Citation : 2021 Latest Caselaw 12264 Ker
Judgement Date : 26 April, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
MONDAY, THE 26TH DAY OF APRIL 2021/6TH VAISAKHA, 1943
WP(C).No.7472 OF 2020(H)
PETITIONER:
MADHU, S/O.KITTUNNY, AGED 58 YEARS,
CHALAKKALAM, THATHAMANGALAM,
PALAKKADU DISTRICT.
BY ADVS.
SRI.C.S.MANILAL
SRI.S.NIDHEESH
RESPONDENTS:
1 THE STATE OF KERALA, REPRESENTED BY
THE SECRETARY TO GOVERNMENT,
WATER RESOURCE DEPARTMENT,
THIRUVANANTHAPURAM - 605 036.
2 THE CHIEF ENGINEER, PROJECT I,
IRRIGATION DEPARTMENT,
KOZHIKODE - 673 001.
3 SUPERINTENDING ENGINEER,
SIRUVANI PROJECT CIRCLE,
PALAKKADU - 678 002.
4 THE EXECUTIVE ENGINEER,
IRRIGATION DIVISION, CHITTOOR,
PALAKKADU - 678 002.
5 THE DEPUTY TAHASILDAR,
CHITTOOR TALUK,
PALAKKAD DISTRICT - 678 002.
BY SR.GOVERNMENT PLEADER SMT.DEEPA NARAYANAN
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 08.02.2021 AND THE COURT ON 26-04-2021 DELIVERED THE
FOLLOWING:
WP(C) No.7472/2020
:2 :
JUDGMENT
~~~~~~~~~
Dated this the 26th day of April, 2021
The petitioner, who is a Government Contractor,
has approached this Court seeking to quash Exts.P1 and P2
to P6 and to declare that revenue recovery proceedings
cannot be invoked in respect of tentative liability and inabilities
which are not quantified or adjudicated by the Civil Court or
other Adjudicating Authority and hence the recovery
proceedings are illegal and non-est.
2. The petitioner was selected for award of the work
"Widening the existing Veliavallampathy Canal from Ch:
8930m to 9210m". The probable amount of contract was
₹13,31,163/-. An agreement was executed on 18.05.2004.
The site was handed over to the petitioner on 31.12.2004.
The work had to be completed before 30.06.2005. The WP(C) No.7472/2020
respondents later extended the period up to 31.12.2005.
3. The petitioner states that the estimate was revised
at the instance of the Department to ₹18,89,475/- on
22.04.2005. According to the petitioner, the work could not be
completed due to non-supply of Departmental materials and
on account of denial of part bills. The petitioner completed
substantial work and raised a part bill for ₹12,50,075/-.
However, only ₹8,41,837/- was paid. An amount of
₹3,55,947/- is yet to be paid.
4. While so, one Mayilswami filed a complaint before
the Enquiry Commissioner and Special Judge, Thrissur. The
Enquiry Commissioner ordered a quick verification. In the
quick verification, the Vigilance found that the total volume of
the work done by the petitioner is ₹11,97,784/- and after
deducting the first part bill of ₹8,41,837.60, the balance
amount due is ₹3,55,947.20. The Vigilance recommended
termination of the contract at the risk and cost of the
petitioner. Thereupon, without issuing any notice, the contract
was cancelled as per Ext.P1 proceedings. WP(C) No.7472/2020
5. The petitioner states that the security amount of
₹1,00,000/- which was directed to be adjusted against another
work of the petitioner was later released on 28.04.2007.
Retention amount due to the petitioner was also released on
31.03.2006. The petitioner also remitted ₹26,665/- being the
amount quantified as the cost of cement.
6. The petitioner states that though the Department
attempted to re-tender the balance work twice, the work was
not carried out. As the work could not be carried out, the
actual risk and cost cannot be quantified in order to fix any
liability on the petitioner. Without quantifying the liability, the
Department issued a requisition to the revenue authority for
recovery and amount of ₹2,99,999/- from the petitioner.
Accordingly, Ext.P6 demand notice was issued under Section
7 of the Revenue Recovery Act. The petitioner challenges
Exts.P1 and P6.
7. The learned counsel for the petitioner, relying on
the judgment of the Apex Court in Union of India v. Raman
Iron Foundry [AIR 1974 SC 1265], argued that a claim for WP(C) No.7472/2020
liquidated damages does not give rise to a debt until the
liability is adjudicated and damages assessed by a decree or
order of a court or other Adjudicating Authority. Relying on
the judgment of this Court in Abraham Sebastian v. State of
Kerala [2002 (3) KLT839], the learned counsel argued that
actual loss which the Government had to suffer in a
terminated contract can be assessed only after the completion
of the work and till then, no revenue recovery proceedings can
be initiated against the appellant.
8. As regards realisation of 30% of the cost provided
under the PWD Manual, the learned counsel for the petitioner
argued that the said 30% amount can be realised only from
EMD/security, bill amount/retention amount, any dues from
the Department to the contractor or bank guarantee/
performance guarantee or by filing a civil suit. Revenue
recovery proceedings cannot be resorted to for recovering the
said 30% of the cost.
9. The 4th respondent-Executive Engineer contested
the case filing counter affidavit. According to the 4 th WP(C) No.7472/2020
respondent, the Government is entitled to recover 30% of the
cost through revenue recovery proceedings. In the additional
counter affidavit filed by the respondents, it has been stated
that as per the PWD Manual, an amount equal to 30% of the
cost of the remaining works at the agreed rates of terminated
contract has to be paid by the petitioner. In the petitioner's
case, 30% of the cost of remaining works was calculated by
the Department as per law based on original agreement and
the work schedule. In view of the provisions contained in the
PWD Manual, there is no need to wait till the work is arranged
alternatively through another contractor, for realising the said
30% amount.
