Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

P.George William vs Corporation Of Cochin
2021 Latest Caselaw 12864 Ker

Citation : 2021 Latest Caselaw 12864 Ker
Judgement Date : 11 June, 2021

Kerala High Court
P.George William vs Corporation Of Cochin on 11 June, 2021
         IN THE HIGH COURT OF KERALA AT ERNAKULAM
                          PRESENT
        THE HONOURABLE MR. JUSTICE P.B.SURESH KUMAR
  FRIDAY, THE 11TH DAY OF JUNE 2021 / 21ST JYAISHTA, 1943
                  WP(C) NO. 22843 OF 2020
PETITIONER/S:

         P.GEORGE WILLIAM,
         ADVOCATE, HOUSE NO.73/2039, S.R.M. ROAD, PACHALAM
         P.O., ERNAKULAM 682012
         BY ADVS.
         PHILIP T.VARGHESE
         SRI.THOMAS T.VARGHESE
         SMT.ACHU SUBHA ABRAHAM
         SMT.V.T.LITHA
         SMT.K.R.MONISHA
         SMT.SHRUTHI SARA JACOB


RESPONDENT/S:

    1    CORPORATION OF COCHIN
         REP.BY ITS SECRETARY, CORPORATION OFFICE, PARK
         AVENUE, ERNAKULAM 682 011
    2    THE SUPERINTENDING ENGINEER
         CORPORATION OF COCHIN, CORPORATION OFFICE, PARK
         AVENUE, ERNAKULAM 682 011
    3    THE EXECUTIVE ENGINEER
         CORPORATION OF COCHIN, CORPORATION OFFICE, PARK
         AVENUE, ERNAKULAM 682 011
    4    K.S.BIJILI
         CONTRACTOR, CORPORATION OF COCHIN, CORPORATION
         OFFICE, PARK AVENUE, ERNAKULAM 682 011
         BY ADVS.
         SRI.E.D.GEORGE
         SRI.MANSOOR.B.H.
         SHRI.K.JANARDHANA SHENOY, SC, KOCHI MUNICIPAL
         CORPORATION


THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
11.06.2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
 W.P.(C) No.22843 OF 2020

                                    2




                      P.B.SURESH KUMAR, J.
               --------------------------------------------
                   W.P.(C) No.22843 of 2020
              -----------------------------------------------
            Dated this the 11th day of June 2021.


                           JUDGMENT

Petitioner is a practising lawyer. He is residing in a

house situated on a plot of land abutting Sivarama Menon

road, within the limits of Kochi Corporation (the Corporation).

The stretch of the road in front of the house of the petitioner

was in a dilapidated condition and the Corporation, therefore,

decided to restore the road adopting Bituminous Macadam and

Bituminous Concrete method and awarded the work of the

same to a Contractor, the fourth respondent. Ext.P1 is the

estimate of the work and Ext.P2 is the schedule of the work

appended to the agreement entered into by the Corporation

with the fourth respondent. It is stated by the petitioner that

the level of the road had raised by about 3 feet during the last W.P.(C) No.22843 OF 2020

20 years as restoration works were earlier carried out on the

road without scarifying the then existing bituminous road

surface. It is also stated by the petitioner that on account of

the said reason, there has been water logging in the area, for

the existing drainage system became ineffective on account of

the level difference between the surface of the road and the

surface of the drainage. In the agreement entered into by the

Corporation with the fourth respondent, there was however a

provision to the effect that the existing bituminous road

surface to a depth of 50 mm (5 cm) needs to be scarified and

removed by mechanical means. It is the case of the petitioner

that the aforesaid part of the work is an integral part of the

restoration work of the road without which the restored road

will not last long. It is alleged by the petitioner in the writ

petition that though the agreement entered into by the

Corporation with the fourth respondent makes it obligatory for

the fourth respondent to scarify and remove the existing

bituminous surface of the road, the fourth respondent is

attempting to complete the work without scarifying and W.P.(C) No.22843 OF 2020

removing the existing bituminous surface. It is also alleged by

the petitioner in the writ petition that if the work is carried out

in the aforesaid fashion, the petitioner may not be able to take

out his car to the road from his residential plot. The relief

sought by the petitioner in the writ petition in the

circumstances, was for a direction to the Corporation and its

officials to ensure that the restoration work of the road is

proceeded and completed only after removing the existing

bituminous road surface and to ensure that the level of the

existing road is not increased by the restoration work.

