Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The State Project Director vs Kbr Infratech Limited
2025 Latest Caselaw 8330 Kant

Citation : 2025 Latest Caselaw 8330 Kant
Judgement Date : 12 September, 2025

Karnataka High Court

The State Project Director vs Kbr Infratech Limited on 12 September, 2025

                                                -1-
                                                       NC: 2025:KHC:36371-DB
                                                      COMAP No. 538 of 2024


                   HC-KAR



                     IN THE HIGH COURT OF KARNATAKA AT BENGALURU
                       DATED THIS THE 12TH DAY OF SEPTEMBER, 2025
                                          PRESENT
                          THE HON'BLE MRS. JUSTICE ANU SIVARAMAN
                                            AND
                            THE HON'BLE MR. JUSTICE RAJESH RAI K
                            COMMERCIAL APPEAL NO. 538 OF 2024
                   BETWEEN:

                   THE STATE PROJECT DIRECTOR
                   RASHTRIYA MADHYAMIKA SHIKSHANA ABHIYANA
                   NEW ANNEX BUILDING
                   K.R. CIRCLE, BENGALURU-560 001.
                                                                ...APPELLANT
                   (BY SMT. SHWETHA KRISHNAPPA, AGA)

                   AND:

                   KBR INFRATECH LIMITED
                   A REGISTERED COMPANY
                   HAVING ITS REGISTERED OFFICE AT:
                   No.1, 1ST FLOOR, 8TH CROSS
                   TATA NAGAR, BALAJI LAYOUT
Digitally signed   RMV EXTENSION, 2ND STAGE POST
by
CHANNEGOWDA        BENGALURU-560 094
PREMA              REPRESENTED BY ITS
Location: High
Court of           MANAGING DIRECTOR
Karnataka          SRI. K. BABU RAJU
                   S/O SRI. K. RAMAKRISHNAMA RAJU
                   AGED ABOUT 56 YEARS.
                                                              ...RESPONDENT
                   (BY SMT. VANI H, ADVOCATE)

                        THIS COMAP IS FILED UNDER SECTION 13(1-A) OF THE
                   COMMERCIAL COURTS ACT, 2015 READ WITH SECTION
                   37(1)(c) OF THE ARBITRATION AND CONCILIATION ACT, 1996,
                   PRAYING TO CALL FOR RECORDS IN COM.A.P. 26/2024, FROM
                            -2-
                                    NC: 2025:KHC:36371-DB
                                   COMAP No. 538 of 2024


HC-KAR



THE HONBLE LXXXV ADDITIONAL CITY CIVIL AND SESSIONS
JUDGE AT BENGALURU AND ETC.

     THIS APPEAL, COMING ON FOR HEARING ON
INTERLOCUTORY APPLICATION THIS DAY, JUDGMENT WAS
DELIVERED THEREIN AS UNDER:

CORAM:    HON'BLE MRS. JUSTICE ANU SIVARAMAN
          and
          HON'BLE MR. JUSTICE RAJESH RAI K


                   ORAL JUDGMENT

(PER: HON'BLE MRS. JUSTICE ANU SIVARAMAN)

This appeal is filed being aggrieved by the judgment

dated 12.09.2024 passed by the LXXXV Additional City

Civil and Sessions Judge, Bengaluru (Commercial Court) in

Com.A.P.No.26/2024.

2. We have heard Smt. Shwetha Krishnappa,

learned Additional Government Advocate appearing for the

appellant and Smt. Vani. H, learned counsel appearing for

the respondent.

3. When the matter was taken up for hearing

today, the learned counsel appearing for the respondent

submits that the issues raised in this Commercial Appeal

NC: 2025:KHC:36371-DB

HC-KAR

have already been considered by a co-ordinate Bench of

this Court in Commercial Appeal No.133/2025 and the

appeal has been dismissed by judgment dated

30.07.2025. The copy of the judgment is placed before us.

4. The learned Additional Government Advocate

appearing for the appellant however contended that the

additional grounds have been raised in this appeal and

that the grant of interest by the Arbitral Tribunal at the

rate of 12% per annum is completely excessive and is not

informed by any reasons. It is further contended that the

Price Adjustment Clause had been specifically deleted from

the notified contract and the e-portal had also specifically

contained a note that the said clause stands deleted. It is

therefore contended that the finding of the Arbitral

Tribunal that the claimant was entitled to pay Price

Adjustment was untenable.

5. We have considered the contentions advanced.

We have also perused the appeal and the grounds raised

NC: 2025:KHC:36371-DB

HC-KAR

therein. We notice that the specific contention raised in

the appeal is to the effect that the provision for price

escalation had been omitted from the award and that the

Arbitral Tribunal erred in awarding the claim as sought for.

It is further contended that though this aspect had been

specifically raised before the Commercial Court, the

contentions of the appellant were not properly considered.

Further, this appeal raises the question of award of

interest. It is contended that the award of interest at 12%

per annum by the learned Arbitrator was without any

discussion on the point and was therefore patently illegal.

It is submitted that though this aspect was specifically

raised before the Court, the said aspect has not been

considered at all.

6. Having considered the contentions advanced on

either side, we notice that the question with regard to

existence or otherwise of the Price Adjustment Clause and

the effect of a note in the e-portal regarding its deletion

has been considered by this Court in Commercial Appeal

NC: 2025:KHC:36371-DB

HC-KAR

No.133/2025. This Court found that the finding of fact by

the Tribunal that the contract entered into between the

parties contained the price variation clause at clause

No.39 is, undisputed. It was therefore found that the

finding of the Arbitral Tribunal that the respondent was

entitled to the amount claimed on the basis of the price

variation clause, could not have been interfered with by

the Commercial Court exercising its limited powers under

Section 34 of the Arbitration and Conciliation Act, 1996.

7. In the instant case also, it is an admitted fact

that the contract signed between the parties contained the

price variation clause. This aspect has been specifically

considered by the learned Arbitrator. Further, with regard

to payment of interest, the learned Arbitrator found that

the contract in question provided for interest on delayed

payments. Having found that the claimant was entitled to

an amount of Rs.1,36,57,304/- towards price variation,

the learned Arbitrator also found that there was a delay of

1350 days in making the payment deducting 60 days as

NC: 2025:KHC:36371-DB

HC-KAR

the period for processing and releasing payments, interest

at 12% per annum was awarded for the amount found to

be payable.

8. Having considered the contentions advanced,

we find that the learned Arbitrator had considered the

provisions of the contract and had found it fit to award

interest at the rate of 12% per annum. The award of

interest was a specific ground of challenge raised by the

appellant before the Commercial Court. The said aspect

was considered as point No.1 in the judgment under

appeal and the Court has come to the conclusion that the

award of interest by the sole Arbitrator cannot be

interfered with. Further, all other contentions raised stand

covered by the judgment in Commercial Appeal

No.133/2025. We find no reason to interfere in the

judgment of the Commercial Court upholding the award of

the Arbitrator in these proceedings. The appeal therefore

fails and is accordingly dismissed.

The parties shall suffer their respective costs.

NC: 2025:KHC:36371-DB

HC-KAR

All pending interlocutory applications shall stand

dismissed.

Sd/-

(ANU SIVARAMAN) JUDGE

Sd/-

(RAJESH RAI K) JUDGE

CP

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter