Citation : 2021 Latest Caselaw 8795 Ker
Judgement Date : 17 March, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE P.B.SURESH KUMAR
WEDNESDAY, THE 17TH DAY OF MARCH 2021 / 26TH PHALGUNA, 1942
WP(C).No.19568 OF 2016(U)
PETITIONER:
1 B.SATHYASEELAN
S/O.BHASKARAN,RESIDING AT CHAIDHANYAM,
(UMMARAPALLIL),KOTTATHALA.P.O,KOTTARAKKARA,PIN-
691507.
2 B.SUNDARAN AGED 50 YEARS
S/O.BALAKRISHNAN.RESIDING AT
'CHATHAINYAM',VALLAM,KOTTARAKKARA-691506.
BY ADVS.
SRI.P.G.JAYASHANKAR
SMT.P.SREELAKSHMI
SRI.V.SREEJAYAN
RESPONDENTS:
1 STATE OF KERALA
REPRESENTED BY ITS SECRETARY,DEPARTMENT OF LOCAL SELF
GOVERNMENT,GOVERNMENT SECRETARIAT,TRIVANDRUM-695001.
2 THE ASST.EXECUTIVE ENGINEER
BLOCK PANCHAYATH,VETTIKKAVALA,KOLLAM-691538.
3 THE SECRETARY
BLOCK PANCHAYATH,VETTIKKAVALA,KOLLAM-691538.
R1 BY ADV.SRI.K.J.MANURAJ, GOVERNMENT PLEADER
R3 BY ADV. SRI.V.JAYAPRADEEP SC
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 09-03-
2021, THE COURT ON 17-03-2021 DELIVERED THE FOLLOWING:
WP(C).No.19568 OF 2016(U)
2
W.P.(C) No.19568 of 2016
------------------------------------------
JUDGMENT
The second petitioner undertook to execute a road work of
Vettikavala Block Panchayat as per Ext.P1 agreement executed on
08.06.1999. The first petitioner was the Power of Attorney holder of
the second petitioner for the said work. The site of the work was
handed over to the first petitioner on 01.07.1999. After the
commencement of the work, since it was found that certain works not
included in the agreement are also to be executed by the contractor,
the estimate of the work was revised twice. Later, the first petitioner
sought revision of the estimate again based on the revision of the
schedule of rates introduced by the Government with effect from
1.7.1999. Though the said revision was also proposed by the third
respondent, the Secretary of the Block Panchayat, the same was not
approved by the competent authority. Nevertheless, a supplementary
agreement was executed by the third respondent with the second
petitioner on 04.02.2002 in terms of which the unapproved revision of
the estimate of the work in tune with the schedule of rates introduced
by the Government with effect from 01.07.1999 was made part of the WP(C).No.19568 OF 2016(U)
agreement. Ext.P3 is the supplementary agreement executed in this
regard on 04.02.2002. The first petitioner has completed the work on
31.03.2002. The grievance of the petitioners in the writ petition
concerns the refusal on the part of the respondents in disbursing the
amounts due to them in terms of Ext.P3 supplementary agreement. It
is alleged by the petitioners that the payment is withheld since the
revision of the estimate which is made part of the supplementary
agreement was not approved by the competent authority. The case of
the petitioners in essence is that in the light of G.O.(MS)No.17/2001-
PLANNING dated 18.06.2001, since the request for revision of estimate
has not been approved by the competent authority within the time
stipulated therein, the third respondent was justified in entering into
Ext.P3 supplementary agreement with the second petitioner and
therefore, they are entitled to payments in accordance with Ext.P3
supplementary agreement.
2. Heard the learned counsel for the petitioners, the
learned Government Pleader as also the learned Standing Counsel for
the third respondent.
3. The materials on record indicate that the authority
constituted by the Government, viz, the State Level Technical
Committee for approving the revised estimate proposed by the third
respondent, has examined the revised estimate and decided not to WP(C).No.19568 OF 2016(U)
approve the same holding that the petitioners having undertook to
execute the work based on the estimate prepared in terms of the pre-
revised schedule of rates cannot be extended the benefit of the
revised schedule of rates. It is seen that pursuant to a direction issued
by this Court, the Government has rejected the claim of the petitioners
accepting the stand taken by the State Level Technical Committee in
terms of Ext.R3(c) order. In Ext.R3(c) order, the Government has
arrived at the amount payable to the petitioners in respect of the work
at Rs.20,17,340/-. The relevant portion of the order reads thus:
"5. The estimate was again revised as per PWD schedule rate of 1999 which was Rs.38,92,000/-. The Block Panchayat Committee had resolved to give the rate revision.
6. As per letter No.DB1/7804/08CE/LSGD dated 06.01.2009 of SLTC, when a work was awarded to a contractor, the estimate of the work cannot be revised, and revised A.S. or T.S. cannot be granted. If a contractor is granted a work as per agreement in writing, he should complete the work as per the agreement and maintain the road during the security period. Hence the committee decided not to give permission to the revised estimate.
7. It is seen that the work was lagged forever as desired by the contractor. Rate revision was one of the examples. Rate revision in the M.Book is also another factor, which was done without getting sanction from competent authority.
8. Government had authorised Rs.15,45,794/- as cost of the road work, Rs.3,29,340/- as cost of the bitumen, and Rs.1,42,206/- as admitted balance amount to the petitioner. Thus the total amount comes to Rs.20,17,340/-.
9. As Government was allowed Rs.20,17,340/- instead of Rs.18,84,710/- (Maximum amount payable to the road work as WP(C).No.19568 OF 2016(U)
per the local rate during that period as per G.O.(P)No.218/98/LAD dated 23.10.1999), the petitioner is not eligible for any more amount in the work. Hence his request is rejected."
Despite Ext.R3(c) order, on a subsequent representation preferred by
the first petitioner before the Chief Minister of the State, the
Government revised Ext.R3(c) order and extended to the petitioners
the benefit of the revision of the schedule of rates introduced with
effect from 1.7.1999 as a special case, having regard to the health
condition of the first petitioner, after holding that he is otherwise not
entitled to the benefit of the same. Ext.P16 is the order issued by the
Government in this regard. In Ext.P16 order, the revised amount
payable to the petitioners for the work executed by them applying the
schedule of rates introduced with effect from 1.7.1999 was arrived at
Rs.29,27,736.76/-. Pursuant to Ext.P16 order, the petitioners were
disbursed the amount ordered therein. The memo filed by the
Government Pleader pursuant to the interim order passed by this
Court on 22.01.2021 indicates that in the matter of arriving at the said
figure, the contractor's profit and tender excess have not been
reckoned. In other words, the only surviving question is as to whether
the petitioners are justified in claiming the contractor's profit and
tender excess on the estimate of the work prepared applying the
schedule of rates for the works introduced with effect from
01.07.1999.
WP(C).No.19568 OF 2016(U)
4. In Ext.R3(c) order as also in Ext.P16 order, the
Government has categorically found that the petitioners are not
entitled to the benefit of the schedule of rates introduced by the
Government with effect from 1.7.1999. The said orders have not been
challenged by the petitioners. That apart, Ext.P16 order of the
Government would also show that the petitioners have been extended
the benefit of the revised schedule of rates, having regard to the
health condition of the first petitioner and treating the case as a
special case. As noted by the Government in Ext.R3(c) order, it is a
case where the second petitioner has entered into a solemn
agreement with the third respondent undertaking to execute the work
on an estimate prepared at the pre-revised schedule of rates. Insofar
as the petitioners are unable to establish their right to claim
contractors' profit and tender excess on the estimate prepared
applying the schedule of rates introduced by the Government with
effect from 1.7.1999, no relief can be granted to them in a
proceedings under article 226 of the Constitution.
In the said view of the matter, there is no merit in the writ
petition and the same is, accordingly, dismissed.