2. When the writ petition came up for admission

on 23.10.2020, this court passed an interim order directing the

Corporation and its officials to ensure that the work of the

road is carried out by the fourth respondent only in accordance

with the terms of the contract.

3. A counter affidavit was filed on behalf of the

Corporation and its officials stating, among others, that it was

difficult to scarify the existing bituminous surface of the road in

terms of the agreement; that when the said part of the work W.P.(C) No.22843 OF 2020

was attempted, the bituminous surface of the road along with

metal in a compact form upto 10 cm depth detached from the

ground surface of the road, resulting in dilapidation of the

basement of the road and that as it was apprehended that the

entire road basement will be lost, if the said work is continued,

60% of the scarified material was rolled in the road itself using

road roller making a strong sub-base for a long lasting road. It

is also stated by the Corporation in the counter affidavit that

the scarification process provided for in the agreement was not

intended to reduce the height of the road and that it was only

intended for the proper binding of the material over the

existing road surface. The fact that the level of the road would

be raised once the work is completed is admitted by the

Corporation in the counter affidavit and it was suggested

therein that if the petitioner is unable to take out his car from

the premises of his house on account of the said reason, he

has to construct a ramp for the said purpose.

4. The petitioner has filed a reply to the counter

affidavit filed by the Corporation stating, among others, that W.P.(C) No.22843 OF 2020

the deviation of the work carried out as admitted by the

Corporation in the counter affidavit is unscientific and

unauthorised. It is also stated by the petitioner in the reply

affidavit that 100% of the material scarified from the surface

of the road were rolled over the road using road roller and the

averment to the contrary made in the counter affidavit is

incorrect.

5. On 19.01.2021, the petitioner filed I.A. No.3 of

2021 seeking leave to amend the writ petition to incorporate a

few additional facts, grounds and prayers. The said

interlocutory application was allowed, and in terms of the order

passed in the interlocutory application, the petitioner has filed

an amended writ petition. In the amended writ petition, it is

alleged by the petitioner, among others, that the writ petition

was partly heard through video conferencing on 14.01.2021

and adjourned to 15.01.2021 due to connectivity issues and

that the work which was stopped after the interim order was

resumed and completed by the fourth respondent as directed

by the officials of the Corporation with police aid in between, W.P.(C) No.22843 OF 2020

during the night hours of 14.01.2021, violating the interim

order passed by this Court. It is also alleged by the petitioner in

the amended writ petition that on completion of the work in

the aforesaid manner, the level of the road now stands

increased by 2 feet at the entrance of the house of the

petitioner, making vehicular entry to the plot of the petitioner

and vehicular exit therefrom impossible. The additional prayers

sought by the petitioner in the writ petition are for a direction

to the Corporation and its officials to re-do the work of the road

in accordance with the terms of the contract, after ensuring

that the level of the road is not increased and for a direction to

the Corporation and its officials to take steps forthwith to

ensure smooth and free ingress and egress of men and

vehicles to and from the plot of the petitioner.

6. Earlier, the petitioner filed I.A. No.2 of 2021 for

appointing an expert engineer to ascertain and report a few

facts. On 28.01.2021, this court allowed the said application

and directed the Superintending Engineer, Roads Central

Circle, PWD, Aluva to ascertain and report the facts sought to W.P.(C) No.22843 OF 2020

be ascertained in terms of the application, after conducting a

local inspection.

7. Pursuant to the said interim order, the expert

appointed by this Court conducted a local inspection on

05.02.2021 and filed a report stating the following:

1. As per the approved initial level proposal 18cm thick wetmix macadam, 5cm thick Bituminous Mecadam & 3cm Bitumen concrete are proposed over the existing road. So the total thickness of these layers as per the approved initial level proposal is 26cm. But in the final level, which is taking after completion of the work, the thickness of these layers is seen reduced to 14cm. Also the item such as providing & laying of hot applied thermoplastic compound and reflective road studs were not seen executed.

