Citation : 2021 Latest Caselaw 13139 Ker
Judgement Date : 23 June, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
WEDNESDAY, THE 23RD DAY OF JUNE 2021/2ND ASHADHA, 1943
WP(C) NO. 399 OF 2021
PETITIONER:
M.ALIYARUKUTTY, M.S.HOUSE,
VAKKANAD P.O., KAREEPRA,
KOLLAM DISTRICT.
BY ADVS.
K.P.SATHEESAN (SR.)
SRI.P.MOHANDAS (ERNAKULAM)
SRI.K.SUDHINKUMAR
SRI.S.K.ADHITHYAN
SRI.SABU PULLAN
SRI.GOKUL D. SUDHAKARAN
RESPONDENTS:
1 THE DIRECTOR OF MINING AND GEOLOGY,
OFFICE OF THE DIRECTOR OF MINING
AND GEOLOGY, KESAVADASAPURAM,
PATTOM P.O., THIRUVANANTHAPURAM-695004.
2 THE GEOLOGIST,
MINING AND GEOLOGY DEPARTMENT,
DISTRICT OFFICE, KOLLAM-691013.
3 THE DISTRICT COLLECTOR,
CIVIL STATION, KOLLAM-691013.
BY GOVERNMENT PLEADER SRI.MANU RAJ
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
23.06.2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
WP(C) No.399/2021
:2 :
JUDGMENT
~~~~~~~~~
Dated this the 23rd day of June, 2021
The petitioner seeks to direct the 2 nd respondent to
forward Ext.P8 application to the 1 st respondent as
expeditiously as possible and to direct the 1 st respondent to
take a decision on Ext.P8 application as per the Rules on
19.02.2019, within a time limit.
2. The petitioner would state that he along with four
others entered into a partnership to conduct business in metal
crusher unit, manufacturing of building materials, etc. The
partnership agreement was entered into on 17.08.2007. The
Firm satisfied all the eligibility conditions required for starting a
quarry. A quarrying permit was issued on 03.04.2019 which
was valid till 31.03.2020.
3. The petitioner submitted application for quarrying
lease on 19.02.2019. There was delay in processing the said WP(C) No.399/2021
application. At the directions of the 1st respondent, the
petitioner cured defects in the application and an application
was submitted afresh. The contention of the petitioner is that
the 2nd respondent-Geologist is not forwarding the application
stating that the petitioner has to comply with the distance rule
of 200 m., as ordered by the National Green Tribunal. The
petitioner therefore seeks to direct the 2 nd respondent to
forward Ext.P8 application to the 1st respondent.
4. Heard the learned counsel for the petitioner and the
learned Government Pleader representing the respondents.
5. Ext.P3 would show that the petitioner was granted a
quarrying permit on 03.04.2019 which was valid up to
31.03.2020. The petitioner as per Ext.P4 had applied for
renewal of the quarrying lease even before the said expiry
date. The petitioner would submit that an accident had
occurred in certain survey numbers and therefore the 2 nd
respondent required the petitioner to give an application
excluding those survey numbers, for renewal of the quarrying
permit. The petitioner wants to consider his renewal WP(C) No.399/2021
application as a continuation of issuance of the original
quarrying permit.
6. Heard the learned counsel for the petitioner and the
learned Government Pleader representing the respondents.
7. It is evident that the petitioner has submitted Ext.P8
application for grant of quarrying lease under Form-B of the
Kerala Minor Mineral Concession Rules. The respondents are
competent to consider Ext.P8 application and also to decide
whether Ext.P8 application should be treated as one in
continuation of the earlier quarrying lease granted. As the
application is in respect of the same land excluding certain
survey numbers, this Court is of the opinion that this should be
considered by the respondents at the first instance.
In the circumstances of the case, the writ petition is
disposed of directing the 1st respondent to consider Ext.P8
application submitted by the petitioner for grant of quarrying
lease under the Kerala Minor Mineral Concession Rules. The
petitioner is at liberty to supply any more documents and
certificates to the 2nd respondent if found required. The 1 st WP(C) No.399/2021
respondent shall consider Ext.P8 application and take a final
decision thereon within a further period of four weeks.
Sd/-
N. NAGARESH, JUDGE
aks/24.06.2021 WP(C) No.399/2021
APPENDIX OF WP(C) 399/2021
PETITIONER'S EXHIBITS
EXHIBIT P1 TRUE COPY OF THE AMENDED DEED OF PARTNERSHIP MADE ON 26.7.2018.
EXHIBIT P2 TRUE COPY OF THE ENVIRONMENTAL CLEARANCE CERTIFICATE DATED 19.6.2018 ISSUED BY THE DISTRICT ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, KOLLAM.
EXHIBIT P3 TRUE COPY OF THE QUARRYING PERMIT ISSUED BY THE 2ND RESPONDENT AS NO.2/2019-
20/MM/GBS/STP/DQQ/S2/1040/19 DATED 3.4.2019.
EXHIBIT P4 TRUE COPY OF THE APPLICATION DATED 19.2.2019 FILED BY THE PETITIONER FOR QUARRYING PERMIT FROM 1.4.2020 (WITHOUT DOCUMENTS).
EXHIBIT P5 TRUE COPY OF THE NO OBJECTION CERTIFICATE ISSUED BY THE 3RD RESPONDENT DATED 15.11.2018.
EXHIBIT P6 TRUE COPY OF THE OBJECTION RAISED BY THE 1ST RESPONDENT TO THE 2ND RESPONDENT DATED 25.5.2020.
EXHIBIT P7 TRUE COPY OF THE LETTER GIVEN BY THE 1ST RESPONDENT TO THE 2ND RESPONDENT WITH COPY TO THE PETITIONER DATED 9.10.2020 (WRONGLY WRITTEN AS 9.10.2019).
EXHIBIT P8 TRUE COPY OF THE APPLICATION SUBMITTED BY THE PETITIONER BEFORE THE 1ST RESPONDENT DATED 12.11.2020 (WITHOUT DOCUMENTS).
ncd
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!