA, THALAVADY P.O.,
ALAPPUZHA-689572.
SMT.PRINCY XAVIER GOVERNMENT PLEADER
SRI.K.JAJU BABU (SR.)
SRI.BRIJESH MOHAN
SMT.RESMI G. NAIR
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR
ADMISSION ON 14.09.2021, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
W.P.(C) No.15259 of 2021 3
P.B.SURESH KUMAR, J.
-------------------------------------------
W.P.(C) No.15259 of 2021
-----------------------------------------------
dated this the 14th day of September, 2021
JUDGMENT
In terms of Ext.P1 tender notice, the third
respondent invited online bids for executing a work for removal
of earth deposited during flood from 'varattar' and
'Adhipamba' rivers in Pathanamthitta District. Both petitioner
and the fourth respondent submitted bids pursuant to Ext.P1
tender notice. The bid submitted by the fourth respondent was
the highest. Though the rate quoted by the fourth respondent
was Rs.501/- per cubic meter, on negotiation, the fourth
respondent raised his offer to Rs.684/- per cubic meter. On
02.06.2020, the third respondent awarded the work to the
fourth respondent and directed him to furnish the security
deposit namely Rs.2,19,65,800/-in the manner prescribed and
execute the agreement in stamp paper worth Rs.4,39,400/-
within 14 days without fine and within 24 days with fine.
Ext.P5 is the selection notice issued by the third respondent to
the fourth respondent in this regard. The fourth respondent did
not furnish the security deposit within the time stipulated in
Ext.P5 selection notice. Instead, on 25.09.2020, he submitted a
representation to the third respondent seeking orders enlarging
the time fixed for furnishing the security deposit and execution
of the agreement in the light of the restrictions imposed by the
Government for preventing the spread of Covid-19 pandemic.
On the basis of the request made by the the fourth respondent,
the third respondent granted time to the fourth respondent till
26.10.2020 for furnishing security deposit and execution of the
agreement. Ext.R3(a) is the communication issued by third
respondent in this regard on 21.10.2020.
2. It appears that the third respondent
entertained a doubt in the meanwhile as to the amount of the
security deposit to be furnished by the fourth respondent, and
after clearing the said doubt, the third respondent issued
Ext.P6 communication to the fourth respondent on 30.10.2020
stating that the amount of the security deposit to be furnished
by him is Rs.4,39,31,500/-. In terms of Ext.P6 communication,
the third respondent directed the fourth respondent to furnish
the security deposit and execute the agreement within seven
days from the date of receipt of the said communication. The
fourth respondent did not execute the agreement within the
time stipulated in Ext.P6 communication as well. Instead, as
the security deposit was doubled, on 23.12.2020, the fourth
respondent preferred a representation to the third respondent
seeking permission to furnish the security deposit in
instalments. Ext.R4(f) is the representation submitted by the
fourth respondent in this regard. Ext.R4(f) representation was
rejected by the third respondent on 24.03.2021.
3. In the meanwhile, on 11.02.2021, the petitioner submitted Ext.P7 representation to the third
respondent requesting the third respondent to award the work
to him pointing out that since the fourth respondent has not
furnished the security deposit and executed the agreement
within the time stipulated in Ext.P5, the work ought to have
been awarded to the petitioner. On the same day on which the
request of the fourth respondent to furnish the security deposit
in instalments was rejected, the third respondent gave Ext.P8
communication to the petitioner requiring to intimate the third
respondent as to whether the petitioner is prepared to
undertake the work at the rate of Rs.684/- per cubic meter
quoted by the fourth respondent. In response to Ext.P8
communication, the petitioner submitted Ext.P9 willingness to
execute the work at the rate quoted by the fourth respondent.
No action was, however, taken on Ext.P9 willingness furnished
by the petitioner. The petitioner, in the circumstances,
preferred a representation to the Chief Minister of the State
complaining about the inaction on the part of the third
respondent in awarding the work to him. Ext.P11 is the
representation submitted by the petitioner to the Chief
Minister. It appears that the said representation has been
forwarded to the office of the third respondent and in the light
of the same, the third respondent has informed the petitioner
that appropriate decision as regards the claim of the petitioner
will be taken by the second respondent soon. Ext.P12 is the
communication issued by the third respondent in this regard.
The writ petition is filed immediately thereafter seeking
directions to respondents 2 and 3 to enter into necessary
agreement with the petitioner for execution of the work. The
case set out by the petitioner in the writ petition is that insofar
as the highest bidder has not executed the agreement within
the time initially stipulated and later enlarged, the petitioner
who is the second highest bidder in the bid process ought to
have been awarded the work.
4. On 30.07.2021, this Court directed the parties
to maintain status quo as regards the work..
5. A statement has been filed on behalf of the
third respondent pointing out that since the fourth respondent
has not furnished the security deposit and executed the
agreement despite having been given sufficient time, the
second respondent, the Chief Engineer of the department has
placed the matter before the Government for appropriate
decision in this regard, and on 14.07.2021, the Government
issued Ext.R3(c) communication to the second respondent
directing him to give seven more days to the fourth respondent
to furnish the security deposit and execute the agreement. It is
stated on behalf of the third respondent that Ext.R3(c)
communication was brought to the notice of the fourth
respondent on 16.07.2021, and in the light of the said
communication, the fourth respondent ought to have furnished
the security deposit and executed the agreement on or before
23.07.2021. It is stated on behalf of the third respondent that
on the next working day, the fourth respondent requested the
third respondent to grant 15 days time more to furnish the
security deposit pointing out his inability to obtain bank
guarantee for the huge sum of money in that short span of
time as the banks are not functioning on regular basis due to
the restrictions imposed by the Government for the prevention
of the Covid-19 pandemic. It is also stated on behalf of the
third respondent in the statement that immediately thereafter
on 04.08.2021, the fourth respondent completed the
formalities for execution of the agreement including furnishing
of the security deposit and the agreement was not executed by
the department with the fourth respondent in the light of the
interim order passed by this Court in the meanwhile on
30.07.2021. It is also stated in the statement that having
regard to the disruptions caused to the normal life on account
of the pandemic, insofar as the fourth respondent has
completed all the formalities relating to the execution of the
agreement, the department does not find any impediment in
entering into the necessary agreement with the fourth
respondent for execution of the work.
6. A counter affidavit has been filed by the fourth
respondent stating, among others, that though he was
informed in terms of the selection notice that the amount of
security deposit to be furnished by him for the work is
Rs.2,19,65,800/-, the same was revised later to
Rs.4,39,31,500/- in terms of Ext.P6 communication issued on
30.10.2020, at a point of time when the Government was
considering the question of reducing the security deposits to be
furnished by the contractors for similar works in the wake of
the pandemic; that he was therefore, advised to wait until the
Government takes a decision in this regard and while so, on
07.01.2021, in terms of Ext.R4(g) order, the Government
reduced the security deposit to be furnished for similar works
substantially; that in the light of Ext.R4(g) order of the
Government, the department themselves sought clarification
from the Government as to the security deposit to be furnished
by him for the subject work, and that it was while the said
request for clarification was pending consideration before the
Government that the Government has issued Ext.R3(c)
communication. It is also stated by the fourth respondent in the
counter affidavit that since no decision was forthcoming from
the Government on the issue relating to the quantum of
security deposit to be furnished by him and since the
Government has issued Ext.R3(c) decision in the meanwhile, he
decided to furnish security deposit in tune with Ext.P6
communication and it is on that basis that he has furnished
security deposit for the work. It is also stated in the counter
affidavit that the delay of a few days in complying with the
direction contained in Ext.R3(c) was due to the delay caused by
the bank in providing the bank guarantee sought by him as the
banks were not functioning on regular basis then due to the
restrictions in connection with the pandemic. It is also
mentioned by the fourth respondent in the counter affidavit
that the rate quoted by the petitioner for the work is less by
Rs.16,44,21,939/- when compared to the rate quoted by him.