2. On verifying the final levels, the height of materials laid over the old surface is 14cm.

3. The height difference from the restored road surface and top of the drainage is varying from the place to place. At three Random points tape measurements were taken in which the height difference is 19cm, 22cm, 16cm. In some points the top of the road surface is same as the top of the drainage cover slab.

4. The height at which the road surface now stands at the entrance of the petitioner's house from the top of the drainage slab in front of his gate is 37cm.

5. Safe access for men and vehicles to the petitioner's property is not possible from the restored road.

6. Water lagging will not be caused in the area due to the increase in the height of the road. The corporation has W.P.(C) No.22843 OF 2020

already prepared a revised estimate incorporating the drainage work and there is out let for draining off the water flowing through drains.

7. No other matters requested by the petitioner.

8. On 5.2.2021, the petitioner filed Contempt

Case No.314 of 2021 alleging that the work was executed

during the pendency of the writ petition flouting the interim

order passed on 23.10.2020. The writ petition was heard

thereafter on 22.3.2021 along with the Contempt Case.

Thereupon, on 24.03.2021, the third respondent has filed a

statement in the matter stating, among others, that the levels

of the road were taken before and after the work and it is

revealed that the level of the road was raised only between

14.5 cms and 18 cms. It is also stated in the said statement

that the level of the road in front of the house of the petitioner

before the work was 22 cms above the level of the plot and the

same was increased only by 14.5 cms after the work. It is also

stated that the Corporation is following Delhi Schedule of Rates

(the DSR) for execution of various works and in terms of the

DSR specification 16.11.2, "scarifying operation will also W.P.(C) No.22843 OF 2020

include consolidation with road roller the aggregate received

from scarifying, although this aggregate will be consolidated

along with aggregate of new wearing course to be paid

separately".

9. Heard the learned counsel for the petitioner as

also the learned Standing Counsel for the Corporation.

10. As noted, the writ petition is instituted seeking

directions to the Corporation and its officials to ensure that the

restoration work of the road is proceeded and completed only

after removing the existing bituminous road surface and to

ensure that the level of the existing road is not increased by

the restoration work. The specific case pleaded by the

petitioner in the writ petition is that the level of the road has

raised by about 3 feet during the last 20 years as the

restoration works were earlier carried out on the road without

scarifying the then existing bituminous road surface; that

there has been water logging in the area on account of the

said reason, for the existing drainage system became

ineffective on account of the level difference between the W.P.(C) No.22843 OF 2020

surface of the road and the surface of the drainage; that it is

provided in the agreement therefore, that the existing

bituminous road surface to a depth of 50 mm needs to be

scarified and removed by mechanical means before making

the fresh bituminous overlay; that the aforesaid part of the

work is an integral part of the restoration work of the road

without which the restored road will not last long; that the

fourth respondent is attempting to complete the work without

scarifying and removing the existing bituminous surface of the

road and that if the work is carried out in the aforesaid fashion,

the petitioner may not be able to take out his car from his

residential plot to the road. The essence of the grievance of the

petitioner in the circumstances is concerning the conduct of

the Corporation in restoring the road in such a fashion as to

raise its level.

11. There is nothing on record to indicate as to

whether the Corporation has prescribed any specifications or

standards or at least guidelines for construction and

maintenance of city roads. The Corporation does not dispute W.P.(C) No.22843 OF 2020

the fact that the level of the road would be raised every time

when road is restored, maintained or resurfaced. The said

course may not be scientific and may affect the interests of

persons residing on either side of the road adversely. But, in

the absence of any obligation for the Corporation in terms of

any statute or guidelines to ensure that the level of road is

maintained when the restoration is carried on, this Court may

not be justified, in exercise of the discretionary jurisdiction

under Article 226 of the Constitution, in granting the relief

sought for by petitioner, especially when the writ petition was

instituted much after the commencement of the work. The

prayer of the petitioner in the amended writ petition is for a

direction to the Corporation re-do the work. As noted, the said

relief is sought by the petitioner on the basis of the allegation

that the work has been executed flouting the interim order

passed in the matter. Even if it is found that the work has been

executed flouting the interim order passed by this Court, the

petitioner is not entitled to the relief sought for in the

amended writ petition merely on account of the said reason, W.P.(C) No.22843 OF 2020