Sd/-
P.B.SURESH KUMAR
Mn JUDGE
WP(C).No.19568 OF 2016(U)
APPENDIX
PETITIONERS' EXHIBITS:
EXHIBIT P1 TRUE COPY OF AGREEMENT NO.2 OF 99 -2000 FOR WORKS
DATED 08.06.1999
EXHIBIT P2 TRUE COPY OF ORDER BEARING
NO.G.O(RT)NO.606/99/PWD DATED 23.06.99
EXHIBIT P2(A) TRUE COPY OF THE ORDER DATED 10.07.2000 ISSUED BY THE COMMISSIONER OF RURAL DEVELOPMENT
EXHIBIT P3 TRUE COPY OF THE SUPPLEMENTARY AGREEMENT DATED 04.02.2002
EXHIBIT P4 TRUE COPY OF THE REVISED ESTIMATE PURSUANT TO EXHIBIT P3
EXHIBIT P5 TRUE COPY OF THE POWER OF ATTORNEY EXECUTED BY THE 2ND PETITIONER
EXHIBIT P6 TRUE COPY OF THE JUDGMENT DATED 11.06.2004 IN O.P.NO.2058/2002 OF THIS HON'BLE COURT
EXHIBIT P7 TRUE COPY OF THE LETTER BEARING NO.C/3777/98 DATED 02.11.2002
EXHIBIT P7(A) TRUE COPY OF THE LETTER ISSUED BY THE 1ST RESPONDENT UNDERTAKING THE CHECK MEASUREMENT AND THE FINALIZATION OF THE BILL PURSUANT TO THE REVISED ESTIMATE BEARING NO.47602/DD1/2007/LSGD DATED 29.01.2008
EXHIBIT P8 TRUE COPY OF THE MEASUREMENT BOOK AS OBTAINED UNDER THE RIGHT TO INFORMATION
EXHIBIT P9 TRUE COPY OF THE JUDGMENT DATED 05.06.2013 IN WP(C)5972/2008
EXHIBIT P10 TRUE COPY OF THE APPLICATION FILED UNDER RIGHT TO INFORMATION ACT
EXHIBIT P11 TRUE COPY OF THE REPLY OBTAINED BY THE 1ST PETITIONER
EXHIBIT P12 TRUE COPY OF THE REPRESENTATION DATED 21.04.2016
EXHIBIT P13 TRUE COPY OF THE LETTER NO.LSGD-DD1/156/2015-LSGD DATED 02.05.2016 WP(C).No.19568 OF 2016(U)
EXHIBIT P14 TRUE COPY OF THE JUDGMENT DATED 07.04.2016 IN WP(C)12659/2016.
EXHIBIT P15 TRUE COPY OF THE NEWS PAPER REPORT DATED 06.01.2017 OF MATHRUBHUMI DAILY.
EXHIBIT P16 TRUE COPY OF THE ORDER BEARING NO.GO NO.350/2017/LSGD DATED 07.02.2017.
EXHIBIT P17 TRUE COPY OF THE RESOLUTION NO.C-1685/2014 DATED 06.03.2017.
EXHIBIT P18 TRUE COPY OF THE GO(RT) NO.989/2017/LSGD DATED 30.03.2017
EXHIBIT P19 TRUE COPY OF THE REPRESENTATION DATED 17.05.2017 FILED BY THE 1ST PETITIONER BEFORE THE 1ST RESPONDENT.
EXHIBIT P20 TRUE COPY OF THE GO(RT) NO.1689/2017/LSGD DATED 23.05.2017.
EXHIBIT P21 TRUE COPY OF THE REPRESENTATION DATED 20.07.2017 FILED BY THE 1ST PETITIONER.
EXHIBIT P22 TRUE COPY OF THE LETTER NO.C-1685/2014 DATED 25.07.2016(sic 25.07.2017)
EXHIBIT P23 TRUE COPY OF THE PETITIONER PREFERRED A DETAILED REPLY DATED 31.07.2017 TO EXT.P22, POINTING OUT THE ARBITRARINESS AND ILLEGALITIES EXHIBITED BY THE 3RD RESPONDENT.
EXHIBIT P24 TRUE COPY OF THE RELEVANT EXTRACTS OF GOVERNMENT ORDER GO(MS)NO.17/2001/PLANNING DATED 18.06.2001
RESPONDENTS' EXHIBITS:
ANNEXURE R3(A) COPY OF THE LETTER DTD 02.03.2018 OF R3
ANNEXURE R3(B) COPY OF THE LETTER DTD 07.03.2018 OF R3
EXHIBIT R3(A) COPY OF THE AGREEMENT DATED 31.03.2001
EXHIBIT R3(B) COPY OF THE LETTER TO THE GOVT DTD 07.03.2018 BY R3
EXHIBIT R3(C) COPY OF THE GOVT ORDER NO.768/2015/LSGD DATED 17/03/2015
EXHIBIT R3(D) COPY OF THE MINUTES OF R3 COMMITTEE ON 13/02/2017 WP(C).No.19568 OF 2016(U)
EXHIBIT RE(E) COPY OF THE LETTER DATED 23.05.2017
EXHIBIT R3(F) COPY OF THE DECISION DT 07.06.2017 OF THE R3 PANCHAYATH COMMITTEE
EXHIBIT R3(G) COPY OF THE RECEIPT DATED 07.06.2017 ISSUED BY THE 1ST PETITIONER ON RECEIPT OF RS.9,66,344/-
//TRUE COPY// PA TO JUDGE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!