7. Heard the learned Senior Counsel for the
petitioner, the learned Government Pleader as also the learned
Senior Counsel for the fourth respondent.
8. The learned Senior Counsel for the petitioner
submitted that in Ext.P5 selection notice, it is categorically
mentioned that if the fourth respondent does not execute the
agreement within the time stipulated therein, the work will be
awarded to the second highest bidder. According to the learned
Senior Counsel, admittedly the fourth respondent has not
executed the work within the time stipulated in Ext.P5
selection notice. It is argued by the learned Senior Counsel
therefore, that the third respondent ought to have awarded the
work to the petitioner as he was the second highest bidder in
the bid process. It was also argued that at any rate, since the
fourth respondent has not furnished the security deposit for the
work and executed the agreement within the time stipulated by
the Government even in Ext.R3(c) direction issued by the
Government, the work should have been awarded to the
petitioner. It was further argued that insofar as the petitioner
has agreed to execute the work at the rate quoted by the
highest bidder, the fourth respondent, there was absolutely no
justification for the third respondent in not awarding the work
to the petitioner. It was all the more so, according to the
learned Senior Counsel, since the work in question was one to
be executed on an emergent basis.
9. The learned Government Pleader has pointed
out that insofar as the fourth respondent has completed all the
formalities in connection with the execution of the agreement
pursuant to Ext.R3(c) direction issued by the Government,
though there is delay of a few days in complying with the said
direction, there is no impediment for the department in
entering into the agreement with the fourth respondent for
execution of the work. It was also pointed out by the learned
Government Pleader that but for the interim order passed by
this court on 30.07.2021, the department ought to have been
entered into the agreement with the fourth respondent for
execution of the work.
10. The learned Senior Counsel for the fourth
respondent reiterated the stand of the fourth respondent in the
counter affidavit filed in the matter. It was emphatically argued
by the learned Senior Counsel that in the light of Ext.R4(g)
order of the Government, the fourth respondent was not liable
to furnish security deposit to the tune of Rs.4,39,31,500/- for
the subject work and it was with a view to complete the work at
the earliest point of time that he has decided to comply with
the direction of the Government contained in Ext.R3(c)
communication. It was argued by the learned Senior Counsel
that in cases of this nature, the officers of the Department
would be well within their powers in granting time for execution
of the agreement for works, if the contractors concerned are
willing to execute the work on the same terms and conditions
offered by them. The learned Senior Counsel has relied on the
decision of the Apex Court in Bharat Coking Coal Ltd. v.
AMR Dev Prabha, (2020) 16 SCC 759, in support of the said
point urged by him.
11. I have perused the pleadings of the parties and
considered the contentions put forward by their learned
counsel.
12. As noted, the security deposit directed to be
furnished by the fourth respondent in terms of Ext.P5 selection
notice dated 02.06.2020 was only Rs.2,19,65,800/-. Ext.P6
communication of the third respondent indicating the revised
security deposit of the work namely, Rs.4,39,31,500/- was
issued to the fourth respondent only on 30.10.2020. The
specific case of the fourth respondent is that though he was
prepared to furnish the security deposit in terms of Ext.P5
selection notice and execute the agreement for the work on
30.06.2020, he was not permitted to do so by the third
respondent on account of the doubt entertained by him as to
the security deposit to be furnished by him for the subject
work. The fact that the fourth respondent has purchased the
stamp paper required for executing the work on 30.06.2020 is
evidenced by Ext.R4(d), the copies of the stamp paper. Ext.P6
communication and Ext.R4(d) stamp papers probablise the
case of the fourth respondent that he has made all
arrangements for execution of the agreement for the work
before 30.06.2020. Again, as noted, the revision of the security
deposit for the work was to the tune of almost Rs.2.2 crores.