since it is found that the petitioner is not entitled to the relief

originally sought in the writ petition. Of course, if the work is

not executed in accordance with the terms of the agreement

and if it is demonstrated that damage has been caused on

account of the same to the people residing on either side of

the road, the petitioner is certainly entitled to appropriate relief

in the matter.

12. I shall, therefore, consider the question as to

whether the case of the petitioner that the work has been

executed by the Corporation otherwise than in accordance with

the terms of the agreement, violating the specific interim order

passed by this Court that the work shall be executed only in

accordance with the terms of the agreement. As noted, the

agreement entered into by the Corporation with the fourth

respondent provides for scarifying the existing bituminous road

surface to a depth of 50 mm. and disposal of the scarified

material within all lifts and lead upto 1000 meters by

mechanical means. The aforesaid part of the work is included

in the schedule accompanying the agreement under serial W.P.(C) No.22843 OF 2020

No.1.005. In the counter affidavit filed by the Corporation on

18.11.2020, it is recited thus :

"It is most respectfully submitted that the above road was constructed by tarring lastly before 7 years. During that time considering heavy vehicular traffic the bitumen surface was done properly and as result of the same, the bitumen surface was thoroughly became compact with the metal used for basement of the road. Due to the strong construction of the road, it has difficult to remove the tar surface alone as per agreement scarifying of existing tar surface upto 5 cm. is only intended in the estimate. Even though it was tried in many places, the tar along with metal in compact form upto 10 cm. depth detached from the ground earth of the road resulting on dilapidation of basement of road. If such activity is continued through the entire road, the basement will be lost resulting the weakness of the existing road. Therefore, about the 60% of scarified material was rolled using roller to make a strong sub

base for a long lasting road."

The extracted averments in the counter affidavit would reveal

that as it was found that the work cannot be executed as

provided for in the agreement, it was decided to execute the

work otherwise than in accordance with the agreement. It is

seen that while the Corporation was proceeding on that basis, W.P.(C) No.22843 OF 2020

the petitioner approached this court and obtained the interim

order dated 23.10.2020, directing the Corporation and its

officials to ensure that the work is carried out only in

accordance with the terms of the agreement. The said interim

order is one passed after hearing the Standing Counsel for the

Corporation. The materials on record indicate that the work

was not continued after the interim order for some time.

Although the Corporation has filed a counter affidavit justifying

their conduct in proceeding to execute the work otherwise than

in accordance with the terms of the contract, this Court did not

permit the Corporation to do so by vacating or modifying the

interim order dated 23.10.2020. As stated by the petitioner,

the writ petition was later taken up for final hearing on

14.1.2021 and directed to be listed on the succeeding day

before the physical court. The case set out by the petitioner in

the amended writ petition is that the work which was stopped

in the light of the interim order of this court was resumed at

about 8 p.m. on 14.1.2021 and completed by about 7 a.m. on

15.1.2021. The relevant pleadings of the petitioner in the W.P.(C) No.22843 OF 2020

amended writ petition read thus :

"11. This writ petition was listed for hearing on 13.1.2021 but it could not be taken up on that day due to paucity of time. On 14.1.2021 this writ petition was listed and the counsel for the petitioner was heard in part. However due to connectivity problems during the hearing through video conferencing, this Hon'ble Court posted the writ petition to 15.1.2021 for physical hearing in the court.