10. Heard learned counsel for the petitioner and
learned Government Pleader representing the respondents.
11. The petitioner is challenging revenue recovery
proceedings initiated by the respondents for recovery of 30%
of the cost of the remaining work at agreed rates, on two
grounds. Firstly, the amount towards liquidated damages can
be recovered from the petitioner only after adjudication of the WP(C) No.7472/2020
amount by a civil court or any other competent authority.
12. Secondly, even under the PWD Manual, recovery
of 30% of the cost of the remaining work can be realised only
from EMD/security, bill amount/retention money, any dues
from Department to the contractor, bank guarantee/
performance guarantee or by filing civil suit against the
contractor. Revenue recovery proceedings for recovery of the
30% of the cost of the remaining work is not contemplated
under the PWD Manual.
13. It is true that a claim for liquidated damages does
not give rise to a debt until the liability is adjudicated and
damages assessed by a decree or order of a civil court or any
other Adjudicating Authority. When there is a breach of
contract, the party who commits the breach does not co
instanti incur any pecuniary obligation, nor does the party
complaining of the breach become entitled to a debt due from
the other party. However, when there is an agreement or
contract enabling one of the parties to recover a pre-decided
sum, such party would be entitled to realise the amount in WP(C) No.7472/2020
accordance with the law without resorting to any proceedings
for adjudication of the said amount.
14. In the case of the petitioner, the petitioner has
executed contract accepting the provisions contained in the
PWD Manual. Clause 2116.2.1 of the PWD Manual reads as
follows:
"2116.2.1 Realisation of loss on account termination An amount equal to 30% of the cost of the remaining works at agreed rates of the terminated contract shall be recovered from the defaulted contractor towards the risk and cost. The contractor shall be directed to remit the risk and cost amount within three months. There is no need to wait till the work is arranged alternatively through another contractor and the total loss sustainable due to the default of the original contractor is assessed. Such loss, if any, shall be realised after completion of the work. If he falls to remit the amount within this periods following steps can be adopted for realisation of loss. The amount can be realised from the following:
2. EMD/Security
3. Bill amount/retention if any due to the contract.
4. Any dues from department to the contract.
5. Bank Guarantee/Performance Guarantee or By filing civil suit against the contractor."
15. As there is a specific agreement between the
petitioner and the respondents in this regard, the respondents
will be entitled to recover 30% of the cost of the remaining WP(C) No.7472/2020
works at the agreed rates from the petitioner. The judgment
of the Apex Court in Raman Iron Foundry (supra) or the
judgment of this Court in Abraham Sebastian (supra) did not
deal with Clause 2116.2.1 of the PWD Manual and therefore
those judgments would not be of any help to the petitioner.
16. The further argument of the petitioner is that the
said 30% of the cost of the remaining works can be realised
by the respondents only from EMD/security, Bill amount/
retention amount, any dues from the department to the
petitioner, bank guarantee/performance guarantee or by filing
civil suit. The argument is that as the said Clause of the PWD
Manual does not specify revenue recovery under the Revenue
Recovery Act as one of the mode of realising the amount, the
respondents cannot resort to revenue recovery.
17. Clause 2116.2.1 of the PWD Manual states that "an
amount equal to 30% of the cost of the remaining works at
agreed rates of the terminated contract shall be recovered
from the defaulted contractor towards the risk and cost".
Therefore, as per the PWD Manual and the contract entered WP(C) No.7472/2020
into by the petitioner with the respondents, the respondents
can legally claim 30% amount on termination of petitioner's
contract. The provisions for realising the amount from
EMD/security etc. mentioned in Clause 2116.2.1 of the PWD
Manual can be treated only as explanatory, and not
exhaustive. The Government can very well resort to revenue
recovery as the 30% of the cost of the remaining works at
agreed rates of a terminated contract, is a sum due to the
Government.
For the above said reasons, this Court finds no
merit in the claim made by the petitioner in the writ petition.
The writ petition lacks merit and it is accordingly dismissed.
Sd/-
N. NAGARESH, JUDGE
aks/16.04.2021 WP(C) No.7472/2020
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE PROCEEDINGS OF THE 4TH RESPONDENT DATED 30/5/2014.
EXHIBIT P2 TRUE COPY OF THE LETTER DATED 20/12/2016 SENT BY THE 4TH RESPONDENT TO THE ADDITIONAL GOVERNMENT PLEADER PALAKKADU.
EXHIBIT P3 TRUE COPY OF THE RE-TENDER DATED 23/11/2017 ISSUED BY 3RD RESPONDENT.
EXHIBIT P4 TRUE COPY OF THE RE-TENDER DATED 12/12/2017 ISSUED BY 3RD RESPONDENT.
EXHIBIT P5 TRUE COPY OF THE SELECTION NOTICE DATED 16/5/2017 ISSUED TO M.M.JOHN.
EXHIBIT P6 TRUE COPY OF THE REVENUE RECOVERY NOTICE DATED 10/1/2020 ISSUED BY 5TH RESPONDENT.
RESPONDENTS' EXHIBITS:
ANNEXURE R1(a) TRUE COPY OF THE LETTER DATED 04.12.2015 ISSUED BY THE EECUTIVE ENGINEER, IRRIGATION DIVISION, CHITTOOR TO THE PETITIONER ANNEXURE R1(b) TRUE COPY REPORT OF THE ASSISTANT EXECUTIVE ENGINEER, KOZHINJAMPARA RBC SUB DIVISION DATED 05.12.2015 ASSESSING THE LIABILITY OF THE BALANCE WORK.
ANNEXURE R1(c) TRUE COPY OF THE RELEVANT PORTION OF PWD MANUAL.
ncd
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!