Ext.R4(g) order of the Government indicates that in the wake of
the Covid-19 pandemic, on 13.5.2020, the Government of India
requested the State Governments to relax the terms of
security deposits to be furnished by the contractors in respect
of procurements and it is in the light of the said request of the
Central Government that the said order has been issued by the
Government. In other words, Ext.R4(g) would probabilise the
case of the fourth respondent that Ext.P6 communication was
issued at a point of time when the Government was examining
the question of relaxing the terms of security deposits to be
furnished by the contractors in respect of procurements. It is
seen that it is in the said circumstances, the fourth respondent
preferred Ext.R4(h) representation before the third respondent
requesting him to revise the security deposit to be furnished by
the fourth respondent in tune with Ext.R4(g) order of the
Government. It is also seen that it is having convinced that
there is merit in the request made by the fourth respondent in
Ext.R4(h) representation, the second respondent placed the
matter before the Government in terms of Ext.R4(j)
communication for a decision as to the security deposit to be
furnished by the fourth respondent. Exts.R4(g), R4(h) and R4(j)
documents would probabilise the case of the fourth respondent
that the agreement for the subject work could not be executed
by him on account of the doubt entertained by the officials of
the department as to the quantum of the security deposit to be
furnished by him. It is further seen that it was while Ext.R4(j)
request made by the second respondent before the
Government was pending consideration, the Government
issued Ext.R3(c) communication directing the department to
forfeit the earnest money deposit furnished by the fourth
respondent if he does not complete the formalities regarding
the execution of the agreement within seven days. As seen
from the materials on record, pursuant to the said direction, the
fourth respondent has furnished the security deposit in tune
with Ext.P6 communication. Of course, there was a delay of
nine days in complying with the direction contained in Ext.R3(c)
communication. In a case of this nature, as rightly contended
by the learned Senior Counsel for the fourth respondent, the
department is well within its power in granting enlargement of
time, and I do not, therefore, find any impropriety or illegality in
the stand taken by the department that they would have
entered into the necessary agreement with the fourth
respondent but for the interim order passed by this Court on
30.07.2021, especially when the petitioner has no case that the
stand aforesaid of the officials is vitiated by malice. I am
fortified in this view by the decision of the Apex Court in
Bharat Coking Coal Ltd. Paragraphs 46 and 47 of of the
said judgment read thus:
46. With regard to other allegations concerning condonation of Respondent 6's delay in producing guarantees, we would only
reiterate that there is no prohibition in law against public authorities granting relaxations for bona fide reasons. In Shobikaa Impex (P) Ltd. v. Central Medical Services Society, it has been noted that: (SCC p. 243, para 20)
"20. ... the State can choose its own method to arrive at a decision and it is free to grant any relaxation for bona fide reasons, if the tender conditions permit such a relaxation. It has been further held that the State, its corporations, instrumentalities and agencies have the public duty to be fair to all concerned. Even when some defect is found in the decision-making process, the Court must exercise its discretionary powers under Article 226 with great caution and should exercise it only in furtherance of public interest and not merely on the making out of a legal point."
47. Even if there had been a minor deviation from explicit terms of the NIT, it would not be sufficient by itself in the absence of mala fide for courts to set aside the tender at the behest of an unsuccessful bidder. This is because notice must be kept of the impact of overturning an executive decision and its impact on the larger public interest in the form of cost overruns or delays.
13. Be that as it may, in a case of this nature, of
course, the department would be well within its power to award
the work to the second highest bidder, if the highest bidder
does not furnish the security deposit and execute the
agreement within the time stipulated. But that does not mean
that the failure on the part of the highest bidder in furnishing
security deposit and executing the agreement within the time
stipulated would confer a right on the second highest bidder to
get the work awarded to him. In other words, even if there is
failure on the part of the highest bidder in furnishing security
deposit and executing the agreement on receipt of selection
notice, the same does not confer any right to the second
highest bidder to claim that the work shall be awarded to him.
Identical is the stand taken by this Court in Rajesh C. v.
District Collector, 2012 (2) KHC 185 and the Calcutta High
Court in Sarbangapur Fishermen's Co-operative Society
v. State of West Bengal, 2018 SCC Online Cal 8094. It is all
the more so since it is trite that the bidders participating in the
tender process have no right other than the right to equality
and fair treatment in the matter of evaluation of the
competitive bids offered by the interested persons in response
to notice inviting tenders in a transparent manner and free
from any hidden agenda [See Meerut Development
Authority v. Assn. of Management Studies, (2009) 6 SCC
171].
The writ petition, in the circumstances is without
merits and the same is, accordingly, dismissed.
Sd/-
P.B.SURESH KUMAR, JUDGE.
YKB
APPENDIX OF WP(C) 15259/2021
PETITIONER EXHIBITS
Exhibit P1 TRUE COPY OF E-TENDER NO.
03/EOI/2019/SE/ISC NOTICE DATED
01/01/2020 ISSUED BY THE 3RD
RESPONDENT.
Exhibit P2 TRUE COPY OF TERMS AND CONDITIONS AND
SCOPE OF THE WORK TO BE UNDERTAKEN BY
THE SUCCESSFUL BIDDER ISSUED BY THE 3RD
RESPONDENT ALONG WITH EXHIBIT P1.
Exhibit P3 TRUE COPY OF COMMUNICATION DATED
19/05/2020 ISSUED BY THE 1ST RESPONDENT
TO THE 2ND RESPONDENT.
Exhibit P4 TRUE COPY OF COMMUNICATION DATED
29/05/2020 ISSUED BY THE 2ND RESPONDENT
TO THE 3RD RESPONDENT.
Exhibit P5 TRUE COPY OF NOTICE OF SELECTION DATED
02/06/2020 ISSUED BY THE 3RD RESPONDENT
TO THE 4TH RESPONDENT.
Exhibit P6 TRUE COPY OF NOTICE DATED 30/10/2020
ISSUED BY THE 3RD RESPONDENT TO THE 4TH
RESPONDENT.
Exhibit P7 TRUE COPY OF REPRESENTATION DATED
11/02/2021 SUBMITTED BY THE PETITIONER
TO THE 3RD RESPONDENT.
Exhibit P8 TRUE COPY OF COMMUNICATION DATED
24/03/2021 3RD RESPONDENT ISSUED TO THE
PETITIONER.
Exhibit P9 TRUE COPY OF COMMUNICATION DATED
05/04/2021 TO THE 3RD RESPONDENT
INTIMATING ACCEPTANCE OF THE GOVERNMENT APPROVED RATE OF RS. 684/M3 FOR
EXECUTING THE WORK.
Exhibit P10 TRUE COPY OF COMMUNICATION DATED 24/03/2021 ISSUED BY THE 3RD RESPONDENT TO THE 4TH RESPONDENT INTIMATING REJECTION OF REQUEST TO PAY THE SECURITY DEPOSIT IN FIVE INSTALMENTS.
Exhibit P11 TRUE COPY OF REPRESENTATION DATED 31/05/2021 SUBMITTED BY THE PETITIONER BEFORE THE HON'BLE CHIEF MINISTER.
Exhibit P12 TRUE COPY OF COMMUNICATION DATED 05/07/2021 ISSUED BY THE 3RD RESPONDENT TO THE PETITIONER.
RESPONDENTS EXHIBITS Exhibit R3(A) COPY OF THE LETTER DATED 21.10.2020 Exhibit R3(B) COPY OF THE LETTER DATED 30.10.2020 Exhibit R3(C) COPY OF THE GOVERNMENT LETTER DATED 14.07.2021 Exhibit R3(D) COPY OF THE LETTER DATED 14.07.2021 ISSUED BY 3RD RESPONDENT.