12. At about 8 pm on 14.1.2021 the petitioner found that machinery for the road work had been brought to the site and that workers had arrived. Paver machine, tractor with air compressor, road roller etc. had been brought to the site. Ms.Soumya, Assistant Engineer and Mr.Santhosh, Overseer of the 1st respondent arrived at the site along with the newly elected Corporation Councilor Ms.Mini Vivera and the former Corporation Councilor Mr.Albert Ambalathingal. Some local political workers were also with them. The petitioner went to them and enquired how the road work was proposed to be done by them. He was told that they are proceeding with the work without removing the scarified materials and the metal laid over it. The petitioner told them that the road work should be proceeded only in accordance with the interim order passed by this Hon'ble Court on 23.10.2020. Ms.Soumya, Assistant Engineer replied that she has been directed by her superiors to go ahead with the work without removing the scarified material or the layer of metal put over it. When the petitioner showed the order, she said that she is aware of the interim order passed by this Hon'ble Court but she is not concerned with that order, but she has to execute the direction given to her by her superiors.

13. The petitioner called Police Control Room (1090) from W.P.(C) No.22843 OF 2020

his mobile number 9847166783 and sought for their assistance to prevent violation of the interim order passed in this writ petition. This was by about 8.30 pm. The Police Control Room informed the petitioner that the police party would arrive at the spot shortly. The counsel for the petitioner phoned the Standing Counsel for the 1st respondent at about 8.40 pm and apprised him about the situation and requested him to inform the Corporation officials that the writ petition is posted for hearing the next day and no work in violation of the interim order of this Hon'ble Court should be done in haste. The Standing Counsel for the 1st respondent later informed the counsel for the petitioner that Corporation officials were not responding to his calls.

14. When the Police party arrived the petitioner apprised them of the situation and requested them to ensure that work in violation of the interim order of this court is not proceeded with at least till the writ petition is heard by this Hon'ble Court the next day. The police party told the petitioner that they have been directed to provide protection to the contractor's workmen and the Corporation officials and they have come to the site for that purpose. The police party told the petitioner that they had been instructed to remove the obstructors and ensure that the road work is done that night itself. By this time a large number of residents of the locality had gathered objecting to the proposed continuation of the work in an unscientific manner by which the height of the road would be considerably raised. However due to adamant stand of the Corporation officials and the intimidating stand taken up by the police party the petitioner and the people of the locality had no option but to helplessly watch the road work being proceeded with in stark violation of the interim order passed by the Hon'ble Court and the terms of the contract. By doing such work that night, knowing fully well W.P.(C) No.22843 OF 2020

that this writ petition is to be heard the next day, the respondents have attempted to overreach the due process of law and to render meaningless the proceedings in this writ petition. They have acted with malafides and have shown utter disregard to the rule of law.

15. The road work continued till about 7.00 am on 15.1.2021. When this writ petition was taken up on 15.1.2021 also the counsel for the petitioner apprised this Hon'ble Court about what had transpired on the night of 14.1.2021. This Hon'ble Court posted the writ petition to 20.1.2021 so as to enable the petitioner to seek for amendment of the writ petition incorporating the subsequent events. Shockingly, the road work continued on the hight of 15.1.2021 till about 7 am the next day. The height of the road stands raised by over 2 feet at the entrance of the petitioner's house. The road surface appears like a cliff from the petitioner's property. The road work done is in such a manner that no vehicular access from the petitioner's property to SRM Road is possible. The height of the road and the nature of its work is such that the people cannot easily or safely step into the road from the petitioner's property. The road construction at the petitioner's entrance is purposefully done in a manner preventing the petitioner and his men from having proper access and vehicular access to SRM Road. From the night of 14.1.2021 it is impossible for the petitioner to take his vehicle out of his property due to the raised height of the road. The respondents have done the road work in such a manner preventing vehicular access to the petitioner's property deliberately so as to harass him and wreak vengeance on him for protesting against the unscientific performance of the road work deviating from the terms of the contract and for resorting to his legal remedy by filing this writ petition. The free movement of the petitioner and his family members to SRM W.P.(C) No.22843 OF 2020

Road has been obstructed due to the road work done now. Such a situation is faced by most of the property owners by the side of SRM Road and persons whose properties are situated on the bylanes starting from the SRM Road. True copies of the photographs showing the present condition of the road at the entrance of the petitioner's property is produced herewith and marked as Exhibit P7. True copies of the photographs showing the SRM Road at different points where bylanes from SRM Road begins are produced herewith and marked as Exhibit P8. It is submitted that respondents 2 to 4 have not come to the work site at any time when the road work was done. Such neglect shown by them in spite interim order being passed by this Hon'ble Court on 23.10.2020 is unjustifiable."

The averments in the amended writ petition as extracted

above stand un-controverted.

13. On a query from the court as to the

justification of the Corporation for completing the work

otherwise than in accordance with the interim order, that too,

when the matter was being argued, the explanation offered by

the Standing Counsel was that the completion of the work

cannot be said to be otherwise than in accordance with the

terms of the agreement since the Corporation has adopted the

specifications in the Delhi Schedule of Rates for execution of W.P.(C) No.22843 OF 2020

the work and in terms of the provisions therein, the deviation

of the work undertaken by the Corporation is permissible. I am

unable to accept this explanation. Clause 16.11.2 of the DSR

only clarifies that scarifying operation may include

consolidation with the road roller the aggregate received from

scarifying with the aggregate of new wearing course to be paid

separately also. In the case on hand, there is no such provision.

On the other hand, the specific provision in the agreement is

that the existing bituminous surface of the road is to be

scarified and removed and the rate provided for in the

agreement is for removing the scarified material for a distance

upto 1 kilometre. Further, the DSR is only a document

describing the rates for executing various civil works prepared

by the Central Public Works Department and the same does

not contain any specification and standard or guideline for

construction and maintenance of roads. As such, even if the

Corporation is following the DSR for effecting payments for the

works executed by it, the same does not confer any authority

on the Corporation to execute the work otherwise than in W.P.(C) No.22843 OF 2020

accordance with the agreement. In the aforesaid

circumstances, the case of the petitioner that the work has

been executed by the Corporation otherwise than in

accordance with the terms of the agreement, violating the

specific interim order passed by this Court, is only to be

accepted. Execution of a road work otherwise than in

accordance with the terms of the agreement resulting in

damage to the people residing on either side of the road

cannot be viewed lightly. Similarly, violation of an order passed

by the Court cannot also be viewed lightly. Needless to say,

the petitioner is entitled to an appropriate relief in this regard.

14. It is seen that raising the level of the road

while carrying out the restoration or maintenance or re-

surfacing work is not an advisable method to be adopted. If a

particular level is not maintained for every road or at least if it

is not ensured that the level of the road is not raised

considerably while carrying out the restoration or maintenance

or resurfacing work, the drains constructed on either side of

the road would be rendered purposeless after a few W.P.(C) No.22843 OF 2020

restoration, maintenance or resurfacing works and it would

become necessary for the owners of the buildings on either

side of the road either to modify or alter the buildings for using

the same for the purpose intended. It is common knowledge

that elsewhere in the world, a level is prescribed for every road

and it is ensured that the said level is not raised in any manner

when restoration or maintenance or re-surfacing work is

carried out. The provision made to this effect in the guidelines

for construction and maintenance of city roads by the Bruhat

Bengaluru Mahanagara Palike during the year 2009 reads

thus :

"On city roads frequent layers are added for renewal/strengthening periodically raising the road level every time, it is necessary to recycle the bituminous materials of the existing road surface. With this, the road level does not go on increasing endlessly and also the old materials are reused with minimum additions. This method is already being adopted in metropolitan cities-Delhi, Mumbai and Chennai."

Reverting to the facts, as far as the road in this case is

concerned, it is pointed out in the counter affidavit that the

road was earlier restored about seven years back. The specific W.P.(C) No.22843 OF 2020

averment of the petitioner in the writ petition that the level of

the road had raised by about 3 feet during the last 20 years is

not disputed by the Corporation in the counter affidavit filed in

the matter. The report filed by the expert appointed in the

matter also indicates that even the work which is the subject

matter of the writ petition was designed in such a fashion as to

raise the level of the road by 26 cms. The report filed by the

expert also indicates that the level difference between the road

and the plot of the petitioner is 37 cms. at the time of

inspection. As noted, the work has not been executed as

originally proposed. Had the work been executed as originally

proposed, the level difference between the road and the plot

of the petitioner would have been 50 cms. The expert has

stated categorically in his report that on account of the said

level difference, after the work, it is impossible for the

petitioner to have vehicular access to and from his residential

plot. It is common knowledge that the situation is not different

in the case of other roads within the Corporation. If the level of

the city roads are raised in this fashion while undertaking the W.P.(C) No.22843 OF 2020