Exhibit R4(A) TRUE COPY OF THE LETTER VIDE NO.D6-
3911/2019/ISC DATED 29.01.2020 ISSUED BY THE 3RD RESPONDENT TO THE 2ND RESPONDENT ALONG WITH TYPED COPY Exhibit R4(B) TRUE COPY OF THE LETTER VIDE NO.W3-
38940/2019/EOI/DB DATED 14.02.2020 ISSUED BY THE 2ND RESPONDENT TO THE 4TH RESPONDENT Exhibit R4(C) TRUE COPY OF THE LETTER DATED 18.02.2020 SUBMITTED BY THE 4TH RESPONDENT BEFORE THE 2ND RESPONDENT ALONG WITH TYPED COPY Exhibit R4(D) TRUE COPY OF THE THREE STAMP PAPERS
DATED 30.06.2020 IN THE NAME OF THE 4TH RESPONDENT.
Exhibit R4(E) TRUE COPY OF THE EMAIL DATED 25.09.2020 SENT BY THE 4TH RESPONDENT TO THE 3RD RESPONDENT.
Exhibit R4(F) TRUE COPY OF THE REPRESENTATION DATED 23.12.2020 SUBMITTED BY THE 4TH RESPONDENT BEFORE THE SUPERINTENDING ENGINEER.
Exhibit R4(G) TRUE COPY OF THE GOVERNMENT ORDER G.O(P)NO.7/2021/FIN DATED 07.01.2021.
Exhibit R4(H) TRUE COPY OF THE REPRESENTATION DATED 19.04.2021 SUBMITTED BY THE 4TH RESPONDENT BEFORE THE 3RD RESPONDENT.
Exhibit R4(I) TRUE COPY OF THE CLARIFICATION LETTER NO.D6-1911/2019/SE/ISC DATED 20.04.2021 ISSUED BY THE 3RD RESPONDENT TO THE 2ND RESPONDENT Exhibit R4(J) TRUE COPY OF THE COMMUNICATION VIDE NO.W3-38940/2019/EOI/DB-2 DATED 08.05.2021 FORWARDED BY THE 2ND RESPONDENT TO THE GOVERNMENT. TRUE COPY OF THE CLARIFICATION LETTER NO.D6-
1911/2019/SE/ISC DATED 20.04.2021 ISSUED BY THE 3RD RESPONDENT TO THE 2ND RESPONDENT Exhibit R4(K) TRUE COPY OF THE CLARIFICATION LETTER NO.D6-1911/2019/SE/ISC DATED 14.07.2021 ISSUED BY THE 3RD RESPONDENT TO THE 4TH RESPONDENT Exhibit R4(L) TRUE COPY OF THE LETTER DATED 19.07.2021 ISSUED BY THE 4TH RESPONDENT TO THE PRIVATE SECRETARY, IRRIGATION AND WATER RESOURCES.
Exhibit R4(M) TRUE COPY OF THE LETTER DATED 19.07.2021 ISSUED BY THE 4TH RESPONDENT TO THE 2ND RESPONDENT.
Exhibit R4(N) TRUE COPY OF THE TREASURY SAVING DEPOSIT CERTIFICATE VIDE NO.JL0404001 DATED 02.08.2021 OF THE SUB TREASURY, CHENGANOOR.
Exhibit R4(O) TRUE COPY OF THE LETTER OF THE STATE BANK OF INDIA DATED 03.08.2021 OFFERING BANK GUARANTEE WITHIN 2 DAYS.
Exhibit R4(P) TRUE COPY OF THE LETTER SUBMITTED BY THE 4TH RESPONDENT BEFORE THE 3RD RESPONDENT AND ITS ACKNOWLEDGMENT Exhibit R4(Q) TRUE COPY OF THE BANK GUARANTEE OFFERED BY THE STATE BANK OF INDIA ON 04.08.2021.
Exhibit R4(R) TRUE COPY OF THE EMAIL SENT BY THE PETITIONER HEREIN ADDRESSED TO THE RESPONDENTS 2 AND 3 ON 23.07.2021.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!