restoration, maintenance or resurfacing works, I have no doubt

that the drains constructed on either side of the roads would

become purposeless and there will be waterlogging in the

properties on either side of the roads. It is seen that it is on

account of this reason that large number of buildings situated

on either side of the roads in the Corporation, the level of

which have been raised considerably on account of restoration

or maintenance or resurfacing works are modified and altered

in course of time and substantial number of buildings are now

being raised by engaging hydrolic jack lifting technology. This

is a sheer waste of resources, and for those who cannot afford

either to modify the building or lift the building, it is a

perennial hardship. This is certainly a matter to be considered

by the Corporation.

In the result, the writ petition is disposed of

directing the Corporation to constitute a committee of experts,

if necessary, with the concurrence of the Directorate of

Municipal Administration of the State Government within three

months to lay down specifications and standards for W.P.(C) No.22843 OF 2020

construction and maintenance of city roads, in the form of

guidelines. The said committee shall address the issue

discussed in paragraph 14 of the judgment also and submit a

report to the Corporation within three months thereafter. The

committee shall also examine in particular, the question

whether the course adopted by the Corporation in completing

the restoration work of the road referred to in the writ petition

is correct and shall suggest the remedial measures. Once the

guidelines are prescribed by the committee as directed, the

construction and maintenance of city roads shall be carried out

only in accordance with the said guidelines. Needless to say,

the Corporation shall also implement the remedial measures, if

any, suggested by the committee in relation to the road

referred to in the writ petition expeditiously.

Sd/-

P.B.SURESH KUMAR, JUDGE.


Mn
 W.P.(C) No.22843 OF 2020





                  APPENDIX OF WP(C) 22843/2020

PETITIONER EXHIBITS        :

EXHIBIT P1             TRUE COPY OF THE ESTIMATE OF
                       RESTORATION WORK BY BM AND BC TO SRM
                       ROAD (BALANCE), NKS ROAD AND TOLL GATE
                       ROAD PREPARED BY THE 1ST RESPONDENT
                       DATED NIL
EXHIBIT P2             TRUE COPY OF THE SCHEDULE OF THE
                       AGREEMENT EXECUTED BY RESPONDENTS 1
                       AND 2 WITH THE 4TH RESPONDENT DATED
                       NIL
EXHIBIT P3             TRUE COPY OF WORK ORDER ISSUED BY THE
                       2ND RESPONDENT ISO/MOE-5/1423/20 DATED
                       23.6.2020
EXHIBIT P4             TRUE COPY OF THE COMPLAINT SUBMITTED
                       BY THE PETITIONER AND OTHERS TO THE
                       1ST AND 2ND RESPONDENTS ON 22.10.2020
EXHIBIT P5             TRUE COPY OF THE PHOTOGRAPH SHOWING
                       THE SCARIFYING WORK OF THE EXISTING
                       BITUMINOUS ROAD SURFACE WORK BY THE
                       4TH RESPONDENT TAKEN ON 17.10.2020
EXHIBIT P6             TRUE COPY OF THE PHOTOGRAPHS OF THE
                       PARTIALLY RESTORED ROAD TAKEN ON
                       20.10.2020
EXHIBIT P7             TRUE COPIES OF THE PHOTOGRAPHS OF THE
                       PRESENT CONDITION OF THE ROAD AT THE
                       ENTRANCE OF THE PETITIONER'S PROPERTY
EXHIBIT P8             TRUE COPIES OF THE PHOTOGRAPHS SHOWING
                       SRM ROAD WHERE BYLANES FROM THE ROAD
                       BEGINS
EXHIBIT P9             TRUE COPY OF THE CAVEAT PETITION DATED
                       14.1.2021
EXHIBIT P9(a)          POSTAL COVER OF THE CAVEAT PETITION
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter